Resolved
That the current project plan be noted.
Economic Development and Enterprise Scrutiny Committee noted this item on Wednesday 20 March 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
That the current project plan be noted.
Newcastle Town Centre Public Realm & Market Refurbishment Project
Task Target Date Dependencies / stages to completion Construct taxi rank in lower High Start early Feb 2013 90% complete. Street End late March 2013 Removal of trees as phase 1 of Complete Completed tree works in line with December 2012 Cabinet resolution Completion of Traffic Regulation Start date - started Tasks Orders (TROS) for Hassell Street End date late June 2013 Staffordshire County Council finalise design of TROs. (Traffic Regulation Orders control Staffordshire County Council complete statutory consultation process. the flow of traffic and access Dependencies times) If no significant objections received TROs can be implemented. If significant objections received this timescale is at risk of being extended. Finalise paving proposals – Start date – started Tasks design and materials End date late April 2013 Borough Council resolving design problems caused by current guidance on tactile paving for visually impaired people. Consultation with Guide Dog for Blind representative. Staffordshire County Council confirms suitability of sub base proposals. (drafted but not formally approved) Staffordshire County Council confirms suitability of taxi rank demarcation proposals. (Previous design rejected). This relates to any enforcement action needed for illegal parking once the scheme is complete. Staffordshire County Council approving drainage design in the light of managing the flood risk for 99p shop and NatWest side door once kerb lines are removed. Dependencies All above approvals being gained. Items in italics are critical dependencies
6/3/2013 Task Target Date Dependencies / stages to completion Construct Friars Street & Hassell Start date August 2013 Tasks Street End date November Staffordshire County Council complete TROs 2013 Staffordshire County Council approve construction design detail. Staffordshire County Council confirm traffic management arrangements whilst construction is underway. Dependencies TRO process being completed No unexpected surprises when groundworks are being undertaken. (every effort has been made to trace underground services).
Obtain planning permission for Started Tasks new market stalls End date late June 2013 Planning application submitted. Deadline for decision 24 April 2013 Dependencies Number of objections received to planning application Planning permission being granted Finalise design of new market Started Tasks stalls, procure and place on site. End date September Finish collecting feedback on the current test stall (significant delay due to recent 2013 poor weather affecting trader attendance and need to prioritise clearing the lower end of High Street.) Resolve issue of removable / fold up counter tops Issue specification and get quotes for manufacture. Appoint contractor for foundation / construction work. Put on site Dependencies Further weather disruption interrupting process. Planning permission being granted. No unexpected surprises when groundworks are being undertaken. Co-ordinate works around the Hassell Street junction with Staffordshire County Council works (new drainage connections cross the market area)
Items in italics are critical dependencies
6/3/2013
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Newcastle Town Centre Public Realm and Market Refurbishment ProjectReport | 28 KB | DownloadRead as text |
Follow Economic Development and Enterprise Scrutiny Committee at Newcastle-under-Lyme and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Mar 2018 | Minutes of previous meetingThat the minutes of the meeting held on 18 September, 2017 be agreed as a correct record. | Agreed | Open |
| 21 Mar 2018 | Future use of land associated with the ryecroft developmentThat the information be received and the comments noted. | Noted | Open |
| 21 Mar 2018 | District dealThat the information be received and the comments noted. | Noted | Open |
| 21 Mar 2018 | Economic performance of the boroughThat the information be received and the comments noted. | Noted | Open |
| 18 Sep 2017 | Minutes of previous meetingThat the minutes of the meeting held on 21 June 2017 be agreed as a correct record. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.