Mansfield and District Crematorium Joint Committee agreed this item on Monday 22 September 2025. Below is the council's own wording, with the papers it was decided on.
AGREED (unanimously that: i) the committee to approve the cremator repairs costing £60,000, from the existing revenue budget; ii) delegated authority be given to the Chair Councillor P Peacock (Newark and Sherwood District Council), Vice-Chair Councillor A Burgin (Mansfield District Council) and Councillor T Hollis (Ashfield District Council), for approval of repairs to the cracked chimney stack if required for health and safety reasons; and iii) the report be noted.
Word for word from the decision Newark and Sherwood published for this meeting.Source: democracy.newark-sherwooddc.gov.uk
Report to Mansfield and District Crematorium Joint Committee
Report to: Mansfield and District Joint Crematorium Committee Date: Monday 22 September 2025 (15:00 hours) Director Lead: Mansfield District Council, Ady Selby, Assistant Director Neighbourhood Services, 01623 463036 Lead Officer: Mansfield District Council, Nada Colclough, Crematorium and Cemeteries Manager and Registrar, 01623 463882
Report Summary
Type of report Open Report
Report Title Operations Report
This report seeks t1.4 Purpose of Report o provide an update the current operation of the crematorium
That the Committee: 1. approve the cremator repairs costing £60,000, from the Recommendations existing revenue budget; and 2. note the report.
1.0Background 1.1 The previous report was presented to the committee in May 2025. This report provides the committee with an update on the crematorium operation since then. 2.0 Proposal/Options Considered and Reasons for Recommendation 2.1 Cremator and Ancillary Equipment 2.2 Cremator number 4 – Cremator 4 was non-operational for a period of five days during September due to failing brick work in the door. This was able to be repaired quickly bringing the cremator back into operation. We are seeking quotes for the cost of a half reline and a cost for replacing the blast tube as the blast tube was repaired on the last service. The hearth is showing signs of wear and will need recasting. While a full reline is expected to cost over £100,000, carrying out necessary repairs should keep cremator 4 operational for the next 12 months at a cost of approximately £60,000. 2.3 Should there be an absolute need for the reline to be carried out in order to remain operation, careful consideration will be taken in line with business need and the impact of decommissioning cremator 4 given the huge costs associated with this. Significant spend of this nature will be avoided where possible. 2.4 Since replacing some of the Adams cards, we haven't encountered any further electrical issues with cremator number 4. We have also purchased an additional full set of Adams cards. The cremator is running ok but still has issues where valves have to manually set during cremations. The main chamber brickwork, roof bars and tiles and the door or satisfactory.
2.5Any required works outside of budgeted spend will be presented to the committee for consideration and a decision will need to be made based on business continuation. Where this is needed the utilisation of any parts on new cremators will form part of the decision making.
2.6Cremator numbers 2 & 3 – On the whole, cremators 2 and 3 are running satisfactorily. There have been a couple of concerns with system errors, and this is believed to be due to the excessive temperatures during the summer months. These errors have been investigated however, as with cremator 4, we will only spend where there is an absolute need, or we have complete failure of the cremator. The main chambers brickwork, roof bars and tiles and the doors are satisfactory.
2.7A quote is being sought for number 2 cremators fan as the invertor has tripped on a couple of occasions.
2.8In addition to the cremator 4 breakdown, we have also experience failure of the gas fail safe which meant that we were unable to cremate for a period of 24 hours. This was resolved quickly.
2.9Building Maintenance and Repair
2.10The following building maintenance is required despite the pending renovation works. While spend is being minimised, works are required to remain operational reduce further risks or for the need to ensure continued service standards for visitors and mourners.
2.10.1 A crack in the chimney stack requires a temporary repair. This will be achieved through temporary strapping which is effective but the least expensive option considering that the stack will be removed during the refurbishment. A bat survey is currently being undertaken to establish the best course of action in relation to the works. Any additional funds required to complete these works will be provided to the committee.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Mansfield and District Crematorium Joint Committee at Newark and Sherwood and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.