Mansfield and District Crematorium Joint Committee, Monday 23 February 2026 at 10.00am

Operations Report

Agreed Committee 3 papers

AI summaryJoint crematorium committee approves £52,572 software replacement over five years, with £21,372.50 in year one, funded from existing budgets.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedReplace crematorium software and note the report
Money£52,572 over five years£21,372.50 in year one plus annual support fees
What happens nextNew supplier, current contract expires September 2026Move to a different provider after market testing
Who it affectsCrematorium and Mansfield DC cemeteriesCost shared; funeral directors and bereaved families affected

What was decided

The committee approved replacement of the existing crematorium software at £52,572 over five years, with £21,372.50 in year one and the annual support subscription costs in subsequent years, financed from existing budgets.

The committee also noted the wider operations report covering cremator maintenance, building repairs, grounds, soil, charity engagement and digital platforms. Report P1

Why

The existing BACAS software is around 25 years old, not cloud based, and does not integrate well with Civica or Govmail systems. Report 2.28

The current supplier, Clear Skies, has been bought out, prompting market testing and a switch to a different provider with additional modules. Report 2.27, 2.28

Officers say the new system will allow funeral directors to book online, map cemetery memorials digitally, and reduce administrative workload. Report 2.29, P32

What happens next

Procure the replacement software, with an annual support subscription of £7,800 in subsequent years and £7,875 from the new provider in the next contract period.

Continue cremator maintenance: spend the previously approved £60k on cremator 4's hearth and flu box and review the brickwork of cremator 2, which may lead to decommissioning discussions. Report 2.2, 2.3

Repair the chimney stack within six months, subject to amending the bat roost licence and bat monitoring managed by MDC Design Services. Report 2.6, 2.7, 2.8

The money

  • £52,572 Total cost of crematorium software replacement over five years
  • £21,372.50 Initial set up cost for the crematorium element in year one
  • £7,800 Annual support subscription cost in subsequent years
  • £7,875 Annual cost to the crematorium from the new BACAS provider in the next contract period
  • £60k Previously approved additional spend on cremator 4 hearth and flu box Report 2.2

Options considered

  • Chosen: Replace the existing BACAS system with a new supplier offering additional modules. Current system is 25 years old, not cloud based, and does not integrate with Civica or Govmail; supplier Clear Skies has been bought out Report 2.27, 2.28
  • Rejected: Continue with the existing BACAS system and invest in upgrades. Would not deliver the integration, online booking and digital mapping benefits needed Report 2.28, 2.29

Implications

  • Financial: All costs to be financed from existing budgets; annual subscription to be paid in subsequent years.
  • Other: Funeral director bookings currently make up 75% of incoming calls; online booking should reduce administrative phone time. Report 2.29, P32
  • Risk: Cremator 2 brickwork integrity is under review and any required reline may lead to decommissioning discussions. Report 2.3
  • Other: Chimney stack repairs must be completed within six months; works are on hold pending amendment to the bat roost licence. Report 2.6, 2.7, 2.8

Who and where

  • Mansfield and District Crematorium service users and bereaved families Report 2.36, 2.38
  • Funeral directors, who will be able to book services online Report 2.29, P32
  • Crematorium and Mansfield District Council cemeteries staff, who will use the new system Report 2.27, 2.28
  • Local and national bereavement charities, covered by a new engagement strategy Report 2.21, 2.22, 2.23

Timeline

  • Week commencing 16th February: Cremator 4 hearth and flu box work scheduled Report 2.2
  • Within six months: Chimney stack repairs to be completed, subject to bat licence amendment Report 2.8
  • September 2026: Current annual BACAS contract expires
  • 26/27 financial year: Further tree works planned in line with permitted felling amounts Report 2.10

Plain English for the jargon

  • BACAS: The crematorium and cemeteries management software currently used, around 25 years old
  • Civica: The council's existing internal finance system
  • MDC: Mansfield District Council, partner authority in the joint crematorium committee
  • ADC: Ashfield District Council, currently hosting the crematorium website which is being transferred to MDC
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item14

Resolved

AGREED (with 6 votes for and 1 abstention) that: i) the committee approve the replacement of the existing crematorium software £52,572 over five years; £ 21,372.50 in year one and the annual support subscription costs, in subsequent years, to be financed from existing budgets; and ii) the committee note the report.
Word for word from the decision Newark and Sherwood published for this meeting. Source: democracy.newark-sherwooddc.gov.uk

Follow this further

Built from Newark and Sherwood's papers

What the report saysPro

Report to Mansfield and District Crematorium Joint Committee

Background

The previous report was presented to the committee in September 2025. This report provides the committee with an update on the crematorium operation since then.

