Resolved :- (a) That the improvements made to date be noted and the proposed revised timetable for the resolution of the outstanding issues indicated in the report be agreed with a further progress report being submitted to the Committee in January 2012. (b) That the Head of Planning and Development continue to report on a quarterly basis on the exercise of his authority, where given by the Committee, to extend the period of time for an applicant to enter into Section 106 Obligations, and of any similar decisions made by the Chair and Vice Chair.
Word for word from the decision Newcastle-under-Lyme published for this meeting.Source: moderngov.newcastle-staffs.gov.uk
To provide Members with an update on the progress of work in respect of planning obligations contained within agreements and unilateral undertakings made under Section 106 of the Planning Act, the planned work regarding the proactive monitoring of them, and related issues identified in previous reports on this matter to the Committee including that on 2 August, 2011.
Recommendations
(a) That the improvements made to date be noted and the proposed revised timetable indicated in the report for the resolution of the outstanding issues indicated below be agreed with a further progress report being brought to the Planning Committee in January 2012.
(b) That the Head of Planning and Development continue to report on a quarterly basis on the exercise of his authority, where given by the Committee, to extend the period of time for an applicant to enter into the Section 106 obligations, and of any similar decisions made by the Chairman and Vice Chairman.
Background
1.1Members may recall items presented at their previous meetings outlined a work programme relating to the preparation and monitoring of planning obligations. This identified the following ten topic areas.
1.2The current position in this work area is as follows:-
Stage and Envisaged Progress to date Further Action improvement task(s) timeframe Required 1. Pre-application - By End of April Partially completed– Include on Website more specific advice 2010 Officers have access to model agreements including on the standard information and obligations website relating to section 106 which are available. obligations to pass on Keep officers and advise developers. updated on changes Developer Contributions to process and best SPD available on website practice as and when but further improvements necessary. required to website. 2. Validation– to By Early in 2011 Completed - “Local List Officers have require applicants as of validation received training on a precondition of requirements” places a the Local List validation to provide requirement for draft “heads of applicants to provide Officers are to terms” “draft heads of terms” continue to identify where appropriate, when the need for section submitting a planning 106 obligations at the application. The Local pre-application stage List of Validation and advise Requirements came into applicants of the rd force on 3 October 2011 validation when it was published on requirement. – the Council’s website Ongoing
3. Prior to the End of April 2010 Completed – discussions Monitor responses committee and have taken place with from consultees in delegated report some consultees terms of their being prepared – to regarding the need to promptness and remind consultees of provide prompt and quality of the the duty to provide detailed responses when response and raise substantive requesting section 106 any issues in review responses; timing requirements. Increased meetings with them – them out if necessary use of unilateral Ongoing and encouragement undertakings when of use of unilateral NTADS contribution and undertakings where Travel Plan monitoring appropriate only requirements. 4. Committee With effect from Ongoing – Pre- Continue with good Report- bringing March 2010 committee instruction of practice, identify any applicant’s attention Head of Central Services common failings in to key dates and and correspondence with clarity or S106 requirements applicants is now being completeness of pre-committee, and carried out in virtually all instructions clear instructions to cases. Improvements in Head of Central clarity and completeness Services of instructions by planning officers still required 5. Post Committee With effect from Initiated - this is being Continue to instruct – prompt instructions March 2010 carried out promptly
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.