Resolved
- (a) That the report be received. (b) That a further update be provided alongside the next quarterly monitoring report on cases where enforcement action has been authorised.
Planning Committee decided this item on Tuesday 2 October 2012. Below is the council's own wording, with the papers it was decided on.
Resolved
- (a) That the report be received. (b) That a further update be provided alongside the next quarterly monitoring report on cases where enforcement action has been authorised.
To inform Members of the current situation regarding the enforcement caseload.
(a) That the report be received.
(b) That a further update be provided alongside the next quarterly monitoring report on cases where enforcement action has been authorised.
1.1In accordance with previous Committee decisions, the format of this report shows existing and previous enforcement cases. The Table included in this report shows the total number of outstanding cases in one format (shown below).
1.2Since the preparation of the last report on 22 June 2012 a further 42 new cases have been reported and overall 72 cases have been closed this Quarter. The net figure as of 14 September 2012 therefore stands at 157 open cases (30 less than last quarter). Progress has again been made within this past Quarter and the fewer ‘new cases’ received (relative to some previous Quarters) has allowed officers to focus again on older cases. The number of total open cases is currently at its lowest for a number of years.
1.3Planning Committee Members continue to be sent a Monthly Enforcement List, which identifies what new enforcement related cases have been logged each calendar month.
2. Conclusions
2.1It remains inevitable that some cases in the ‘backlog’ will remain open for some time because of their complexity.
2.2Progress continues to be made in tackling older cases and there is still a significant body of work being undertaken behind the scenes, which has lead to progress in several complex cases. Officers’ enforcement workload is regularly reviewed to ensure continuity and case progression.
2.3The Council’s Planning Enforcement Officer continues to assist Planning Officers where possible by providing updates to their enforcement caseload and to seek to progress either the taking of enforcement action or their closure. This has also resulted in the submission of several additional planning applications. It should be noted that the total number of cases open remains well below 200 cases (157 at the time of report preparation).
3. Current Outstanding Enforcement Cases
3.1The Table below shows the current statistics in comparison to the previous Quarter based on the position up to and including 14 September 2012.
Current Enforcement Status
Year Total Open C1 C2 C3 BOC L M H
2012 180 66 13 38 13 2 2011 204 22 2 14 6 2010 206 11 2 7 2 - - - 2009 233 18 - 12 3 1 - 1 1 2008 276 13 - - - - 3 10 - 2007 353 6 - - - - 1 4 1 2006 280 9 - - - - 2 4 3 2005 227 2 - - - - - 2 2004 252 3 - - - - 1 1 1 2003 244 1 - - - - - 1 - 2002 247 5 - - - - - 2 3 2001 204 1 - - - - - 1 - 2000 219 - - - - - - - - 1999 177 - - - - - - - - 1998 217 - - - - - - - - 1997 263 - - - - - - - -
Open Cases 157 (inc Backlog) Previous Quarter 187
Note for Table – C categories represent the categories agreed by the Planning Committee in February 2009; BOC indicates that the case concerns a Breach of Condition, whilst L, M and H represent Low, Medium and High priorities respectively allocated to the pre-February 2009 cases
Officers will continue to make progress in tackling the previous backlog, whilst maintaining a manageable reservoir of new/existing cases at a sustainable level. A number of the above cases have associated pending planning applications awaiting determination (4 as of 14 September 2012).
4. Date Report Prepared 14 September 2012
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Open Enforcement CasesReport | 31 KB | DownloadRead as text |
Follow Planning Committee at Newcastle-under-Lyme and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 18 Aug 2026 | Minutes of previous meeting(s)That the minutes of the meeting held on 21 July, 2026 be agreed as a correct record. | Agreed | Open |
| 18 Aug 2026 | Application for major development - tadgedale quarry. wain homes north west. 24/00589/fulThat the application be permitted subject to the undermentioned conditions: (i) Variation of condition 2 to refer to ... | Agreed | Open |
| 18 Aug 2026 | Application for major development - land off bar hill road onneley. owl homes limited. 25/00897/remThat the application be permitted, subject to the undermentioned conditions: (i) Link to outline planning permission ... | Approved | Open |
| 18 Aug 2026 | Application for other development - 25-27 well st & 82 garden st, newcastle. marshallsay. 26/00051/couThat the application be refused for the following reasons: (i) Contrary to Policy HOU7 (Homes in Multiple Occupation)... | Refused | Open |
| 18 Aug 2026 | Five-year housing land supply update report 2026-31(i) That Members note the content of the five-year housing Land supply position statement (appendix 1) and agree that... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.