AGREED t hat Cabinet: a) approve an additional £100k be added to this year’s budget funding from the HRA Newark and Sherwood Homes Merger Transfer reserves; and b) note that any additional funding will be included in 2023/24 budget setting process.
Word for word from the decision Newark and Sherwood published for this meeting.Source: democracy.newark-sherwooddc.gov.uk
1.1Through the pandemic, the Council restricted its repairs service to cover emergencies and some external planned works. All appointed repairs were held until restrictions and risk assessments allowed a return to normal arrangements. This resulted in around 800 repairs in the system which have been caught up within existing resources. However, combined with an increase in demand and a reduced resource to service them due to challenges with recruitment, this has then created a further high number of newer repairs outstanding. 1.2. Capita shows the service is experiencing an increase in the number of repairs reported, possibly as people report more repairs now they feel able to allow access.
1.3Number of repair orders in and completed repairs by month:
1.4Over the past 12 months we have had approximately 10 vacancies for our trade posts which have been extremely difficult to recruit to. This has had an impact on the number of repairs being completed each month. We currently have 5 vacancies: 2 Electricians, 1 Joiner, 1 Plumber and 1 Builder/Plasterer.
1.5Up to now, we did not have the relevant information to monitor operative performance easily available to enable us to challenge and improve performance (number of repairs completed and number of follow-ons per operative) as the systems do not enable us to do this automatically.
1.6The current repairs workload cannot be reduced on current resources alone. Manual processes are being putting in place to record operative performance on follow-ons and number of jobs completed by each operative. This will allow us to challenge and improve operative performance resulting in higher numbers of repairs completed and reducing follow-ons. This will help prevent future issues.
1.7Below is the current list of works, broken down to trade, category, cost. Table 1 below shows outstanding jobs in system with current assigned costs. Those jobs highlighted in yellow are priority works. Table 2 adjusts these costs to provide a more accurate figure for the works to be completed by a contractor and allows for any materials cost increase.
Budget Performance Report Quarter 1That Cabinet: (a) note the General Fund projected unfavourable outturn variance of £0.665m; (b) note the Housing Reve...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.