NEWCASTLE TOWN DEAL

Noted Scrutiny 1 paper

AI summaryNewcastle-under-Lyme scrutiny committee notes progress on £23.6m Town Deal and three town centre regeneration projects, with £18.4m spent so far.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCommittee noted the report; no new decisions made
Money£23.6m awarded, £18.4m spentOf £4.7m unspent, £4.75m is committed
What happens nextFurther updates to followMore reports at later scrutiny meetings
Who it affectsNewcastle-under-Lyme town centre and boroughMultiple regeneration sites across the area

What was decided

The committee noted the report on delivery of the Newcastle Town Deal funds and the three major town centre regeneration projects. Report P2

Why

The report updates the committee on progress and issues with the Town Deal funded projects and the three town centre regeneration schemes. Report P4, 4.1

The Council has secured Future High Street Funding and Town Deal Funds to redevelop key regeneration sites across the town centre and wider Borough. Report 1.1

What happens next

The committee will continue to receive further reports on these projects at subsequent meetings. Report 3.1

Archaeological consultant procurement is underway at Karparc, following the discovery of human remains during basement excavation; a plan will be put in place should further remains be found. Report P28

The money

  • £23.6m Total Town Deal funding awarded to the Council Report 8.1
  • £18,454,117.00 Total Town Deal funding spent to date Report 8.1, P95
  • £4,749,347.00 Town Deal funding committed but not yet spent Report P95
  • £396,536.00 Town Deal funding neither contracted nor order placed Report P95
  • £3,510,000 Digital Society project allocation and spend (Keele in Town) Report P37, P38
  • £400,000 EV charging points project allocation and spend (complete) Report P40

Options considered

  • Rejected: Options for individual projects. Considered in detail in earlier Cabinet reports on each project Report 5.1

Implications

  • Financial: All £23.6m Town Deal allocation received, with £18.4m spent and £4.75m committed. Report 8.1, P95
  • Legal: The Council must ensure activities are legally and state aid compliant, including the Public Sector Duty in the Equality Act 2010 and the Prudential Code. Report 6.2, 6.3
  • Equalities: No specific equality impacts identified from the development of these projects. Report 7.1
  • Risk: Risk management is central to the Council's commercial approach, with all potential activities assessed in line with corporate risk management. Report 9.1

Who and where

  • Residents and community groups in Newcastle-under-Lyme town centre and wider borough Report 1.1, P38, P46
  • Aspire Housing tenants and Keon Homes purchasers on Cross Street, Chesterton Report P51, P53
  • Future users of the 5 small enterprise units planned for North Street Report P57
  • Pedestrians, cyclists and bus users in Newcastle Report P60, P61, P63

Timeline

  • November 2025: Astley Place works commenced by Capital&Centric and AC1 Report P10
  • November 2025: Ryepark site clearance and ground works commenced Report P23
  • Early 2028: Ryepark development expected to complete (27 month build) Report P23
  • Early November 2025: Karparc works started by Clegg Construction Report P28
  • Summer 2027: Karparc development expected to complete (18 month build) Report P28
  • June 2026: Final claim scheduled for Keele in Town acoustic work Report P38
  • End of July 2026: Knutton Enterprise Centre extension units to be occupied Report P46
  • November 2026: Countryside development of 39 social rented apartments and bungalows for over 55s expected to complete Report P53
  • Late 2026: North Street enterprise units expected to complete Report P57
  • 2027/28: Hassell Street cycle lane expected to be delivered by Staffordshire County Council Report P61
  • January 2027: Astley Place development due to be completed (13 month build) Report P10
  • Summer 2026: McCarthy and Stone residential development works anticipated to commence Report P21
  • Late 2027: McCarthy and Stone development expected to complete Report P21

Plain English for the jargon

  • Town Deal Fund: Central government funding awarded to towns to support regeneration, infrastructure and connectivity projects.
  • Future High Streets Fund: Government funding for the redevelopment of town centres.
  • State aid: Government financial support that may affect trade between UK and EU member states, subject to compliance rules.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item4

Resolved

Resolved : That the report on the delivery of the Newcastle Town Deal Funds projects and the three major town centre regeneration projects be noted. Watch the debate here
Word for word from the decision Newcastle-under-Lyme published for this meeting. Source: moderngov.newcastle-staffs.gov.uk

Follow this further

Built from Newcastle-under-Lyme's papers

What the report saysPro

Report to Economy and Place Scrutiny Committee

Recommendation

That:-

1. Scrutiny Committee notes this report on the delivery of the Newcastle Town Deal Funds projects and the three major town centre regeneration projects.

Reasons

To update the Scrutiny Committee on the progress with the various projects that are being funded or part funded through the Newcastle Town Deal as well as the three Town Centre regeneration projects.

