AI summaryCabinet notes £0.665m General Fund and £1.112m HRA projected budget shortfalls and approves revised Capital Programme of £73.110m, with reserves available to cover the variances.
Written from the decision and the officer reportPDF Pro
OutcomeNoted
Money£73.110m capital budget
What happens nextMonitoring and reserve cover
Who it affectsGeneral Fund and HRA services
What was decided
Noted the General Fund projected unfavourable outturn variance of £0.665m
Noted the Housing Revenue Account projected unfavourable outturn variance of £1.112m to the Major Repairs Reserve
Approved the variations to the Capital Programme at Appendix C and the revised budget and financing of £73.110m
Noted the Prudential indicators at Appendix F showing full compliance with all indicators Report 1.19
Why
An unfavourable variance of £1.530m is currently being projected on service budgets representing 7.04% of total service budgets. Recruitment challenges have impacted vacancy savings, with the vacancy factor provision set at 7.5% for 2026/27 based on an 8.4% vacancy rate in 2024/25. Report 1.2
What happens next
Budget managers will continue to monitor vacancy levels and associated savings on a regular basis and report further updates in subsequent quarterly monitoring reports. Report 1.4
The projected position will continue to be monitored throughout the year with further updates reported to Cabinet in subsequent quarterly monitoring reports. Report 1.11, 2.2
The money
£0.665m General Fund projected unfavourable outturn variance (unfavourable) Report 1.1, P5
£1.112m HRA projected unfavourable variance to Major Repairs Reserve (unfavourable) Report 1.9, P16
£73.110m Revised Capital Programme budget and financing Report 1.13, P21
£1.530m Service budgets projected unfavourable variance Report 1.1, P5
£0.360m Additional anticipated surplus from renewable energy properties in business rates Report 1.5
Options considered
Chosen: Note the projected variances and approve capital programme variations. The report recommends this course of action in accordance with the Council's Constitution to show performance against approved estimates, report major variances, and approve capital programme variations. Report 2.1, 2.2
Implications
Financial: General Fund projected to draw £0.665m from reserves. HRA projected to reduce transfer to Major Repairs Reserve by £1.112m. Sufficient reserves are available to cover both variances. Capital programme revised to £73.110m. Report 1.1, 1.9, 1.13
Risk: Significant recruitment challenges continue across the council and the local government sector. Vacancy savings target of £1.768m may not be fully achieved. Report 1.4
Financial: Additional investment income of £0.190m and Arkwood income overachievement of £0.110m partially offset other variances. Report 1.6
Capital Programme schemes (General Fund and HRA) Report 1.11
Council taxpayers and business rates payers Report 1.5
Timeline
4 March 2026: Treasury Management Strategy, Capital Strategy and Investment Strategy approved by Audit and Accounts Committee Report 1.18
5 March 2026: Treasury Management Strategy, Capital Strategy and Investment Strategy approved by Full Council Report 1.18
30 June 2026: Current position date for Q1 monitoring Report P2
July 2026: Budget Manager meetings to analyse actual income and expenditure and forecast to March 2027 Report 1.1
21 July 2026: Capital Programme slippage reported to Cabinet Report 1.7, 1.12
31 March 2027: End of 2026/27 financial year Report 1.1
Plain English for the jargon
MRP: Minimum Revenue Provision - a charge to the revenue account to provide for the repayment of debt capital expenditure
NNDR: National Non-Domestic Rates, also known as Business Rates
HRA: Housing Revenue Account - accounts for the income and expenditure relating to the council's housing stock
Major Repairs Reserve: Reserve ring-fenced for HRA capital expenditure on housing stock
Capital Receipts: Income from the sale of capital assets that can be used to fund new capital expenditure
Vacancy Factor: Budget provision for savings expected from posts vacant during the year
Prudential Indicators: Metrics set to ensure borrowing remains affordable and sustainable
MTFP: Medium Term Financial Plan - financial planning covering multiple years
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6
Resolved
That Cabinet: (a) note the General Fund projected unfavourable outturn variance of £0.665m; (b) note the Housing Revenue Account projected unfavourable outturn variance of £1.112m to the Major Repairs Reserve; (c) approve the variations to the Capital Programme at Appendix C; (d) approve the Capital Programme revised budget and financing of £73.110m; and (e) note the Prudential indicators at Appendix F.
Word for word from the decision Newark and Sherwood published for this meeting.Source: democracy.newark-sherwooddc.gov.uk
Overview of General Fund Revenue Projected Outturn for 2026/27
Current position (as at 30 June 2026): variances
1.1Table 1 shows a projected unfavourable variance against the revised budget of £1.530m on Service budgets, with an overall unfavourable variance of £0.665m that would need to be transferred from the General Fund reserve, based on the current forecast outturn position, sufficient reserves are available to cover this variance if required. This is based on meetings which took place with Budget Managers during July, whereby they have analysed actual income and expenditure to 30th June 2026 and forecasted forward to the end of March 2027 the additional income and expenditure currently expected to be incurred. Further details of the variances projected against portfolio holder budgets are in Appendix A.
Table 1: General Fund revenue outturn for 2026/27 financial year as at 30 June 2026
Original Revised Projected Variance Budget Budget Outturn £'m £’m £'m £'m Climate and the Environment 3.445 3.515 3.588 0.073 Corporate Services 3.459 3.617 3.584 (0.033) Health, Wellbeing and Leisure 0.486 0.580 0.559 (0.021) Heritage, Culture and the Arts 0.765 0.837 0.833 (0.004) Housing 0.325 0.410 0.510 0.100 Public Protection and Community Relations 4.190 4.305 4.262 (0.043) Strategy, Performance and Finance 7.778 8.234 8.064 (0.170) Sustainable Economic Development 2.198 2.259 1.869 (0.390) Vacancy Factor & Savings (2.018) (2.018) 0.000 2.018 Net Cost of Services 20.628 21.739 23.269 1.530 Other Operating Expenditure 5.386 5.386 5.386 0.000 Finance & Investment Income/Expenditure (1.796) (1.796) (2.129) (0.333) Taxation & Non-Specific Grant Income (26.064) (26.064) (26.428) (0.364) Net Cost of Council Expenditure (1.846) (0.735) 0.098 0.833 Transfer to/(from) Usable Reserves 0.739 (0.437) (0.437) 0.000 Transfer to/(from) Unusable Reserves 1.107 1.172 1.004 (0.168) Transfer to/(from) General Reserves 0.000 0.000 (0.665) (0.665)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Options Appraisal - 14 & 14a MillgateThat Cabinet: a) approve the proposal as set out in Option 2 – the sale of the property; b) approve the progression o...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.