Local Regeneration Fund (LRF) Programme Update

Noted Executive 1 paper

AI summaryCabinet noted progress on three Local Regeneration Fund projects in Newark, agreed a reduced budget for the Market Place Improvement Scheme, approved additional funding for the Castle Gatehouse project, and delegated authority for grant awards to officers.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNoted
Money£45m total programme, exact amounts exempt
What happens nextMarket Place works start Spring 2027
Who it affectsNewark town centre regeneration

What was decided

Cabinet noted the updates associated with the LRF programme and projects, noted progress on the 32 Stodman Street Project, and agreed to reduce the Market Place Improvement Scheme capital budget and deliver the scheme with updated scope including power for markets and events, lighting, CCTV, pavement improvements and new market stalls. Report 1.12, P15

Cabinet delegated authority to the Council's Section 151 Officer and Director of Planning and Growth to approve a grant award of up to £ to Newark Town Council towards new and improved Market Stalls, to be formalised via a Grant Funding Agreement.

Cabinet agreed to increase the Castle Gatehouse project capital budget by £, funded by LRF grant, and delegated authority to the Section 151 Officer to approve commitment of the remaining LRF grant towards existing Newark LRF capital projects as further contingency. Report 1.19, 1.20

Why

The 32 Stodman Street project is progressing well with practical completion anticipated for late October 2026 and Heads of Terms finalised with two retail tenants, with advanced negotiations ongoing for the remaining units. Report 1.7

The Market Place Improvement Scheme scope was updated to achieve impactful benefits for the local community whilst remaining within the available LRF budget, including power for markets and events, lighting, CCTV enhancements, pavement improvements and new market stalls owned by Newark Town Council. Report 1.12, P15, 1.13

The Castle Gatehouse project requires additional budget due to unexpected archaeological discoveries, fragile high-level masonry requiring design amendments and revised Historic England consents, programme adjustments, cost pressures from provisional sums tested against current market rates, approximately 18 months of construction inflation and ongoing volatility in global materials markets. Report 1.16, 1.18, 1.19

What happens next

The 32 Stodman Street project will reach practical completion in late October 2026 with formal opening and tenant occupation to follow, and the residential units will be marketed for sale by Arkwood Developments Ltd. Report 1.7

Market Place Improvement Scheme works are anticipated to commence on site in Spring 2027 and complete by Autumn 2027, working within the LRF spend deadline of 31st March 2028. Report 1.13

The Castle Gatehouse project is expected to complete and open in Summer 2027, with attention turning to detailed design and integration between historic fabric and new construction. Report 1.15, 1.17

The money

  • £45m Total transformational Local Regeneration Fund investment awarded within the district between 1st April 2021 and 31st March 2028 Report 1.1
  • £2.5m Interest only loan to Arkwood Developments Ltd for 40 years at 2.5% to support purchase of 29 residential apartments at Stodman Street, agreed by Cabinet in March 2022 Report 1.8
  • £256,999 Present value of subsidy estimated for the Arkwood loan, below the Minimal Financial Assistance threshold but exceeding £100,000 and subject to subsidy transparency requirements and publication on the Subsidy Control Database Report 2.3, 2.4
  • £3.61m Existing capital budget for the Market Place Improvement Scheme, proposed to be reduced to a figure in the Exempt Appendix Report 1.13

Options considered

  • Rejected: Maintain original Market Place Improvement Scheme scope and budget. Updated scope was developed to achieve impactful benefits whilst remaining within the available LRF budget Report 1.12, 1.13
  • Chosen: Deliver Market Place Improvement Scheme with updated scope. Provides power for markets and events, lighting, CCTV enhancements, pavement improvements and new market stalls within available budget Report 1.12, P15
  • Chosen: Increase Castle Gatehouse project capital budget by £ from LRF grant. Required to address cost pressures from archaeological discoveries, masonry issues, market rate increases, construction inflation and global materials market volatility Report 1.19, 1.20

Implications

  • Financial: Market interest rates have increased since the 2022 loan approval to Arkwood Developments Ltd, resulting in the loan now potentially classifiable as a subsidy under the UK Subsidy Control Regime with an estimated present value of £256,999, requiring publication on the Subsidy Control Database. Report 1.8, 2.3, 2.4
  • Legal: The commitment of LRF capital budget for the Market Place Improvement Scheme would be subject to review and re-approval by the Section 151 Officer of the existing and approved project Business Case to ensure funding compliance and assurance requirements are met.
  • Financial: The 32 Stodman Street project is progressing well within the current budget and remains regularly monitored; the loan facility was originally approved at 2.5% interest rate but market rates have increased requiring updated advice on subsidy classification. Report 2.2, 2.3

Who and where

  • Arkwood Developments Ltd Report 1.8, 2.3
  • Newark Town Council Report 1.10, 1.12
  • Residents and visitors of Newark town centre Report 1.9, 1.12
  • Tenants of 32 Stodman Street retail and residential units Report 1.6, 1.7

Timeline

  • 1st April 2021 to 31st March 2028: LRF programme delivery period, with all grant requiring spend by 31st March 2028 Report 1.1
  • May 2021: Newark and Sherwood District Council secured £25m LRF (Newark Towns Deal) Report 1.2
  • Late October 2026: 32 Stodman Street project practical completion anticipated Report 1.7
  • Summer 2027: Castle Gatehouse project expected to complete and open Report 1.15
  • Spring 2027: Market Place Improvement Scheme works anticipated to commence on site Report 1.13
  • Autumn 2027: Market Place Improvement Scheme anticipated completion Report 1.13

Plain English for the jargon

  • LRF: Local Regeneration Fund, announced by UK Government in September 2025 consolidating the Levelling Up Fund, Town Deals and Pathfinder Pilot
  • MHCLG: Ministry of Housing, Communities and Local Government
  • NSDC: Newark and Sherwood District Council
  • NTC: Newark Town Council
  • TIP: Town Investment Plan, 30-year plan developed in partnership with the Newark Town Board
  • FBC: Full Business Case for the Market Place Improvement Scheme
  • RIBA: Royal Institute of British Architects, industry standard design stages
  • Section 151 Officer: Senior council officer responsible for financial administration under the Local Government Act 1972
  • UK Subsidy Control Regime: Legal framework governing government subsidies to organisations, requiring transparency and compliance with subsidy control rules
  • Arkwood Developments Ltd: Council's wholly owned company purchasing the 29 residential apartments at 32 Stodman Street
  • PiPP: Pride in Place Programme, a separate £20m programme delivered via the Newark Town Board vehicle
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item15

Resolved

That Cabinet: a) note the updates associated with the LRF programme and projects, as detailed throughout this report. LRF 32 Stodman Street Project b) Note the projects progress as detailed in 1.6 to 1.8 of this report. LRF Market Place Improvement Scheme c) Agree to reduce the projects existing capital budget of £3.61m to £ (information within Exempt Appendix) and deliver the scheme in accordance with the updated scope set out within 1.12 and 1.13 of this report, of which £ (information within Exempt Appendix) is detailed at Recommendation ‘d’ below. The project budget would be fully funded by LRF grant, subject to approval of the project Business Case by the Council’s Section 151 Officer, as set out in 1.14 of this report. d) delegate authority to the Council’s Section 151 Officer and Director of Planning & Growth to determine and approve a grant award of up to£ (information within Exempt Appendix) to Newark Town Council towards the purchase of new/improved Market Stalls. This would be formalised via a Grant Funding Agreement and included within the projects proposed capital budget, as referenced at Recommendation ‘ c’ above. LRF Castle Gatehouse Project e) Agree to increase the projects capital budget by £ (Information within Exempt Appendix), funded by LRF grant, in accordance with the resolution of the Newark Town Board on 2 nd September 2026 and as set out within 1.19 of this report. f) Information within Exempt Appendix. g) Note the remaining balance of LRF capital grant totalling £ (information within Exempt Appendix) , following the budget amendments set out at Recommendations ‘ c’ and ‘e’ above. h) Delegate authority to the Council’s Section 151 Officer, in consultation with the Director of Planning & Growth to approve the commitment of the remaining £ (information within Exempt Appendix) of LRF grant (as referenced at Recommendation ‘g’ above) towards any of the existing and agreed Newark LRF capital projects, providing further contingency for ongoing projects.
Word for word from the decision Newark and Sherwood published for this meeting. Source: democracy.newark-sherwooddc.gov.uk

Follow this further

Built from Newark and Sherwood's papers

What the report saysPro

Report to Cabinet

Report to: Cabinet Meeting: 15 September 2026 Portfolio Holder: Councillor Paul Peacock – Strategy, Performance & Finance Councillor Claire Penny – Sustainable Economic Development Director Lead: Matt Lamb, Director, Planning & Growth Lead Officers: Neil Cuttell, Head of Economic Growth & Visitor Economy Sarah Husselbee, Economic Development Grants & Programmes Manager Carys Coulton Jones, Assistant Director, Culture & Communities

