Capital Works Programme Report

Agreed Committee 4 papers

Mansfield and District Crematorium Joint Committee agreed this item on Monday 24 May 2021. Below is the council's own wording, with the papers it was decided on.

Item8

Resolved

AGREED that: i) members approve the setting up of Officer Meetings to discuss further details of works at the crematorium to then share all this information with their respective Members. This allows works to progress more quickly rather than waiting for Member meetings to take place throughout the year; and ii) the committee approve a further budget for associated works as described in section 4 of the update on MAE.
Word for word from the decision Newark and Sherwood published for this meeting. Source: democracy.newark-sherwooddc.gov.uk

Follow this further

Built from Newark and Sherwood's papers

What the report saysPro

Report to Mansfield and District Crematorium Joint Committee

Summary

1.1This report provides an update to the committee on the provision of the new Abatement Equipment (MAE) and other capital projects at the crematorium including plans for major refurbishment works of all public and staff areas. This report is to be read in conjunction with the exempt report attached to this agenda.

Recommendations

2.1That members approve the setting up of Officer Meetings to discuss further details of works at the crematorium to then share all this information with their respective members. This allows works to progress quicker rather than waiting for member meetings to take place throughout the year.

2.2That the Committee approve further budget for associated works as described in section 4 of the update on MAE.

Background

3.1A report was received by the JCC on 7 September 2020 providing an update on the replacement MAE. There was a request to increase the budget from £627,000, the cost for MAE design, manufacture, delivery, installation and commissioning, to allow for works over and above that will arise from the main works.

3.2The Committee agreed that the budget should not be increased until such time as it was possible to get quotes for the additional Builders accommodation works. The accommodation works when approved will be funded from capital reserves.

3.3Members were also advised on 24 February 2020 that the order had been placed with Matthews reiterating the need to ensure compatibility with the cremators. (Attached is the procurement report sent to members explaining the procurement process as asked for as appendix 3).

3.4They have now reviewed the programme of work and assessed their resource capacity. In doing so, they have considered the fact that any substantial work on the roof area needs to be completed by the end of April due to the presence of bats. It is their view therefore that they should only start work if there is no risk of the works running beyond that time. Given that they have had two closures due to Covid-19 they have anticipated some lost time due to the pandemic either from their operations or their supply chain.

1 3.5 Based on this assessment they believe that they would not be able to be in a position to have the majority of the noisy/heavy work on the roof completed by the end of April 2021 and therefore would have to stop work and not be able re-commence work until October 2021 to comply with the restriction due to the bats. This would result in them leaving the site for five months in a state of partial construction and also having their site compound including welfare facilities etc being there for an extended period.

3.6To avoid such disruption Matthews have issued a revised programme. Whilst this is not desirable, given the amount of disruption experienced to date and the potential for further disruption, it is a sensible approach to scheduling the works and not exposing the Crematorium to any risk of part completed works or non-compliance with the European Protected Species Licence should the work overrun into May 2021.

3.7The key milestones within the revised programme are as follows

1. Detail design development – commence 1 March 2021 - COMMENCED 2. Procurement lead time of major equipment – commence 29 March 2021 - COMMENCED 3. Site setup and removal of existing plant – 6 August 2021 – 26 September 2021 4. Plant installation – 4 September 2021 – 16 December 2021 5. Electrical installation – 21 December 2021 – 14 February 2022 6. Testing and Commissioning – 24 January 2022 – 14 March 2022 7. Completion and site handover – 14 March 2022 – 6 April 2022

It is anticipated that details of the work and possible prices will be provided at the committee meeting scheduled for as soon as possible.

4. UPDATE ON MAE

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Works Programme ReportReport 346 KB DownloadRead as text
PDF
Item 8a Refubishment: Provisional schedule of items: April 2020Report 27 KB Download
PDF
Item 8b REVISED PROGRAMME 7474 PL001rev2 Mansfield CrematoriumReport 277 KB Download
PDF
Item 8c 2021-02-22 MAE Procurement ReportReport 346 KB Download

At this meeting

Whole meeting

Who was there

7 of 14 attended
DM
Councillor David MartinCommittee Member, apologies
TH
Councillor Tom HollisVice-Chair, present
MH
Councillor Mrs Helen-Ann SmithCommittee Member, present
MA
Mayor Andrew AbrahamsCommittee Member, apologies, sent representative
AB
Councillor Andy BurginChairman, present
SR
Councillor Stuart RichardsonCommittee Member, present
ML
Councillor Mrs Lydia HurstCommittee Member, present
TS
Councillor Tom SmithCommittee Member, present
EA
Eve AllsopOfficer, expected
LS
Lisa SimpsonOfficer, expected
CB
Craig BonarOfficer, expected
WG
Wendy GregsonOfficer, expected

All 14 on the meeting page

More from Newark and Sherwood Mansfield and District Crematorium Joint Committee

All decisions
MeetingDecisionOutcome
23 Feb 2026 Operations ReportAGREED (with 6 votes for and 1 abstention) that: i) the committee approve the replacement of the existing crematorium... Agreed Open
23 Feb 2026 Financial Management Review April-December 2025AGREED (unanimously) that the financial information provided in Appendix 1 and Table 1 in the report be noted. Agreed Open
23 Feb 2026 Annual Review of Fees and Charges for 2026/27AGREED (unanimously) that: i) the proposed cremation fee as shown in Table 2 for the period 1 April 2026 to 31 March ... Agreed Open
23 Feb 2026 Revenue and Capital Budget 2026/27 - 2028/29AGREED (unanimously) that: i) the proposed revenue and capital budgets for 2026/27 be approved, as per Appendix 1; ii... Agreed Open
23 Feb 2026 Crematorium Development ReportAGREED (unanimously) that the Committee noted the report. Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies