Plan for Neighbourhoods Programme and Local Assurance Framework Update (Key Decision)

Noted Executive 4 papers

AI summaryCabinet endorsed the Newark Town Board's Pride in Place Programme Regeneration Plan for UK Government submission and approved £1,502,000 revenue and £5,306,000 capital budgets for 2026-2030, subject to a finalised funding Memorandum of Understanding.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedRegeneration Plan and Local Assurance Framework approved
MoneyNot stated
What happens nextSubmit Regeneration Plan by 28 November 2025Plan to be sent to UK Government, subject to MoU
Who it affectsNewark residents, businesses, communities10-year programme to 2036, led by Newark Town Board

What was decided

Cabinet noted the Pride in Place Programme name change and the role of the Newark Town Board, and endorsed the board's Regeneration Plan, comprising a 10-year vision and four-year indicative investment profile, for submission to the UK Government by 28 November 2025. Report P3, P4, P15

Cabinet approved a revenue budget of £1,502,000 and a capital budget of £5,306,000 for the first four years of PiPP delivery (2026 to 2030), with individual financial commitments to be approved by the Newark Town Board and the Section 151 Officer.

Cabinet approved the proposed Newark Town Board Local Assurance Framework, subject to the council receiving sufficient assurance of funding through a finalised Memorandum of Understanding from the UK Government, to be approved by the Section 151 Officer.

Why

The recommendations are needed to enable the Newark Town Board to oversee and deliver the Pride in Place Programme over the next decade, with the Local Assurance Framework clearly defining roles and processes to be followed throughout delivery. Report P3, P4

The governance and funding arrangements are set by the UK Government through the Pride in Place Programme prospectus, with the council acting as the Accountable Body and the Newark Town Board as the strategic decision maker. Report P3, P15, P16

Up to £19.5m of funding will be available to Newark over 10 years from April 2026, with Newark selected as one of 10 East Midlands areas in the initial 75-place tranche announced in March 2025. Report P3, P13, P60

What happens next

The Regeneration Plan is to be submitted to the UK Government by 28 November 2025, subject to Newark Town Board and Section 151 Officer approval.

A finalised Memorandum of Understanding from the UK Government is required before the revenue and capital budgets are confirmed, with the Section 151 Officer to approve it.

Programme delivery commences in April 2026, with the first four-year period running to 2030, overseen by the Newark Town Board working with the council as Accountable Body. Report P13, P15

The money

  • £1,502,000 Revenue budget approved for first four years of PiPP delivery (2026 to 2030)
  • £5,306,000 Capital budget approved for first four years of PiPP delivery (2026 to 2030)
  • £19.5m Maximum funding available to Newark through PiPP over 10 years Report P3, P13
  • £1.5 billion Initial Pride in Place Programme funding announced in March 2025 Report P3, P13
  • £5 billion Total PiPP value after second tranche of 169 communities added in September 2025 Report P3, P13
  • £25m Previous UK Government award to Newark in 2020 through the Local Regeneration Fund (Towns Deal) Report P4, P16, P39
  • £20m UK Government Levelling Up Funding awarded for the Newark Southern Link Road Report P47, P68

Options considered

  • Chosen: Endorse the Newark Town Board's PiPP Regeneration Plan, approve the £1,502,000 revenue and £5,306,000 capital budgets, and approve the Local Assurance Framework. Necessary to enable the Newark Town Board to oversee and deliver the PiPP over the next decade and to allow submission to the UK Government by 28 November 2025.
  • Rejected: Reject or amend the recommendations. The governance and funding arrangements are set by the UK Government through the PiPP prospectus, with the council as Accountable Body and the Newark Town Board as strategic decision maker.

Implications

  • Legal: The council acts as the Accountable Body for PiPP funding, with compliance of all funding-related decisions to be monitored in line with the Memorandum of Understanding and the Local Assurance Framework. Report P3, P4
  • Risk: Both budgets remain subject to the council receiving sufficient assurance of funding through a finalised Memorandum of Understanding from the UK Government.
  • Governance: The Local Assurance Framework clearly defines roles, responsibilities and processes to be followed by the Newark Town Board and the council throughout programme delivery. Report P3
  • Equalities: PiPP aims to tackle deprivation, reduce social exclusion, spread opportunities for young people, improve health and wellbeing, build stronger and more cohesive communities, and reduce crime and anti-social behaviour in left-behind areas. Report P3, P13, P17
  • Other: Up to £19.5m of funding will be available to Newark over the 10-year period commencing April 2026, with the programme based on an iterative community engagement approach. Report P13, P15

Who and where

  • Newark Town Board, as strategic decision maker for local PiPP delivery Report P3, P4
  • Newark and Sherwood District Council, acting as the Accountable Body for PiPP funding Report P3, P4
  • Newark residents, communities and businesses within the agreed PiPP boundary Report P4, P17, P56
  • Local community groups, schools, colleges, charities and under-represented groups involved in engagement Report P77, P4
  • Neighbouring East Midlands authorities participating in PiPP, with whom best practice will be shared Report P60, P61, P62

Timeline

  • March 2025: UK Government announced the initial £1.5 billion Pride in Place Programme, with Newark among 75 places selected Report P3, P13
  • September 2025: A further 169 communities added through a second tranche, bringing total PiPP value to £5 billion Report P3, P13
  • 11 November 2025: Cabinet decision to endorse the Regeneration Plan, approve budgets and approve the Local Assurance Framework
  • 28 November 2025: Deadline for submission of the Regeneration Plan to the UK Government, subject to Board and Section 151 Officer approval
  • 2026 to 2030: First four years of PiPP delivery, with £1,502,000 revenue and £5,306,000 capital budgets
  • April 2026: PiPP funding period commences Report P13
  • 2026 to 2036: 10-year PiPP vision and delivery period for Newark Report P2, P3, P4

Plain English for the jargon

  • PiPP: Pride in Place Programme, the new UK Government name for the Plan for Neighbourhoods initiative
  • LAF: Local Assurance Framework, defining roles and processes for the Newark Town Board and the council
  • MoU: Memorandum of Understanding, to be finalised between the council and the UK Government for PiPP funding
  • MHCLG: Ministry of Housing, Communities and Local Government, the UK Government department overseeing PiPP
  • TIP: Town Investment Plan, the 2020 strategy guiding 30-year regeneration in Newark with £25m of funding
  • LUF: Levelling Up Fund, providing £20m for the Newark Southern Link Road
  • IMD: Index of Multiple Deprivation, ranking areas across seven domains of deprivation
  • LSOA: Lower Super Output Area, a small geographic area used for deprivation statistics
  • BUA: Built-Up Areas, used by MHCLG to define the Newark PiPP boundary
  • NSDC: Newark and Sherwood District Council
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item320

Resolved

That Cabinet: a) note the updates provided in relation to the Plan for Neighbourhoods initiative including the recent name change implemented by the UK Government of the ‘Pride in Place Programme’ (PiPP) and the related role of the Newark Town Board, as set out in section 2.0 of the report; b) note and endorse the Newark Town Board’s PiPP Regeneration Plan for submission to the UK Government by 28 November 2025 (subject to Board and Section 151 Officer approval), comprising a 10-year vision document and four-year indicative investment profile; c) approve the addition of a revenue budget of £1,502,000 and a capital budget of £5,306,000 required for the first four years of the PiPP delivery (2026 to 2030) with individual financial commitments to be approved by the Newark Town Board and the Section 151 Officer. Both budgets remain subject to the Council receiving sufficient assurance of funding through a finalised Memorandum of Understanding (MoU) from the UK Government, to be approved by the Section 151 Officer, as detailed further in paragraphs 2.5 and 2.6 of the report; and d) approve the proposed Newark Town Board Local Assurance Framework (LAF), as provided in Appendix 3 of the report and detailed further in paragraphs 2.12 and 2.13. The recommendations within this report are necessary to enable the local Newark Town Board to oversee and deliver the PiPP over the next decade through the provision of programme budgets. The proposed Local Assurance Framework will support the council to effectively fulfil its assurance role, clearly defining roles and processes to be followed by the Newark Town Board throughout programme delivery. Options Considered: The governance and funding arrangements detailed within this report are set by the UK Government throughout the PiPP prospectus. In particular, the council’s role as the accountable body for programme funding, with the local Newark Town Board considered the strategic decision makers. The recommendations within this report reflect the arrangements and the funding conditions set by MHCLG.
Word for word from the decision Newark and Sherwood published for this meeting. Source: democracy.newark-sherwooddc.gov.uk

Follow this further

Built from Newark and Sherwood's papers

What the report saysPro

Report to Cabinet

PRIDE IN PLACE PROGRAMME

Newark Regeneration Plan 10 - Year Vision (2026 to 2036) November 2025

1 Executive Summary In March 2025, the UK Government announced a £1.5 billion initiative known as the identified for the area alongside potential opportunities for programme investment Pride in Place Programme (PiPP), investing up to £19.5m in an initial 75 places over within Newark, over the next 10 years. This includes a local focus on 5 key investment the next decade. In September 2025, a further 169 communities were added to the themes of: scheme through the announcement of a second tranche of funding, resulting in a total PiPP worth £5 billion. • Regeneration, Heritage and High Streets • Transport/Connectivity The PiPP aims to tackle specific local and national challenges, with a focus on raising • Cohesion living standards, reducing social exclusion, spreading opportunities for young people, • Safety and Security improving health and wellbeing, building stronger and more cohesive communities and • Work, Productivity and Skills reducing crime and anti-social behaviour. Each area was selected by the UK Government based on a combination of metrics including the indices of multiple The board has ensured local PiPP plans complement and enhance other key deprivation and population size, healthy life expectancy, gross value added per hour strategies and investment programmes within the area. Examples include the Newark

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
11.11.25: Plan for Neighbourhoods: Appendix 1Appendix 4.3 MB DownloadRead as text
PDF
11.11.25: Plan for Neighbourhoods: Appendix 2Appendix 148 KB Download
PDF
11.11.25: Plan for Neighbourhoods: Appendix 3Appendix 364 KB Download
PDF
Plan for Neighbourhoods Programme and Local Assurance Framework Update (Key Decision)Decisions 243 KB Download

At this meeting

Whole meeting

Who was there

8 of 19 attended
PP
Councillor Paul PeacockChair, present
RC
Councillor Rowan CozensCommittee Member, present
SC
Councillor Susan CrosbyCommittee Member, present
LB
Councillor Lee BrazierCommittee Member, present
SF
Councillor Simon FordeCommittee Member, present
CP
Councillor Claire PennyCommittee Member, present
PT
Councillor Paul TaylorCommittee Member, present
JK
Councillor Jack KellasCommittee Member, present
NH
Nigel HillSecretary, expected
MF
Matt FinchOfficer, expected
DK
Deborah K JohnsonOfficer, expected
SK
Sanjiv KohliOfficer, expected

All 19 on the meeting page

On this subject at Newark and Sherwood

Search all
  1. Plan for Neighbourhoods Programme and Local Assurance Framework Update (Key Decision)This decision
  2. Plan for Neighbourhoods Update (Key Decision)Agreed

More from Newark and Sherwood Cabinet

All decisions
MeetingDecisionOutcome
15 Sep 2026 Budget Performance Report Quarter 1That Cabinet: (a) note the General Fund projected unfavourable outturn variance of £0.665m; (b) note the Housing Reve... Noted Open
15 Sep 2026 Community Plan Performance Report Quarter 1That Cabinet: a) review the Community Plan Performance Report attached as Appendix 1; b) review the compliance report... Decided Open
15 Sep 2026 Housing Compliance Assurance Report Quarter 1That Cabinet note: a) the exceptions to performance of the housing service compliance functions; b) interim arrangeme... Decided Open
15 Sep 2026 Annual Review of Exempt ItemsThat Cabinet note the report, with any items being released into the public domain if considered no longer being exempt. Noted Open
15 Sep 2026 Progress Towards Net ZeroThat Cabinet: a) notes the Council's 2025/26 corporate emissions position and progress towards the Net Zero 2035 targ... Decided Open