Mansfield and District Crematorium Joint Committee agreed this item on Monday 24 May 2021. Below is the council's own wording, with the papers it was decided on.
AGREED that: i) members approve the setting up of Officer Meetings to discuss further details of works at the crematorium to then share all this information with their respective Members. This allows works to progress more quickly rather than waiting for Member meetings to take place throughout the year; and ii) the committee approve a further budget for associated works as described in section 4 of the update on MAE.
Word for word from the decision Newark and Sherwood published for this meeting.Source: democracy.newark-sherwooddc.gov.uk
Report to Mansfield and District Crematorium Joint Committee
Summary
1.1This report provides an update to the committee on the provision of the new Abatement Equipment (MAE) and other capital projects at the crematorium including plans for major refurbishment works of all public and staff areas. This report is to be read in conjunction with the exempt report attached to this agenda.
Recommendations
2.1That members approve the setting up of Officer Meetings to discuss further details of works at the crematorium to then share all this information with their respective members. This allows works to progress quicker rather than waiting for member meetings to take place throughout the year.
2.2That the Committee approve further budget for associated works as described in section 4 of the update on MAE.
Background
3.1A report was received by the JCC on 7 September 2020 providing an update on the replacement MAE. There was a request to increase the budget from £627,000, the cost for MAE design, manufacture, delivery, installation and commissioning, to allow for works over and above that will arise from the main works.
3.2The Committee agreed that the budget should not be increased until such time as it was possible to get quotes for the additional Builders accommodation works. The accommodation works when approved will be funded from capital reserves.
3.3Members were also advised on 24 February 2020 that the order had been placed with Matthews reiterating the need to ensure compatibility with the cremators. (Attached is the procurement report sent to members explaining the procurement process as asked for as appendix 3).
3.4They have now reviewed the programme of work and assessed their resource capacity. In doing so, they have considered the fact that any substantial work on the roof area needs to be completed by the end of April due to the presence of bats. It is their view therefore that they should only start work if there is no risk of the works running beyond that time. Given that they have had two closures due to Covid-19 they have anticipated some lost time due to the pandemic either from their operations or their supply chain.
1 3.5 Based on this assessment they believe that they would not be able to be in a position to have the majority of the noisy/heavy work on the roof completed by the end of April 2021 and therefore would have to stop work and not be able re-commence work until October 2021 to comply with the restriction due to the bats. This would result in them leaving the site for five months in a state of partial construction and also having their site compound including welfare facilities etc being there for an extended period.
3.6To avoid such disruption Matthews have issued a revised programme. Whilst this is not desirable, given the amount of disruption experienced to date and the potential for further disruption, it is a sensible approach to scheduling the works and not exposing the Crematorium to any risk of part completed works or non-compliance with the European Protected Species Licence should the work overrun into May 2021.
3.7The key milestones within the revised programme are as follows
1. Detail design development – commence 1 March 2021 - COMMENCED 2. Procurement lead time of major equipment – commence 29 March 2021 - COMMENCED 3. Site setup and removal of existing plant – 6 August 2021 – 26 September 2021 4. Plant installation – 4 September 2021 – 16 December 2021 5. Electrical installation – 21 December 2021 – 14 February 2022 6. Testing and Commissioning – 24 January 2022 – 14 March 2022 7. Completion and site handover – 14 March 2022 – 6 April 2022
It is anticipated that details of the work and possible prices will be provided at the committee meeting scheduled for as soon as possible.
4. UPDATE ON MAE
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Mansfield and District Crematorium Joint Committee at Newark and Sherwood and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.