FIVE-YEAR HOUSING LAND SUPPLY UPDATE REPORT 2026-31

Noted Planning 3 papers

AI summaryNewcastle-under-Lyme Planning Committee noted a five-year housing land supply position statement showing 7.57 years supply, enough to use as a material consideration in planning decisions, and asked officers to prepare an action plan on delivery.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedUsed as material planning consideration
MoneyNot stated
What happens nextPrepare action planOn housing delivery challenges in Borough
Who it affectsPlanning decisionsApplicants and development management

What was decided

Members noted the five-year housing land supply position statement covering 1 April 2026 to 31 March 2031 and agreed it represents the current supply position. Report P1

Members agreed the position statement can be used as a material consideration for development management decision taking. Report P1

Members noted the need to prepare an action plan covering how the Council will respond to challenges in housing delivery in the Borough.

Why

To ensure the five-year supply calculation follows the National Planning Policy Framework and Planning Practice Guidance and reflects the most up to date position on deliverable sites. Report P2, P4

The Local Plan 2020 to 2040 sets a requirement of 400 dwellings per annum, which is less than 80 percent of the standard method figure, so a 20 percent buffer applies under paragraph 78(C) of the 2024 NPPF. Report P5, P7

As of 31 March 2026, the Council can demonstrate 7.57 years supply of housing, exceeding the 5 year requirement, with a track record of exceeding delivery over the last three years. Report P8, P9

What happens next

Officers are to prepare an action plan on how the Council will positively respond to challenges in housing delivery in the Borough.

Updated Housing Delivery Test figures are expected later in 2026 and will inform the next assessment. Report P8

The money

  • 400 dwellings per annum Housing requirement in adopted Local Plan Report P5, P7
  • 559 dwellings per annum Local housing need using the standard method, as of May 2026 Report P5
  • 80 dwellings per annum Additional dwellings from the 20 percent buffer Report P7
  • 480 each year Total annual requirement with buffer applied Report P7
  • 2400 Aggregate five-year requirement figure from 2026 to 2031 Report P7

Options considered

  • Chosen: Use adopted Local Plan figure of 400 dwellings per annum with a 20 percent buffer. Strategic policies in the Local Plan 2020 to 2040 are up to date, but the requirement is below 80 percent of the standard method and the Plan was examined under the 2023 NPPF, so a buffer is required. Report P5, P7
  • Rejected: Use the standard method figure of 559 dwellings per annum. Strategic housing policies in the Local Plan are recently adopted and up to date, so the Local Plan figure is used. Report P5, P7

Implications

  • Legal: The position statement is a material consideration in development management decisions, and the calculation must align with the National Planning Policy Framework and Planning Practice Guidance. Report P1, P2
  • Other: Demonstrating 7.57 years supply means policies for delivering housing are not treated as out of date under the presumption in favour of sustainable development. Report P4, P9
  • Equalities: Officers consider the proposal will not have a differential impact on people with protected characteristics under the Equality Act 2010. Report P11

Who and where

  • Planning applicants in Newcastle-under-Lyme Borough Report P1
  • Council development management officers determining planning applications Report P1
  • Landowners and developers of allocated, windfall and permitted sites Report P9

Timeline

  • December 2024: Housing Delivery Test result published showing the Council exceeded requirements over the last three years Report P8
  • Later in 2026: Updated Housing Delivery Test figures expected Report P8
  • 31 March 2026: Date as of which the Council can demonstrate 7.57 years supply Report P9
  • 1 April 2026 to 31 March 2031: Five-year housing land supply period covered by the position statement Report P6, P9
  • 03 August 2026: Date the report was prepared Report P20

Plain English for the jargon

  • NPPF: National Planning Policy Framework, the government's planning policy document.
  • PPG: Planning Practice Guidance, government guidance supporting the NPPF.
  • Housing Delivery Test: Government measure comparing homes delivered against homes required over a three year period.
  • Buffer: Extra percentage added to the five-year housing requirement to provide a margin of safety.
  • Windfall: Sites not specifically allocated in a development plan that come forward for development.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6

Resolved

(i) That Members note the content of the five-year housing Land supply position statement (appendix 1) and agree that it represents the current housing land supply position and can be used as a material consideration for development management decision taking. (ii) That Members note the need to prepare an action plan that will consider how the Council will positively respond to challenges in housing delivery in the Borough. Watch the debate here
Word for word from the decision Newcastle-under-Lyme published for this meeting. Source: moderngov.newcastle-staffs.gov.uk

Follow this further

Built from Newcastle-under-Lyme's papers

What the report saysPro

Report to Planning Committee

Recommendation

1. That Members note the content of the five-year housing land supply position statement (appendix 1) and agree that it represents the current housing land supply position and can be used as a material consideration for development management decision taking.

Reason for recommendation

To ensure the Council calculates its five-year housing land supply statement in accordance with the National Planning Policy Framework (“NPPF”), Planning Practice Guidance (“PPG”) and reflects the most up-to-date position regarding the supply of deliverable sites in the Borough.

Key Issues

A five-year housing land supply report is prepared by Council’s to demonstrate that there are sufficient housing land sites to meet housing needs over a five-year period. When a Council cannot demonstrate a five-year supply of housing then policies for delivering housing are deemed out of date. The National Planning Policy Framework notes that in such circumstances, applications for housing should be decided based on the presumption in favour of sustainable development.

Where a Local Plan was adopted in the last five years, or where strategic housing policies have been reviewed and found to be up to date, housing requirement figures set out in adopted policies should be used for the calculation. The housing figure in our Local Plan is 400 dwellings per annum. In other circumstances, the five-year housing land supply will be measured against the area’s local housing need calculated using the standard method (which is, as of May 2026 559 dwellings per annum)

Member’s attention is drawn to the accompanying five-year housing land supply statement over the five-year period from 1st April 2026 to 31st March 2031 and its associated appendices. The purpose of this report is not to repeat the content of the supply statement, but rather to draw attention to key elements of it.

As noted above, as strategic policies in the Local Plan (2020-2040) are recently adopted, then land supply should be measured against the housing requirement outlined in the adopted plan. However, for the purposes of the five-year housing land supply calculation, paragraph 78(C) of the 2024 National Planning Policy Framework requires a 20% buffer to be added to our calculated figure. This is because the Newcastle under Lyme Local Plan was examined under an earlier (2023 as opposed to the latest published in 2024) version of the NPPF. Also, as the housing requirement in the Local Plan (400 dwellings per annum) is less than 80% of the standard method figure for the Borough (currently 559 dwellings per annum) then a buffer (the 20% buffer as set out above) is required in line with the NPPF. This equates to an extra 80 dwellings per annum being added, bringing a total of 480 each year or an aggregate five-year requirement figure of 2400 from 2026-2031.

The borough’s track record of housing delivery, as determined by its latest Housing Delivery Test results has also been considered in line with government guidance. The housing delivery figure was published in December 2024 and indicates that the Council has exceeded our requirements over the last three-year period. We are expecting updated figures for the housing delivery test later in 2026.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
App 1 HLS Report_v1Appendix 521 KB Download
PDF
FIVE-YEAR HOUSING LAND SUPPLY UPDATE REPORT 2026-31Report 79 KB DownloadRead as text
PDF
Item 7 Five Year Supply Report Supplementary ReportSupplementary 78 KB Download

At this meeting

Whole meeting

Who was there

11 of 23 attended
CS
Councillor Christopher SaxtonChair, present
JD
Councillor Jonathan DownsVice-Chair, present
MC
Mayor.Councillor Christopher BaileyCommittee Member, present
GE
Councillor Gary EvansCommittee Member, apologies
AF
Councillor Andrew FearCommittee Member, present
MH
Councillor Mark HollandCommittee Member, present
DH
Councillor David HutchisonCommittee Member, present
DJ
Councillor Dave JonesCommittee Member, present
SK
Councillor Simon KasperowiczCommittee Member, present
IS
Councillor Ian SparksCommittee Member, present
GT
Councillor Glenn TiftCommittee Member, present
AT
Councillor Andrew TurnockCommittee Member, present

All 23 on the meeting page

On this subject at Newcastle-under-Lyme

Search all
  1. FIVE-YEAR HOUSING LAND SUPPLY UPDATE REPORT 2026-31This decision
  2. FIVE YEAR HOUSING LAND SUPPLY STATEMENT FOR THE BOROUGH OF NEWCASTLE-UNDER-LYME. 1 APRIL 2021 to 31 MARCH 2026Noted
  3. FIVE YEAR HOUSING LAND SUPPLY STATEMENT FOR THE BOROUGH OF NEWCASTLE-UNDER-LYME FROM 1 APRIL 2020 to 31 MARCH 2025Noted
  4. Five year housing land supply statement 2019-2024Noted
  5. FIVE YEAR HOUSING LAND SUPPLY STATEMENT FOR THE BOROUGH OF NEWCASTLE-UNDER-LYME COVERING THE FIVE YEAR PERIOD FROM 1 APRIL 2018 to 31ST MARCH 2023Noted
  6. Five year housing land supply statement for the borough of newcastle-under-lyme from 1 april 2017 to 31 march, 2022Noted

More from Newcastle-under-Lyme Planning Committee

All decisions
MeetingDecisionOutcome
18 Aug 2026 Minutes of previous meeting(s)That the minutes of the meeting held on 21 July, 2026 be agreed as a correct record. Agreed Open
18 Aug 2026 Application for major development - tadgedale quarry. wain homes north west. 24/00589/fulThat the application be permitted subject to the undermentioned conditions: (i) Variation of condition 2 to refer to ... Agreed Open
18 Aug 2026 Application for major development - land off bar hill road onneley. owl homes limited. 25/00897/remThat the application be permitted, subject to the undermentioned conditions: (i) Link to outline planning permission ... Approved Open
18 Aug 2026 Application for other development - 25-27 well st & 82 garden st, newcastle. marshallsay. 26/00051/couThat the application be refused for the following reasons: (i) Contrary to Policy HOU7 (Homes in Multiple Occupation)... Refused Open
21 Jul 2026 Minutes of previous meeting(s)That the minutes of the meeting held on 23 June, 2026 be agreed as a correct record. Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies