That no further action be taken in relation to the changing of the windows to top-opening casements subject to the following:- (a) The occupier/owners be notified by letter that the windows shall remain permanently obscure glazed to level 5, that no further changes to the window are permitted, and that casement/stay hinges are fitted to permanently restrict the opening to no more that 10-12cm within 4 weeks; (b) Should the window restriction in (a) above not be undertaken, or further unauthorised modifications to the windows are undertaken at a later date, Legal Services be instructed to take enforcement action to secure full and permanent closure of the windows in line with the original Section 106 agreement; and (c) If appropriate, invite occupiers to provide a unilateral obligation to secure (a) above.
Word for word from the decision Newcastle-under-Lyme published for this meeting.Source: moderngov.newcastle-staffs.gov.uk
The purpose of the report is to determine whether enforcement action is necessary or appropriate in relation to the following matter – the breach of a Section 106 agreement relating to fixed obscure glazed windows at Block E Portland Mews (linked to permission 94/00872/FUL).
Recommendation
No further action be taken in relation to the changing of the windows to top opening casements subject to the following;
1. The occupier/owners be notified by letter that the windows shall remain permanently obscure glazed to level 5, that no further changes to the window are permitted, and that casement /stay hinges are fitted to permanently restrict the opening to no more that 10-12 cm within 4 weeks 2. Should the window restriction in 1 above not be undertaken, or further unauthorised modifications to the windows are undertaken at a later date, Legal Services be instructed to take enforcement action to secure full and permanent closure of the windows in line with the original Section 106 agreement. 3. If appropriate, invite occupiers to provide a unilateral obligation to secure step 1 above.
Background Information
Planning History
Permission was granted for the final phase of this Portland Mews development by Planning Committee in 1994, and relates to four flats arranged in two octagonal blocks. There were issues with the construction of the flats at the time where the developer made several unauthorised internal and external changes to the design and layout which were not approved. These included, amongst other matters the addition of windows to allow additional light into the properties given that the layout had been changed and the properties were now ‘handed’. Eventually agreement was reached that the additional windows would be kept obscure glazed and non-opening.
A complaint was received from a local resident whose property borders the site and who would be overlooked should the windows referred to above be replaced. The complaint centred around the replacement of the single fixed obscure glazed windows, and their replacement with top opening casements (opening outwards), but there is no restriction on the opening imposed through a condition of any planning permission. The complainant suggests that the replacement of the windows is in breach of the Section 106 agreement signed by the developer which required the windows specified to remain fixed and obscure glazed. The complainant advises that the change of the windows directly affects her privacy and no longer feels safe or comfortable in using her lounge and bedroom for fear of residents of the flats being able to see into her property.
The complaint was originally received late September 2012, but officers were unable to locate the Section 106 agreement based on the information provided at the time. Subsequent enquiries identified the relevant documents, but the complaint was escalated when a resident of the adjacent flat instructed contractors to replace their windows also. Officers attended the site immediately and liaised with the owner of the property and contractor and advised that the continuation of the alterations would be entirely at his own risk and that this was a breach of the Section 106 agreement in place. The owner instructed the contractor to continue, but did advise that if the Authority wishes for the windows to be replaced/modified so they do not open, then he would comply with this request.
The reasons stated for the replacement of the windows are purely for improving internal ventilation which is allegedly very poor especially during the winter months as the flats have to rely on extractor fans and/or opening a first floor French window. The current flat owners claim to have not been advised of the requirements of the Section 106 agreement. The agreement is registered as a local land charge which would be revealed upon a Search of the Local Land Charges Register..
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.