Quarterly Report on Section 106 Agreements/Obligations

Noted Planning 1 paper

Planning Committee noted this item on Tuesday 25 October 2011. Below is the council's own wording, with the papers it was decided on.

Item9

Resolved

Resolved :- (a) That the improvements made to date be noted and the proposed revised timetable for the resolution of the outstanding issues indicated in the report be agreed with a further progress report being submitted to the Committee in January 2012. (b) That the Head of Planning and Development continue to report on a quarterly basis on the exercise of his authority, where given by the Committee, to extend the period of time for an applicant to enter into Section 106 Obligations, and of any similar decisions made by the Chair and Vice Chair.
Word for word from the decision Newcastle-under-Lyme published for this meeting. Source: moderngov.newcastle-staffs.gov.uk

Follow this further

Built from Newcastle-under-Lyme's papers

What the report saysPro

Report to Planning Committee

Purpose of the report

To provide Members with an update on the progress of work in respect of planning obligations contained within agreements and unilateral undertakings made under Section 106 of the Planning Act, the planned work regarding the proactive monitoring of them, and related issues identified in previous reports on this matter to the Committee including that on 2 August, 2011.

Recommendations

(a) That the improvements made to date be noted and the proposed revised timetable indicated in the report for the resolution of the outstanding issues indicated below be agreed with a further progress report being brought to the Planning Committee in January 2012.

(b) That the Head of Planning and Development continue to report on a quarterly basis on the exercise of his authority, where given by the Committee, to extend the period of time for an applicant to enter into the Section 106 obligations, and of any similar decisions made by the Chairman and Vice Chairman.

Background

1.1Members may recall items presented at their previous meetings outlined a work programme relating to the preparation and monitoring of planning obligations. This identified the following ten topic areas.

1.2The current position in this work area is as follows:-

Stage and Envisaged Progress to date Further Action improvement task(s) timeframe Required 1. Pre-application - By End of April Partially completed– Include on Website more specific advice 2010 Officers have access to model agreements including on the standard information and obligations website relating to section 106 which are available. obligations to pass on Keep officers and advise developers. updated on changes Developer Contributions to process and best SPD available on website practice as and when but further improvements necessary. required to website. 2. Validation– to By Early in 2011 Completed - “Local List Officers have require applicants as of validation received training on a precondition of requirements” places a the Local List validation to provide requirement for draft “heads of applicants to provide Officers are to terms” “draft heads of terms” continue to identify where appropriate, when the need for section submitting a planning 106 obligations at the application. The Local pre-application stage List of Validation and advise Requirements came into applicants of the rd force on 3 October 2011 validation when it was published on requirement. – the Council’s website Ongoing

3. Prior to the End of April 2010 Completed – discussions Monitor responses committee and have taken place with from consultees in delegated report some consultees terms of their being prepared – to regarding the need to promptness and remind consultees of provide prompt and quality of the the duty to provide detailed responses when response and raise substantive requesting section 106 any issues in review responses; timing requirements. Increased meetings with them – them out if necessary use of unilateral Ongoing and encouragement undertakings when of use of unilateral NTADS contribution and undertakings where Travel Plan monitoring appropriate only requirements. 4. Committee With effect from Ongoing – Pre- Continue with good Report- bringing March 2010 committee instruction of practice, identify any applicant’s attention Head of Central Services common failings in to key dates and and correspondence with clarity or S106 requirements applicants is now being completeness of pre-committee, and carried out in virtually all instructions clear instructions to cases. Improvements in Head of Central clarity and completeness Services of instructions by planning officers still required 5. Post Committee With effect from Initiated - this is being Continue to instruct – prompt instructions March 2010 carried out promptly

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Quarterly Report on Section 106 Agreements/ObligationsReport 42 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 16 attended
AF
Councillor Andrew FearChairman, present
DC
Councillor David ClarkeVice-Chair, present
EB
Councillor Edward BodenCommittee Member, present
GC
Councillor George CairnsCommittee Member, present
MR
Councillor Michael Ross ClarkeCommittee Member, apologies
JC
Councillor John CooperCommittee Member, present
AH
Councillor Ashley HowellsCommittee Member, present
TL
Councillor Thomas LawtonCommittee Member, present
IM
Councillor Ian MatthewsCommittee Member, apologies
MM
Councillor Miss Marion ReddishCommittee Member, present
BS
Councillor Bill SinnottCommittee Member, apologies
RS
Councillor Robin StuddCommittee Member, present

All 16 on the meeting page

On this subject at Newcastle-under-Lyme

Search all
  1. Quarterly Report on Section 106 Agreements/ObligationsThis decision
  2. Quarterly report on extensions to time periods within which obligations under section 106 can be entered intoNoted
  3. Quarterly report on extensions to time periods within which obligations under section 106 can be entered intoNoted
  4. Quarterly report on extensions to time periods within which obligations under section 106 can be entered intoNoted
  5. Quarterly report on extensions to time periods within which obligations under section 106 can be entered intoNoted
  6. Quarterly report on extensions to time periods within which obligations under section 106 can be entered intoNoted

More from Newcastle-under-Lyme Planning Committee

All decisions
MeetingDecisionOutcome
18 Aug 2026 Minutes of previous meeting(s)That the minutes of the meeting held on 21 July, 2026 be agreed as a correct record. Agreed Open
18 Aug 2026 Application for major development - tadgedale quarry. wain homes north west. 24/00589/fulThat the application be permitted subject to the undermentioned conditions: (i) Variation of condition 2 to refer to ... Agreed Open
18 Aug 2026 Application for major development - land off bar hill road onneley. owl homes limited. 25/00897/remThat the application be permitted, subject to the undermentioned conditions: (i) Link to outline planning permission ... Approved Open
18 Aug 2026 Application for other development - 25-27 well st & 82 garden st, newcastle. marshallsay. 26/00051/couThat the application be refused for the following reasons: (i) Contrary to Policy HOU7 (Homes in Multiple Occupation)... Refused Open
18 Aug 2026 Five-year housing land supply update report 2026-31(i) That Members note the content of the five-year housing Land supply position statement (appendix 1) and agree that... Noted Open