Background

1.1As reported to previous Scrutiny meetings, the Council has secured Future High Street Funding and Town Deal Funds for the redevelopment of several key regeneration sites across the Town Centre and the wider Borough.

2. Updates

2.1Town Centre Regeneration Projects

The current position regarding the three major regeneration projects is as follows:

2.1.1 Astley Place

Capital&Centric and their contractor AC1 commenced works (November 2025) with the development due to be completed in January 2027 (13 month build period).

Classification: NULBC UNCLASSIFIED Classification: NULBC UNCLASSIFIED

Works are ongoing with external facade works, internal courtyard landscaping and internal wall placements progressing at speed.

Merriel Street Elevation – external facade works

Internal Courtyard – levelling of area for landscaping

Classification: NULBC UNCLASSIFIED Classification: NULBC UNCLASSIFIED

Internal Courtyard Area and internal facing elevations

Internal wall fit out for apartments

Classification: NULBC UNCLASSIFIED Classification: NULBC UNCLASSIFIED

RyePark

2.1.2 McCarthy and Stone Residential Development

It is now anticipated that the works will commence in the summer of 2026 with completion in late 2027 to coincide with the adjacent Capital&Centric works.

2.1.3 Capital &Centric Ryepark Development

Capital&Centric have now appointed Henry Boot to undertake the Ryepark constructions works. Site clearance and ground works commenced in November 2025 and completion is expected in early 2028 (27 month build period). Drainage and foundation preparation works are currently underway.

Classification: NULBC UNCLASSIFIED Classification: NULBC UNCLASSIFIED

Aspire Town Houses – frames and roofing underway

Central Apartment Block framing and foundations underway

2.2Newcastle Town Deal

2.2.1 Karparc As with the previous schemes noted above Capital&Centric have appointed Clegg Construction to undertake the works to this development. Works started in early November and will be completed by the summer of 2027 (18 month build period). Works underway include the continuation of the concrete ‘cut-out’ works, preparation for new lift and stairwells and external facade steelworks. During excavation of the attenuation tank (for stormwater fall off) in the basement of the building human remains were found. The police were notified and investigations into them was undertaken. The coroner and the police both concluded that the remains are of sufficient age that any ‘foul play’ can be ruled out and that the site can be handed back to the contractor. Procurement of an archaeologist consultant is underway to begin the planning and licence process for the excavation to begin and a plan put in place should any further remains be found.

Classification: NULBC UNCLASSIFIED Classification: NULBC UNCLASSIFIED

New Entrance created at undercroft with Boots / Roebuck

Classification: NULBC UNCLASSIFIED Classification: NULBC UNCLASSIFIED

New Balustrade punch outs for apartment balcony

Classification: NULBC UNCLASSIFIED Classification: NULBC UNCLASSIFIED

New Atrium along central spine of the development to create ‘lightwell’

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
NEWCASTLE TOWN DEALReport 6.6 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 17 attended
MA
Councillor Martyn AshworthChair, present
RB
Councillor Robert Bettley-SmithCommittee Member, apologies, sent representative
AB
Alexandra BondOfficer, expected
JC
Councillor Jon ChamberlainCommittee Member, present
AC
Allan ClarkeOfficer, expected
CC
Councillor Charlie ClarkeCommittee Member, present
GD
Geoff DurhamOfficer, expected
GE
Councillor Gary EvansCommittee Member, apologies
GE
Georgina Evans-StadwardOfficer, expected
AF
Councillor Andrew FearCommittee Member, present
PH
Councillor Patricia HarrisonVice-Chair, present
SM
Simon McEnenyOfficer, in attendance

All 17 on the meeting page

On this subject at Newcastle-under-Lyme

Search all
  1. NEWCASTLE TOWN DEALThis decision
  2. Newcastle town centre public space protection order renewalApproved
  3. Newcastle town deal updateNoted
  4. Business improvement district, newcastle town centre - re-ballotNoted
  5. Newcastle town centre public space protection order renewalAgreed
  6. Newcastle town centre community safety partnershipNoted

More from Newcastle-under-Lyme Economy and Place Scrutiny Committee

All decisions
MeetingDecisionOutcome
18 Jun 2026 Minutes of previous meetingResolved : That the minutes of the meeting held on 19 th March 2026 be agreed as true and accurate record. Watch the ... Agreed Open
18 Jun 2026 Kidsgrove towndealResolved : That the report on the delivery of the Kidsgrove Town Deal Funds projects be noted. Watch the debate here Noted Open
18 Jun 2026 Pride in placeResolved : That the verbal update be noted. Watch the debate here Noted Open
18 Jun 2026 Work programmeResolved : That the Work Programme be discussed. Watch the debate here Decided Open