FINANCIAL AND PERFORMANCE REVIEW REPORT - THIRD QUARTER 2025/26

Noted Finance 3 papers

AI summaryNewcastle under Lyme Borough Council's scrutiny committee noted the Q3 2025/26 performance report, with 82% of targeted indicators met, six below target, and the flats recycling rollout flagged amber.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCommittee noted the report and will keep monitoring and challenging performance.
Money£19.730m General Fund Revenue BudgetApproved on 12 February 2025.
What happens nextContinue scrutinyCommittee to keep monitoring and challenging performance.
Who it affectsResidents and businessesPerformance information is shared with members, businesses and residents.

What was decided

The committee noted the contents of the Q3 2025/26 report and its two appendices on finance and performance. Report 4.1, 15.1

The committee will continue to monitor and challenge the council's service and financial performance for the period. Report 4.1

Why

To enable financial and performance information to be presented for continued scrutiny and to encourage improvement in council delivery. Report 5.1, 4.1

The council has a Best Value duty to provide value for money services. Report 7.1

What happens next

Officers will continue to monitor the six off target service areas and take steps to address performance where feasible and appropriate. Report 3.1, 2.3

The rollout of recycling and food waste services to flats is scheduled for completion in April 2026, after which overall recycling performance will be reassessed. Report 3.3

The Capital Programme Review Group will continue to meet every two months to monitor the capital programme, with quarterly reports to Cabinet. Report 10.2

The money

  • £19.730m General Fund Revenue Budget approved on 12 February 2025. Report 1.2

Options considered

  • Chosen: No other option at this time; presentation of information is continually reviewed.. Officers felt no other option was necessary for consideration. Report P17

Implications

  • Financial: Any positive year end variance on the General Fund Revenue Account will transfer to the Budget Support Fund for future use; any adverse variance will be met from that fund. Report 9.1
  • Risk: Changing market conditions are the greatest risk to the revenue budget, particularly for income from discretionary services and for waste and recycling volumes that fluctuate. Report 10.1
  • Risk: The capital programme needs regular monitoring to identify any projects slipping behind their planned completion dates. Report 10.2
  • Equalities: No differential equality issues arise directly from this report. Report 8.1

Who and where

  • Residents and businesses in the borough, who are given contextual performance information Report P5
  • Users of council facilities and waste and recycling services Report 10.1
  • Council staff delivering the monitored services and priority projects Report 2.3, 2.5, 3.1

Timeline

  • 12 February 2025: Council approved the General Fund Revenue Budget of £19.730m. Report 1.2
  • April 2025 to December 2025: Q3 reporting period covered by the report. Report 2.1
  • April 2026: Scheduled completion of the rollout of recycling and food waste services to flats. Report 3.3

Plain English for the jargon

  • Simpler Recycling: Government requirements on recycling collections, which the council says it is fully compliant with two years early.
  • Budget Support Fund: A reserve that absorbs year end variances on the General Fund Revenue Account.
  • Capital Programme Review Group: Officer group that meets every two months to monitor progress of the capital programme.
  • Amber rating: Status flagging a priority action that needs attention but is not off track.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item4

Resolved

Resolved : That the contents of the report and appendices be noted and that the Council’s service and financial performance for this period continue to bed monitored and challenged. Watch the meeting here
Word for word from the decision Newcastle-under-Lyme published for this meeting. Source: moderngov.newcastle-staffs.gov.uk

Follow this further

Built from Newcastle-under-Lyme's papers

What the report saysPro

Report to Finance, Assets & Performance Scrutiny Committee

Background

1.1This quarterly report provides Members with a detailed update on how the Council has performed during the quarter by presenting performance data and progress summaries set within a financial context. The report provides broad financial information (Appendix A) and also details service performance (Appendix B) for the period to the end of quarter three in 2025/26.

1.2The Council approved a General Fund Revenue Budget of £19.730m on 12 February 2025. Further financial information is provided in Appendix A.

