CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Newcastle-under-Lyme Borough Council
Cabinet, Wednesday 17 July 2013 at 7.00pm

Newcastle Town Centre Public Realm Project

Agreed Executive 1 paper

Cabinet agreed this item on Wednesday 17 July 2013. Below is the council's own wording, with the papers it was decided on.

Item12

Resolved

The Chief Executive agreed that a comprehensive report be made available for the Cabinet meeting in October detailing how the project had been run to date and the problems that had led to it being behind schedule. This document would be used as a learning tool for future projects.
Word for word from the decision Newcastle-under-Lyme published for this meeting. Source: moderngov.newcastle-staffs.gov.uk

Follow this further

Built from Newcastle-under-Lyme's papers

What the report saysPro

Report to Cabinet

Purpose of the report

To seek Member approval to formalise the allocation of the existing Capital Programme for Town Centre Works to the Newcastle Town Centre Public Realm project.

Recommendations a) That the existing Capital Programme allocation for Town Centre Works is allocated to the public realm project. b) That the Executive Director for Regeneration and Development is authorised in conjunction with the Portfolio Holder for Economic Development, Regeneration and Town Centres to procure the required contracts to deliver the project within the agreed budget.

Reasons

This report outlines the current position with regard to the Town Centre Public Realm Project and outlines the requirements in order that the project can commission appropriate works to be completed to a standard that is fit for purpose and minimises the requirement for future maintenance works in the project area. It is important that officers are given sufficient direction to enable the relevant aspects to be commissioned within a timely manner and this requires the Cabinet to allocate sufficient financial resources. The report outlines the revised timescales and explains the reasons for the budgetary requirement. Additionally, the current approved plans include extending the market trading area into Hassell Street and this requires the Council to amend the designated formal trading area.

Background

1.1The Newcastle Town Centre Public Realm (public realm) project is a joint project with Staffordshire County Council that is intended to bring economic benefit to Newcastle town centre by closing Hassell Street to through traffic during the day and refurbishing Newcastle market. The business case for the project has been previously set out in a number of Cabinet reports.

1.2To date the focus of work has been on preliminary actions to remove various forms of traffic from Hassell Street in the daytime. This has included changes to the bus station, new traffic signals and a bus lane on Barracks Road; plus changes to the entrance of the Ironmarket to enable a taxi rank to operate in this area. These works have been 100% funded by Staffordshire County Council.

1.3More recently, works have taken place at the lower end of High Street to remove market stalls and introduce parking for disabled drivers, loading bays and a taxi rank in that area. These works have been 100% funded by Newcastle Borough Council. 1.4 Planning permission has been obtained for the new market stalls and a prototype stall which was on site by the Guildhall until earlier this year has been used to make design refinements in co-operation with market traders.

1.5The project focus is now on the core area of High Street, Hassell Street and Friars Street. Work is being completed to produce final detailed designs for the landscaping works that are required in the core area. This, combined with County Council approved designs for the sub-base construction and new drainage connections will be used by the County Council’s contractor to price the contract for this element of the project. Alongside this, the Borough Council will manage the procurement and placement on site of new market stalls.

2. Issues

2.1A recent review of the Council’s Capital Programme allocation for the NTCPR project has highlighted the requirement to formalise a proposed virement of funding between items in the Town Centre Works Capital Programme Allocation.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Newcastle Town Centre Public Realm ProjectReport 60 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 8 attended
ME
Councillor Mrs Elsie BatesCommittee Member, present
MA
Councillor Mrs Ann BeechCommittee Member, present
TK
Councillor Tony KearonCommittee Member, present
GS
Councillor Gareth SnellChair, present
TT
Councillor Terry TurnerCommittee Member, present
MS
Councillor Mike StubbsVice-Chair, present
JW
Councillor John WilliamsCommittee Member, present
NL
Nick LamperSecretary, expected

On this subject at Newcastle-under-Lyme

Search all
  1. Newcastle Town Centre Public Realm ProjectThis decision
  2. Newcastle town dealNoted
  3. Newcastle town centre public space protection order renewalApproved
  4. Newcastle town deal updateNoted
  5. Business improvement district, newcastle town centre - re-ballotNoted
  6. Newcastle town centre public space protection order renewalAgreed

More from Newcastle-under-Lyme Cabinet

All decisions
MeetingDecisionOutcome
15 Sep 2026 Minutes of previous meetingsThat the Minutes of the meeting held on the 4 August be agreed as a correct record. Agreed Open
15 Sep 2026 Walleys quarry odour updateThat the contents of the update report be noted. Noted Open
15 Sep 2026 Local government reorganisation update(i) That the content of the letter from the Minister for Devolution received on 7 th September 2026, reviewing decisi... Noted Open
15 Sep 2026 Recycling & waste re-routing(i) That the recycling and waste collection day changes for approximately 22,000 households in the south of the borou... Approved Open
15 Sep 2026 Improving safety and welfare infrastructure at knutton lane depot(i) That the works and budget necessary to refurbish and upgrade the Knutton Lane depot to improve health & safety we... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies