Resolved
Resolved :- That the application be deferred to the next meeting to be held on 10 December, 2013 to enable matters to be further investigated.
Planning Committee deferred this item on Tuesday 19 November 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved :- That the application be deferred to the next meeting to be held on 10 December, 2013 to enable matters to be further investigated.
REFUSE for the following reasons:-
1. The development does not include adequate parking provision and has the potential to exacerbate existing on street parking problems in the area resulting in highway safety concerns. 2. The development does not include adequate space within the site for the turning of a refuse vehicle thereby resulting in highway safety concerns due to the need to service the site from the highway. 3. In the absence of a secured planning obligation the development fails to make an appropriate contribution to the Newcastle (urban) Transport and Development Strategy (NTADS) which seeks to improve local accessibility and promote the most sustainable modes of travel. 4. In the absence of a secured planning obligation and having regard to the likely additional pupils arising from a development of this scale and the capacity of existing educational provision in the area, the development fails to make an appropriate contribution towards primary school provision. 5. In the absence of a secured planning obligation the development fails to make an appropriate contribution towards the provision of affordable housing which is required to provide a balanced and well functioning housing market. 6. In the absence of a secured planning obligation the development would not make an appropriate financial contribution towards the development, improvement and maintenance of off-site public open space.
The development is acceptable in principle, has an acceptable design and layout and achieves adequate amenity levels for the occupiers of the proposed properties and the existing adjoining properties. The development does not include adequate parking provision and has the potential to exacerbate existing on street parking problems in the area resulting in highway safety concerns. Additional there is inadequate space within the site for the turning of a refuse vehicle thereby resulting in highway safety concerns due to the need to service the site from the highway.
The application site contains a Sycamore that is protected by a Tree Preservation Order and additional information has been sought to establish whether the retaining wall within the root protection area of the tree will have an adverse impact on that tree. An update will be provided. The proposed development of this vacant site introduces additional trips on the highway network and in the absence of a contribution to NTADS appropriate improvements to local accessibility would not be secured nor would sustainable modes of transport be promoted. Additionally the development would result in additional pressure on limited primary school places of the schools whose catchment area it is located and would place pressure on off-site public open space and in the absence of a financial contribution such adverse impacts would not be appropriately mitigated against.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
00785FUL Land adj 31 Banbury Street, Butt Lane ESMReport | 59 KB | DownloadRead as text |
PDF |
13 785Report | 197 KB | Download |
PDF |
Application for Major Development: Land adjacent to 31 Banbury Street, Butt Lane, Browns (Shopfitting and Constructions) Ltd, 13/0078/FULReport | 22 KB | Download |
Follow Planning Committee at Newcastle-under-Lyme and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 18 Aug 2026 | Minutes of previous meeting(s)That the minutes of the meeting held on 21 July, 2026 be agreed as a correct record. | Agreed | Open |
| 18 Aug 2026 | Application for major development - tadgedale quarry. wain homes north west. 24/00589/fulThat the application be permitted subject to the undermentioned conditions: (i) Variation of condition 2 to refer to ... | Agreed | Open |
| 18 Aug 2026 | Application for major development - land off bar hill road onneley. owl homes limited. 25/00897/remThat the application be permitted, subject to the undermentioned conditions: (i) Link to outline planning permission ... | Approved | Open |
| 18 Aug 2026 | Application for other development - 25-27 well st & 82 garden st, newcastle. marshallsay. 26/00051/couThat the application be refused for the following reasons: (i) Contrary to Policy HOU7 (Homes in Multiple Occupation)... | Refused | Open |
| 18 Aug 2026 | Five-year housing land supply update report 2026-31(i) That Members note the content of the five-year housing Land supply position statement (appendix 1) and agree that... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.