2. Performance

2.1The Q3 report (April 2025 to December 2025) has been produced using business intelligence tools in order to automate and improve the monitoring, analysis and reporting of Council performance. The indicators included are those agreed as part of the new Council Plan and reflect the priorities for the Borough. In addition to reporting on key performance indicators, the report also includes progress summaries for each priority action, detailing the progress with the delivery of planned activities.

1 2.2 Contextual performance information is provided (indicators without a target), not only to ensure the monitoring of the corporate activities of the Council, but also to inform Members, businesses and residents of performance in their local area that the Council cannot directly control.

2.3Any indicators failing to meet the set targets include a comment explaining the reasons behind the performance and what steps are being taken to ensure improvement in the future.

2.4For this report a total of 50 indicators were monitored, 17 of these indicators were contextual and had no set target. Of these contextual measures that had historic trend data available, 46% showed an improvement or maintenance when compared to the previous year’s performance. Of the remaining 33 indicators, the proportion which have met their target during this period stands at 82%, with the remaining 18% falling short of target. Five off target measures this quarter show a negative trend when comparing to the same time period of the previous financial year with one off-target measures showing an improvement from the year before. It must also be noted that a small number of these ‘off target’ measures have more stretching targets this year, in line with benchmarking findings and council ambition. In terms of trend data overall, with measures where there is comparable data, the proportion of indicators showing an improvement or maintenance of the previous year’s performance stands at 56%.

2.5Five project/actions have been classified as completed by their respective owners this quarter

3. Issues

3.1There are six indicators ‘off target’ this quarter. Officers do not view these give rise to serious cause for concern (see commentaries within Appendix B). The management of each of the service areas concerned continue to monitor and take steps to address performance improvement where feasible and appropriate.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Q3 Finance and Performance 2025-26Appendix A 246 KB Download
PDF
Corporate Performance Quarter 3 2025-26 v2.2Appendix B 4.1 MB Download
PDF
FINANCIAL AND PERFORMANCE REVIEW REPORT: THIRD QUARTER 2025/26Report 187 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 22 attended
MH
Councillor Mark HollandChair, present
AB
Councillor Amy BryanVice-Chair, expected
AP
Councillor Andrew ParkerCommittee Member, apologies, sent representative
AT
Councillor Andrew TurnockCommittee Member, present
PW
Councillor Paul WaringCommittee Member, present
M-
Mayor - Councillor Robert Bettley-SmithCommittee Member, apologies, sent representative
MS
Councillor Mike StubbsCommittee Member, present
DA
Councillor David AllportCommittee Member, apologies
AL
Councillor Annabel LawleyCommittee Member, apologies
DG
Councillor David GrocottCommittee Member, present
LD
Councillor Lynn DeanCommittee Member, apologies
DM
Deputy Mayoress. Councillor Susan BeestonSubstitute, present as substitute

All 22 on the meeting page

On this subject at Newcastle-under-Lyme

Search all
  1. FINANCIAL AND PERFORMANCE REVIEW REPORT - THIRD QUARTER 2025/26This decision
  2. Financial and performance review report q1 2026-27Approved
  3. Financial and performance review report - fourth quarter 2025/26Noted
  4. Financial and performance review report - third quarter 2025/26Noted
  5. Financial and performance review report - second quarter 2025-26Noted
  6. Financial and performance review report - first quarter 2025/26Noted

More from Newcastle-under-Lyme Finance, Assets & Performance Scrutiny Committee

All decisions
MeetingDecisionOutcome
2 Jul 2026 Minutes of a previous meetingResolved : That the minutes of the meeting held on 26 th March 2026 be agreed as a true and accurate record. Watch th... Agreed Open
2 Jul 2026 Work programmeThat the work Programme be noted and the additions be received. Watch the debate here Noted Open
26 Mar 2026 Minutes of a previous meetingResolved : That the minutes of the meeting held on 15 th January 2026 be agreed as a true and accurate record. Agreed Open
26 Mar 2026 Town deal and future high street funds updateResolved : That the report on the delivery of the Town Deal and Future High Street Funds projects be noted. Watch the... Noted Open