Resolved
That Cabinet approve: a) the additional £13,591,929 to be added to the Capital programme, making a total capital budget of £ 25m; b) the variation to the Facility Agreement to accommodate the power to vary the agreement and the extension to the cap on the facility from £12m to £25m; and c) subject to the subsidy control advice, to delegate responsibility to the Portfolio Holder for Strategy, Performance & Finance to amend the Facility Agreement to ensure the agreement remains subsidy control compliant. To ensure that the Council’s wholly owned company are able to meet their contractual commitments and complete the existing developments. This aligns with Ambition two within the Council’s Community Plan ensuring which has a specific action relating to ‘Develop new homes for open market sale or rent through Arkwood Developments Ltd’. Options Considered: Should the recommendation not be approved, this would impact on Arkwood’s ability to be able to progress the sites they are contractually obliged to complete and would force the company to seek external finance.