Resolved :- (a) That the report be noted. (b) That the period of time for the applicant to enter into the S106 Obligation in respect of planning application 11/00430/FUL be extended to 23 March 2012 and that the period of time previously agreed in respect of planning applications 11/00284/FUL and 11/00509/FUL be extended to 27 March 2012. (c) That the above revised dates be further extended in consultation with the Chair and Vice Chair but only if very exceptional circumstances exist to justify such an extension. (d) That the Head of Planning and Development continue to report on a quarterly basis on the use of his delegated authority to grant further extensions of time allowed to secure Section 106 Obligations and of any similar decisions made by the Chair and Vice-Chair.
Word for word from the decision Newcastle-under-Lyme published for this meeting.Source: moderngov.newcastle-staffs.gov.uk
To provide Members with a quarterly report on the exercise by either the Head of Planning and Development or the Chairman and Vice Chairman of the authority to extend periods within which planning obligations can be secured by
Recommendations
(a) That the report be noted
(b) That the Head of Planning and Development continue to report on a quarterly basis on the exercise of his authority, to extend the period of time for an applicant to enter into the Section 106 obligations, and of any similar decisions made by the Chairman and Vice Chairman.
Introduction
Since 30 March 2010, the Committee have normally, when resolving to permit an application subject to the prior completion of a planning obligation, also agreed to authorise the Head of Planning and Development to extend the period of time for an applicant to enter into the Section 106 obligations if he subsequently considers it appropriate (as an alternative to seeking such authority from the Committee, as had previously been required). It was envisaged that such an extension might occur where the Head of Planning and Development was satisfied that it would be unreasonable for the Council not to allow for additional time for an obligation to be secured It was recognised that an application would need to be brought back to Committee for decision should there have been a change in planning policy in the interim. It was agreed that your Officer would provide members with a regular quarterly report which on the exercise of such authority.
In the period since the last report on 25 October 2011 meeting was prepared (mid October 2011) to mid February 2012 it has been necessary to exercise this delegated authority with respect to 6 applications. Details are provided below:-
Application 10/00777/OUT
Members are advised that there was a considerable delay in concluding a planning obligation with respect to application relating to the Oxford Arms, May Bank which came before the Planning Committee on 8 March 2011, and was the subject of a resolution requiring the obligation to be completed by 1 April. The 8 week period on this application expired on 11 April 2011
On this occasion your officer chose not to exercise his delegated authority to refuse the application due to delays in the preparation and completion of the obligation on the part of both the Borough Council and the County Council and as such it was considered unreasonable to refuse the proposal.
Staffordshire County Council indicated that they would require the inclusion of additional obligations – notwithstanding that such obligations were not being sought by the Planning Authority. Lengthy negotiations then took place between the Borough Council, the County Council and the applicant on this matter. The County Council eventually agreed to the exclusion of the additional obligations in accordance with the advice of your Officer. Given these protracted discussion it was considered unreasonable to refuse the application under the delegated authority and extensions of time were agreed to allow the obligation to be secured.
The agreement securing the obligation was completed on 23 November 2011 and the planning permission was issued on 29 November 2011, following your officer being satisfied that there had been no material change in planning circumstances relevant to the proposal between 8 March 2011 and the day of the planning permission being issued.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.