- (a) That the information be received. (b) That the Head of Planning and Development continue to report on a quarterly basis on the exercise of his authority to extend the period of time, previously appeared by the Committee, for an applicant to enter into the Section 106 Obligations and of any similar decisions made by the Chairman and Vice-Chairman.
Word for word from the decision Newcastle-under-Lyme published for this meeting.Source: moderngov.newcastle-staffs.gov.uk
To provide Members with a quarterly report on the exercise by the Head of Planning and Development of the authority to extend periods within which planning obligations can be secured by (as an alternative to refusal of the related planning application).
Recommendations
(a) That the report be noted.
(b) That the Head of Planning and Development continue to report on a quarterly basis on the exercise of his authority, to extend the period of time for an applicant to enter into the Section 106 obligations, and of any similar decisions made by the Chairman and Vice Chairman.
Introduction
For sometime the Committee have usually, when resolving to permit an application subject to the prior completion of a planning obligation, also agreed to authorise the Head of Planning and Development to extend the period of time for an applicant to enter into the Section 106 obligations if he subsequently considers it appropriate (as an alternative to refusing the application or seeking such authority from the Committee).
When this practice was first established it was envisaged that such an extension might occur where the Head of Planning and Development was satisfied that it would be unreasonable for the Council not to allow for additional time for an obligation to be secured. It was recognised that an application would need to be brought back to Committee for decision should there have been a change in planning policy in the interim. It was agreed that your Officer would provide members with a regular quarterly report on the exercise of that authority.
In the period since the last such report to 6 March 2012 meeting was prepared (in late February 2012) to mid April 2012 it has been necessary to decide whether or not to exercise this delegated authority on 5 occasions with respect to 3 applications. Details are provided below:-
Application ref 11/00430/FUL
The proposal for the erection of 61 dwellings at land off Keele Road, Newcastle came before the Planning Committee on 4 October 2011 and members resolved to permit the application subject to the completion of a section 106 obligation by 18 November 2011 (securing obligations similar to those entered into in 2000). The 13 week period for the application ended on that same day. An appeal against an earlier decision was withdrawn on the basis of the Committee resolution. The obligation was not completed by the date referred to in the Committee resolution. Given that all parties had made significant efforts to resolve this matter but due to the complexity of the issues that had not happened, it was agreed to extend the period for the completion of the obligation to 9 January 2012 and then a further extension until 23 March 2012.
When this matter was last reported to the Planning Committee on 6 March 2012 Members indicated that unless very special circumstances emerge as to why a further extension should be given, this date (of 23 March) should not be exceeded, and that the Chairman and Vice-Chairman should be consulted by the Head of Planning and Development if he was proposing to accept any further extension.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.