Resolved
Resolved : That the report on the delivery of the Newcastle Town Deal Funds projects and the three major town centre regeneration projects be noted. Watch the debate here
AI summaryNewcastle-under-Lyme scrutiny committee notes progress on £23.6m Town Deal and three town centre regeneration projects, with £18.4m spent so far.
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
Resolved : That the report on the delivery of the Newcastle Town Deal Funds projects and the three major town centre regeneration projects be noted. Watch the debate here
That:-
1. Scrutiny Committee notes this report on the delivery of the Newcastle Town Deal Funds projects and the three major town centre regeneration projects.
Reasons
To update the Scrutiny Committee on the progress with the various projects that are being funded or part funded through the Newcastle Town Deal as well as the three Town Centre regeneration projects.
1.1As reported to previous Scrutiny meetings, the Council has secured Future High Street Funding and Town Deal Funds for the redevelopment of several key regeneration sites across the Town Centre and the wider Borough.
2. Updates
2.1Town Centre Regeneration Projects
The current position regarding the three major regeneration projects is as follows:
2.1.1 Astley Place
Capital&Centric and their contractor AC1 commenced works (November 2025) with the development due to be completed in January 2027 (13 month build period).
Classification: NULBC UNCLASSIFIED Classification: NULBC UNCLASSIFIED
Works are ongoing with external facade works, internal courtyard landscaping and internal wall placements progressing at speed.
Merriel Street Elevation – external facade works
Internal Courtyard – levelling of area for landscaping
Classification: NULBC UNCLASSIFIED Classification: NULBC UNCLASSIFIED
Internal Courtyard Area and internal facing elevations
Internal wall fit out for apartments
Classification: NULBC UNCLASSIFIED Classification: NULBC UNCLASSIFIED
RyePark
2.1.2 McCarthy and Stone Residential Development
It is now anticipated that the works will commence in the summer of 2026 with completion in late 2027 to coincide with the adjacent Capital&Centric works.
2.1.3 Capital &Centric Ryepark Development
Capital&Centric have now appointed Henry Boot to undertake the Ryepark constructions works. Site clearance and ground works commenced in November 2025 and completion is expected in early 2028 (27 month build period). Drainage and foundation preparation works are currently underway.
Classification: NULBC UNCLASSIFIED Classification: NULBC UNCLASSIFIED
Aspire Town Houses – frames and roofing underway
Central Apartment Block framing and foundations underway
2.2Newcastle Town Deal
2.2.1 Karparc As with the previous schemes noted above Capital&Centric have appointed Clegg Construction to undertake the works to this development. Works started in early November and will be completed by the summer of 2027 (18 month build period). Works underway include the continuation of the concrete ‘cut-out’ works, preparation for new lift and stairwells and external facade steelworks. During excavation of the attenuation tank (for stormwater fall off) in the basement of the building human remains were found. The police were notified and investigations into them was undertaken. The coroner and the police both concluded that the remains are of sufficient age that any ‘foul play’ can be ruled out and that the site can be handed back to the contractor. Procurement of an archaeologist consultant is underway to begin the planning and licence process for the excavation to begin and a plan put in place should any further remains be found.
Classification: NULBC UNCLASSIFIED Classification: NULBC UNCLASSIFIED
New Entrance created at undercroft with Boots / Roebuck
Classification: NULBC UNCLASSIFIED Classification: NULBC UNCLASSIFIED
New Balustrade punch outs for apartment balcony
Classification: NULBC UNCLASSIFIED Classification: NULBC UNCLASSIFIED
New Atrium along central spine of the development to create ‘lightwell’
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
NEWCASTLE TOWN DEALReport | 6.6 MB | DownloadRead as text |
Follow Economy and Place Scrutiny Committee at Newcastle-under-Lyme and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 18 Jun 2026 | Minutes of previous meetingResolved : That the minutes of the meeting held on 19 th March 2026 be agreed as true and accurate record. Watch the ... | Agreed | Open |
| 18 Jun 2026 | Kidsgrove towndealResolved : That the report on the delivery of the Kidsgrove Town Deal Funds projects be noted. Watch the debate here | Noted | Open |
| 18 Jun 2026 | Pride in placeResolved : That the verbal update be noted. Watch the debate here | Noted | Open |
| 18 Jun 2026 | Work programmeResolved : That the Work Programme be discussed. Watch the debate here | Decided | Open |
| 19 Mar 2026 | Minutes of previous meetingResolved : That the minutes of the meeting held on 15 th December 2025 be agreed as a true and accurate record. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.