Resolved
That the Committee should receive further reports on financial matters surrounding Gatedale and its Receivers and the Multi-story car park.
Finance, Resources and Partnerships Scrutiny Committee decided this item on Monday 20 May 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Committee should receive further reports on financial matters surrounding Gatedale and its Receivers and the Multi-story car park.
1. FINANCIAL AND PERFORMANCE MANAGEMENT REPORT TO END OF QUARTER FOUR (March) 2013
Submitted by: Head of Finance and Head of Business Improvement & Partnerships
Portfolio: Communications, Transformation & Partnerships; Finance and Budget Management
Wards Affected: All
Purpose To provide Transformation and Resources Overview & Scrutiny Committee with the Performance Review for the 2012/13 Fourth Quarter (January-March).
Recommendations (a) That Members note the contents of the report and recommend that the Council continues to monitor and scrutinise performance alongside finances. (b) That Members note that the appendix is a new style of performance report to be further developed for 2013-14 as detailed in line with the Performance Management Framework Review and the Council Plan 2013-14 to 2015-16. (c) That Members feedback their views and comments to members of Cabinet prior to the May meeting where this appendix will also appear in the Financial & Performance Management report.
Reasons These monitoring reports provide information about the corporate performance of individual council services.
1. Background, issues and options
1.1This report provides Members with a detailed update on how the Council has performed during the fourth quarter of 2012/13 by presenting performance data set in a financial context.
1.2The Council approved a General Fund Revenue Budget of £14,260,980 on 22 February 2012. The actual position compared to this budget is continuously monitored by managers in order to detect any significant variances of expenditure or income from the approved amounts contained in the budget. Regular reports are made available to members by the Portfolio Holder for Finance and Budget Management informing them of the current position, highlighting any significant factors giving rise to variances.
1.3A Capital Programme totalling £18,480,100, covering the two years 2011/12 to 2012/13, was approved at the same Council meeting. Of this total, £4,457,200 was estimated to be spent in 2012/13.
1.4This report also provides detailed analysis of performance in the fourth quarter, focusing on key performance indicators.
1.5A summary of the overall picture is presented in section 5 of this report. Performance is progressing well, with the majority of targets currently met. 2. Revenue Budget Position
2.1The outturn is not yet available because, although the 2012/13 accounts now include all the payments that have actually been made and all of the cash actually received up to and including 31 March 2013, there are still a number of adjustments and accounting entries which remain to be made in order to complete the year’s accounts. These adjustments will be finalised over the next few weeks.
2.2Current indications are that the final revenue budget outturn will be in line with the approved budget.
2.3The Square, High Street, Newcastle is let to Gatedale Limited (in liquidation) on a 125 year lease which commenced in 1998. Since July 2001 the tenant has been paying £100,000 per annum to the Council. The rent review provisions within the lease provide that as from September 2005 a minimum of £100,000 per annum is to be paid to the Council and dependant on the income and expenditure in respect of the car park, shopping mall and cinema an extra payment may be payable.
Following prolonged negotiations with the LPA Receiver appointed to act for Gatedale’s creditors, your Officers have provisionally agreed that an additional sum of £393,278 is to be paid to the Council for the period 2005 to 2012 (end of).
4. Investment Counterparties
4.1Investment counterparties with whom money is invested, as at 31 March 2013 are as follows (with the parent company shown in brackets, where applicable):
Halifax Bank of Scotland (Lloyds Banking Group) Heritable Bank (Landsbanki) Nationwide Building Society
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Financial and Performance Management Report, Quarter 4 2012/13Report | 40 KB | DownloadRead as text |
PDF |
NBC Qtr 4 performance monitoring report period 2012 Q4 v10 02 05 13Report | 109 KB | Download |
Follow Finance, Resources and Partnerships Scrutiny Committee at Newcastle-under-Lyme and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 24 Jan 2018 | Minutes of previous meetingThat the minutes of the meeting held on 27 November 2017 be agreed as a correct record. | Agreed | Open |
| 24 Jan 2018 | Treasury Management Strategy 2018-19Agreed: The Committee approved the strategy for submission to Full Council on 21 February 2018. | Agreed | Open |
| 24 Jan 2018 | Revenue and Capital Budgets 2018-2019Agreed: That the budget for replacement of waste bins be examined further by Cabinet. | Agreed | Open |
| 24 Jan 2018 | Date of next meetingIt was agreed that, due to a lack of business to be transacted, the next meeting of the Finance, Resources and Partne... | Agreed | Open |
| 27 Nov 2017 | Minutes of previous meetingThat the minutes of the meeting held on 5 October 2017 be agreed as a correct record. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.