Newcastle-under-Lyme Borough Council
Planning Committee, Tuesday 26 March 2013 at 7.00pm

Stoke-on-Trent City Council and Newcastle-under-Lyme Borough Council Community Infrastructure Levy Viability Assessment - February 2013

Approved Planning 4 papers

Planning Committee approved this item on Tuesday 26 March 2013. Below is the council's own wording, with the papers it was decided on.

Item13

Resolved

That consideration of the business of the meeting be continued.] (1) That it be recommended that the Community Infrastructure Levy (CIL) rates be accepted for consultation purposes; (2) That it be recommended that the draft joint consultation proposals as set out in the report be approved; and (3) That a report be submitted to a subsequent meeting of the committee on the results of the consultation on the preliminary draft Charging Schedule to enable consideration of the next steps.
Word for word from the decision Newcastle-under-Lyme published for this meeting. Source: moderngov.newcastle-staffs.gov.uk

Follow this further

Built from Newcastle-under-Lyme's papers

What the report saysPro

Report to Planning Committee

Purpose of the report

To present the findings and recommendations of the Community Infrastructure Levy (CIL) Viability Study to help inform the Preliminary draft Charging Schedule.

To consider draft proposals to undertake joint public consultation on a Preliminary draft charging schedule with the City of Stoke-on-Trent.

Recommendations

1) That it be recommended to Cabinet that the Community Infrastructure Levy (CIL) rates are accepted for consultation purposes.

2) That it be recommended to Cabinet to agree the draft joint consultation proposals as set out in this report.

3) That a report be submitted to a subsequent meeting of the Committee on the results of the consultation on the Preliminary draft Charging Schedule and to approve the next steps.

Reasons To enable the views of the Planning Committee to be taken into account by Cabinet. To ensure the Council makes timely progress towards becoming a ‘charging authority’ under the Community Infrastructure Levy Regulations, 2011.

1.0Introduction

1.1The Community Infrastructure Levy (CIL) is designed to be a predictable charge, levied on all new buildings and extensions* according to their floor area and normally payable on commencement of the development. A minimum threshold of 100 sq m gross internal floor area (GIA) applies to non- residential development. This threshold does not apply to new dwellings. If a new dwelling is being created, it will pay CIL for any net increase in its gross internal floor area.

*A credit is allowed for any existing GIA which is demolished. Unlike section 106, CIL is non-negotiable (except in exceptional circumstances).

1.2Any money the Borough Council receives from CIL must be used for the purpose of funding the infrastructure required to support new development as part of the Authority’s development strategy. In the case of the Borough this is the adopted joint Core Spatial Strategy. The intention is to mitigate against the cumulative impacts of development rather than to address the site specific impacts of a development. CIL revenue is not tied to any particular infrastructure project and might include:-

 Highways and Transport Improvements;  Educational Facilities;  Health Centres;  Community Facilities & Libraries;  Sports and Recreation Facilities; and  Green Infrastructure

1.3It should be noted that there will not necessarily be sufficient funding from CIL to finance all infrastructure required to support new development. Furthermore the infrastructure identified as being funded by CIL can be updated by the Council on an annual basis.

1.4Setting CIL The CIL Regulations and Guidance have given local authorities flexibility in their approach to setting CIL. The Levy can be a fixed rate for development across the entire area, or can be set at a variable rate, e.g. different levy rates between the rural and urban areas where there is evidence of different levels of economic viability. Irrespective of how the rates are set, the Government makes it clear that the rates must appear to strike an appropriate balance between the desirability of raising money towards the cost of infrastructure and the economic viability of development.

1.5Authorities wishing to charge CIL are required to produce a CIL charging schedule to set out the rates that will be applied to new development and this must be subject to several rounds of consultation prior to being tested at an ‘examination in public’ by an independent person.

1.6The Charging Schedule must be founded on a robust evidence base which works to demonstrate that the CIL rates are sufficiently sensitive to different economic circumstances and likely development costs.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
13(b): Community Infrastructure Levy: appendix 1Appendix 500 KB Download
PDF
13(c): Community Infrastructure Levy: appendix 2Appendix 21 KB Download
PDF
13(d): Sipplement: Advance supplementary template on CILSupplementary 17 KB Download
PDF
Stoke-on-Trent City Council and Newcastle-under-Lyme Borough Council Community Infrastructure Levy Viability Assessment: February 2013Report 85 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 16 attended
EB
Councillor Eddie BodenCommittee Member, present
GC
Councillor George CairnsCommittee Member, present
MC
Councillor Michael ClarkeVice-Chair, present
AF
Councillor Andrew FearChair, present
MS
Councillor Mrs Sandra HambletonCommittee Member, present
TH
Councillor Trevor HambletonCommittee Member, present
AH
Councillor Ashley HowellsCommittee Member, apologies
NJ
Councillor Nigel JonesCommittee Member, apologies
IM
Councillor Ian MatthewsCommittee Member, present
MM
Councillor Miss Marion ReddishCommittee Member, present
MS
Councillor Miss Sophia BakerCommittee Member, apologies
DS
Councillor David StringerCommittee Member, present

All 16 on the meeting page

On this subject at Newcastle-under-Lyme

Search all
  1. Stoke-on-Trent City Council and Newcastle-under-Lyme Borough Council Community Infrastructure Levy Viability Assessment - February 2013This decision
  2. Application for other development - 1 copper close, stoke-on-trent. mr and mrs hopper. 22/00594/fulApproved
  3. Application for major development - land to north of shelton boulevard, the south of newport lane and in between festival way and the a500 (queensway), and land at grange lane, wolstanton city of stoke-on-trent council. 21/00574/fulDecided
  4. Application for other development - land off lowfield drive, stoke-on-trent. ee limited. 21/00377/tdetApproved
  5. Application for other development - land at chemical lane, stoke-on-trent. ee limited. 21/00379/tdetApproved
  6. Application for major development - land to north of shelton boulevard, the south of newport lane and in between festival way and the a500 (queensway), and land at grange lane, wolstanton. city of stoke-on-trent council. 20/00630/fulDecided

More from Newcastle-under-Lyme Planning Committee

All decisions
MeetingDecisionOutcome
18 Aug 2026 Minutes of previous meeting(s)That the minutes of the meeting held on 21 July, 2026 be agreed as a correct record. Agreed Open
18 Aug 2026 Application for major development - tadgedale quarry. wain homes north west. 24/00589/fulThat the application be permitted subject to the undermentioned conditions: (i) Variation of condition 2 to refer to ... Agreed Open
18 Aug 2026 Application for major development - land off bar hill road onneley. owl homes limited. 25/00897/remThat the application be permitted, subject to the undermentioned conditions: (i) Link to outline planning permission ... Approved Open
18 Aug 2026 Application for other development - 25-27 well st & 82 garden st, newcastle. marshallsay. 26/00051/couThat the application be refused for the following reasons: (i) Contrary to Policy HOU7 (Homes in Multiple Occupation)... Refused Open
18 Aug 2026 Five-year housing land supply update report 2026-31(i) That Members note the content of the five-year housing Land supply position statement (appendix 1) and agree that... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies