Resolved
AGREED (unanimously) that: i) the financial information provided in Table 1 and Appendix 1 was for noting only.
Mansfield and District Crematorium Joint Committee agreed this item on Monday 24 February 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
AGREED (unanimously) that: i) the financial information provided in Table 1 and Appendix 1 was for noting only.
1.1Summary forecast financial position as at 31 December 2024 for revenue and capital budgets, see appendix 1.
Table 1 below summarises the income and expenditure incurred to 31 December 2024 and the variances to revised budgets expected at the financial year end. Explanations are provided where there are significant variances between the forecasted out-turn position and the revised budgets. Table 1- Crematorium Revenue and Capital
1 April 2024 to CREMATORIUM REVENUE 31 December 2024 Variance - Current Forecast to Description Forecast Actuals Budget Revised Budget Employee Costs 476,405 424,553 -51,852 299,865 Premises Related Expenses 603,208 572,706 -30,502 300,150 Supplies and Services 196,999 227,249 30,250 111,588 Support Services 80,574 80,574 0 346 Depreciation & Impairment 129,265 129,265 0 0 Capital Charges 120,000 0 -120,000 0 Revenue Gross Expenditure 1,606,451 1,434,347 -172,104 711,949 Revenue Income -2,290,850 -1,996,832 294,018 -1,440,788 Income -2,290,850 -1,996,832 294,018 -1,440,788 Recharge to Cemeteries -32,210 -32,210 0 0 Income Recharges -32,210 -32,210 0 0 Revenue Gross Income -2,323,060 -2,029,042 294,018 -1,440,788 Net Cost of Service -716,609 -594,695 121,914 -728,839 Depreciation to be Reversed -129,265 -129,265 0 0 Contribution from/to General Reserve -29,126 0 29,126 0 Below Net Cost of Service -158,391 -129,265 29,126 0 Net (-) Surplus -875,000 -723,960 151,040 -728,839
1 April 2024 to CREMATORIUM CAPITAL 31 December 2024 Variance - Current Forecast to Description Forecast Actuals Budget Revised Budget Crem Capital Unallocated - Hired Contracted Services 24,000 24,000 0 0 Crem Cap New Dev Crematorium SSRS - Design Services 6,985 6,985 0 0 Capital Gross Expenditure 30,985 30,985 0 0
1.1.1 Employee Expenses total forecasted variance -£51,852.
There has been a reduction to employee expenses due to vacancies in the Clerical Assistant and Gardener/Relief Technician posts, resulting in savings on salaries, national insurance and superannuation payments.
1.1.2 Premises Expenses total forecasted variance -£30,502.
Forecast for premises expenses has decreased for Electricity and Gas costs due to a reduction in price per kWh and price per unit for usage.
1.1.3 Supplies and Services total for forecasted variance £30,250.
Increases to forecasted spend on webcasting from £15,000 to £45,000 due to increased demand for the service. There is also a forecasted increased spend of £6,000 on CAMEO Non-Abatement Fees based on supplier price increase.
These increases have been partially offset by savings on advertising of £1,300 and printing and stationary of £1,000.
There has also been a reduction to Medical Referee Fees due to a lower number of cremations taking place, which is reflected in a drop in income.
1.1.4 Capital Charges total forecasted variance -£120,000
Capital Charges are not expected to begin in 24/25 in relation to the New Development, due to a delay on a decision being taken.
1.1.5 Income total forecasted variance £294,018.
Forecast for cremation fees has decreased by £387,600 due to a reduced throughput estimate, from 2,200 to 1,800 cremations. Memorial fee income has also decreased by £22,700 due to less interest and less cremations taking place.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Financial Management Review April-December 2024Report | 718 KB | DownloadRead as text |
Follow Mansfield and District Crematorium Joint Committee at Newark and Sherwood and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Feb 2026 | Operations ReportAGREED (with 6 votes for and 1 abstention) that: i) the committee approve the replacement of the existing crematorium... | Agreed | Open |
| 23 Feb 2026 | Financial Management Review April-December 2025AGREED (unanimously) that the financial information provided in Appendix 1 and Table 1 in the report be noted. | Agreed | Open |
| 23 Feb 2026 | Annual Review of Fees and Charges for 2026/27AGREED (unanimously) that: i) the proposed cremation fee as shown in Table 2 for the period 1 April 2026 to 31 March ... | Agreed | Open |
| 23 Feb 2026 | Revenue and Capital Budget 2026/27 - 2028/29AGREED (unanimously) that: i) the proposed revenue and capital budgets for 2026/27 be approved, as per Appendix 1; ii... | Agreed | Open |
| 23 Feb 2026 | Crematorium Development ReportAGREED (unanimously) that the Committee noted the report. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.