2.0Proposal/Options Considered and Reasons for Recommendation

2.1Cremator and Ancillary Equipment

2.2Winter servicing has been completed on the cremators, and this has identified the following concerns:

2.2Cremator number 4 – The blast tube and a small number of tiles have been replaced which has provided a temporary repair. It is anticipated that the additional approved spend of up to £60k, approved at the previous meeting, will be spent on the heath and the flu box. This work is being completed week commencing 16th February.

2.3Cremator numbers 2 – The rake door keeps coming loose however we have spares available to repair this. Issues have been identified with the integrity of the brickwork which is being reviewed. Any required reline may render conversations that will determine the decommissioning of the cremator.

2.4Number 3 cremator is operating as expected with no issues

2.5Building Maintenance and Repair

2.6The identified crack in the chimney stack that requires repair is still on hold due to the bat roosts. While ongoing monitoring of the roosts is required an amendment to the license is required prior to any works being carried out. The amendments to the licence are underway.

2.7Bearing in mind the health and safety concerns, a referral has been made to building control to firstly provide confidence that there are no immediate concerns of collapse and secondly that advise sought may support the license for works to be carried out.

2.8While there was no immediate concern for collapse identified we are advised that the stack works need to be remedied within a six-month period. Appointment of an appropriate contractor and the associated bat monitoring is being managed through MDC Design Services team.

2.9Grounds Maintenance

2.10Tree work detailed in the operations report from September ’25 has now been completed with further tree works planned for the 26/27 financial year. This is in line with the new financial year but also to support permitted felling amounts per quarter.

2.11The further tree work is required for tree management and to overcome challenges with tree cover effecting the growth of grass and shrubs.

2.12Soil Management

2.13At the meeting in September members were made aware of concerns with the soil quality within the crematorium grounds and the impact that this was having on the growth of memorial plants, shrubs and grass.

2.14Issues have been identified specifically in areas where cremated remains are scattered due to the ashes being very high in salts, high in pH (alkaline), low in organic matter, low in nutrients usable by plants and are mostly calcium phosphate and minerals. Because of this, adding cremated remains directly to soil can harm or stunt plants unless it is handled appropriately.

2.15The negative effects on soil & plants are that high salt levels can dehydrate roots, and a high pH can prevent nutrient uptake. Low organic material also means that soil structures are not improved.

2.16Effectively diluted or treated remains can be included into soil safely and incorporated as part of memorial planting

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Charity Engagement StrategyAppendix 1 130 KB Download
PDF
Digital ImprovementAppendix 3 64 KB Download
PDF
Operations ReportReport 162 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 11 attended
TH
Councillor Tom HollisCommittee Member, present
CH
Councillor Chris HuskinsonCommittee Member, present
MH
Councillor Mrs Helen-Ann SmithCommittee Member, present
AB
Councillor Andy BurginVice-Chair, present
CH
Councillor Charles HammersleyCommittee Member, present
CW
Councillor Craig WhitbyCommittee Member, present
LB
Councillor Lee BrazierCommittee Member, apologies
SC
Councillor Susan CrosbyCommittee Member, apologies
PP
Councillor Paul PeacockChair, present
NH
Nigel HillClerk, expected
KL
Karen LangfordSecretary, expected

On this subject at Newark and Sherwood

Search all
  1. Operations ReportThis decision
  2. Operations ReportAgreed
  3. Operations ReportAgreed
  4. Operations ReportAgreed
  5. Operations ReportAgreed
  6. Operations ReportAgreed

More from Newark and Sherwood Mansfield and District Crematorium Joint Committee

All decisions
MeetingDecisionOutcome
23 Feb 2026 Financial Management Review April-December 2025AGREED (unanimously) that the financial information provided in Appendix 1 and Table 1 in the report be noted. Agreed Open
23 Feb 2026 Annual Review of Fees and Charges for 2026/27AGREED (unanimously) that: i) the proposed cremation fee as shown in Table 2 for the period 1 April 2026 to 31 March ... Agreed Open
23 Feb 2026 Revenue and Capital Budget 2026/27 - 2028/29AGREED (unanimously) that: i) the proposed revenue and capital budgets for 2026/27 be approved, as per Appendix 1; ii... Agreed Open
23 Feb 2026 Crematorium Development ReportAGREED (unanimously) that the Committee noted the report. Agreed Open
23 Feb 2026 Committee Work ProgrammeAGREED that Members note the . Agreed Open