Report Summary Key-Decision (Open with Exempt Appendix)

The appendix to this report contains exempt information as defined under Schedule 12A of the Local Government Act 1972, Paragraph 3 under which the Cabinet has the power to exclude the press and public if it so wishes. Type of Report It is considered that the need to treat the information in this report as exempt outweighs the public interest in disclosure because it contains information which is both commercially sensitive as well as financial or business affairs not yet publicly discussed, relating to the organisations referenced throughout the report. This information has been redacted or excluded in this open report. Report Title Local Regeneration Fund Update

To provide an update and recommendations relating to the Purpose of Report delivery of the Local Regeneration Fund (LRF) programme. That Cabinet: a) note the updates associated with the LRF programme and projects, as detailed throughout this report. LRF 32 Stodman Street Project

Recommendations b) Note the projects progress as detailed in 1.6 to 1.8 of this report. LRF Market Place Improvement Scheme c) Agree to reduce the projects existing capital budget of £3.61m to £ (information within Exempt Appendix) and deliver the scheme in accordance with the updated scope set out within 1.12 and 1.13 of this report, of which £ (information within Exempt Appendix) is detailed at Recommendation ‘d’ below. The project budget would be fully funded by LRF grant, subject to approval of the project Business Case by the Council’s Section 151 Officer, as set out in 1.14 of this report. d) delegate authority to the Council’s Section 151 Officer and Director of Planning & Growth to determine and approve a grant award of up to £ (information within Exempt Appendix) to Newark Town Council towards the purchase of new/improved Market Stalls. This would be formalised via a Grant Funding Agreement and included within the projects proposed capital budget, as referenced at Recommendation ‘c’ above. LRF Castle Gatehouse Project e) Agree to increase the projects capital budget by £ (Information within Exempt Appendix), funded by LRF grant, in accordance with the resolution of the Newark Town Board on 2nd September 2026 and as set out within 1.19 of this report. f) Information within Exempt Appendix. g) Note the remaining balance of LRF capital grant totalling £ (information within Exempt Appendix), following the budget amendments set out at Recommendations ‘c’ and ‘e’ above. h) Delegate authority to the Council’s Section 151 Officer, in consultation with the Director of Planning & Growth to approve the commitment of the remaining £ (information within Exempt Appendix) of LRF grant (as referenced at Recommendation ‘g’ above) towards any of the existing and agreed Newark LRF capital projects, providing further contingency for ongoing projects.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Local Regeneration Fund (LRF) Programme UpdateReport 263 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 18 attended
PP
Councillor Paul PeacockChair, present
RC
Councillor Rowan CozensCommittee Member, present
SC
Councillor Susan CrosbyCommittee Member, present
LB
Councillor Lee BrazierCommittee Member, present
SF
Councillor Simon FordeCommittee Member, apologies
PH
Councillor Peter HarrisCommittee Member, present
CP
Councillor Claire PennyCommittee Member, present
PT
Councillor Paul TaylorCommittee Member, present
JK
Councillor Jack KellasCommittee Member, present
NH
Nigel HillSecretary, expected
MF
Matt FinchOfficer, expected
DK
Deborah K JohnsonOfficer, expected

All 18 on the meeting page

On this subject at Newark and Sherwood

Search all
  1. Local Regeneration Fund (LRF) Programme UpdateThis decision
  2. Local Regeneration Fund Update (Key Decision)Noted
  3. Local Regeneration Fund and Newark Capital Projects Update (Key Decision)Noted

More from Newark and Sherwood Cabinet

All decisions
MeetingDecisionOutcome
15 Sep 2026 Budget Performance Report Quarter 1That Cabinet: (a) note the General Fund projected unfavourable outturn variance of £0.665m; (b) note the Housing Reve... Noted Open
15 Sep 2026 Community Plan Performance Report Quarter 1That Cabinet: a) review the Community Plan Performance Report attached as Appendix 1; b) review the compliance report... Decided Open
15 Sep 2026 Housing Compliance Assurance Report Quarter 1That Cabinet note: a) the exceptions to performance of the housing service compliance functions; b) interim arrangeme... Decided Open
15 Sep 2026 Annual Review of Exempt ItemsThat Cabinet note the report, with any items being released into the public domain if considered no longer being exempt. Noted Open
15 Sep 2026 Progress Towards Net ZeroThat Cabinet: a) notes the Council's 2025/26 corporate emissions position and progress towards the Net Zero 2035 targ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies