Resolved
(a) That prior approval is required (b) That details of the method of demolition and restoration of the site be approved
Planning Committee approved this item on Thursday 3 April 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
(a) That prior approval is required (b) That details of the method of demolition and restoration of the site be approved
SUPPLEMENTARY REPORT TO THE PLANNING COMMITTEE rd 3 April 2014
Agenda item 10 Application ref 14/00188/DEEM4
Former Sainsbury’s Site, Ryecroft
Comments of the Environmental Health Division and the Highway Authority were have been received.
The Environmental Health Division (EHD) indicates that there is a significant potential for noise and vibration to cause disturbance to the surrounding area. They advise that these issues will be controlled through the tendering and contractual arrangements that will be in place as the contractor will be responsible for applying to the Council for prior consent under Section 61 of the Control of Pollution Act 1974. Additionally the hours in which demolition work may take place will be restricted as the selected contractor will need to be registered to an appropriate site management/good neighbour scheme. The tendering and contractual arrangements also require the contractors to mechanically sweep the road from the site to address mud and dust on the highway. Due to the proposed hours of work, it is unlikely that any light nuisance would occur. They have no objections to the application.
The Highway Authority (HA) have no objections subject to a condition requiring the submission of a Traffic Management Plan detailing the management and routeing of demolition traffic, delivery times, internal compound arrangements and wheel wash facilities.
The Conservation Advisory Working Party have no objections to the demolition but has concerns over the loss of car parking and does not want solid boarding
Your Officers’ comments
The EHD highlight that whilst the proposed demolition has the potential to create noise/vibration, mud and dust and light nuisance these are suitably controlled through other legislation or are specified in the method of demolition and restoration included within the submission. As such the matters that are raised do not need to be addressed through conditions on any prior approval that is granted.
The HA recommend a condition that relates to highway safety, which is not a matter that can be addressed through this application process. The comments of the HA should be passed to the applicant for information, however.
Whilst CAWP is concerned about the loss of car parking, there is no loss relative to that currently provided (the upper floors of the multi-storey having been closed for sometime), and the loss of car parking is not considered to be a matter that can be addressed through this particular application process anyway. The submission indicates that the security boarding, to a height of 1.8m, may be erected if it is considered that the appearance of the site is not aesthetically suitable without it. To ensure that consideration is given to the final appearance of the boarding it is recommended that a condition is attached requiring details of any hoardings that may be erected to be approved by the Local Planning Authority.
Recommendation (a) remains as set out in the main agenda report, recommendation (b) is amended so to remain one of approval but to now include the condition referred to above, and an additional recommendation is made that the comments of the HA are passed to the applicant with any decision.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
00188DEEM4 demolition of Sainsbury's ESMReport | 25 KB | DownloadRead as text |
PDF |
14 188Report | 210 KB | Download |
PDF |
Application for other Development; Former Sainsburys Site; NuLBC; 14/00188/DEEM4Report | 38 KB | Download |
Follow Planning Committee at Newcastle-under-Lyme and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 18 Aug 2026 | Minutes of previous meeting(s)That the minutes of the meeting held on 21 July, 2026 be agreed as a correct record. | Agreed | Open |
| 18 Aug 2026 | Application for major development - tadgedale quarry. wain homes north west. 24/00589/fulThat the application be permitted subject to the undermentioned conditions: (i) Variation of condition 2 to refer to ... | Agreed | Open |
| 18 Aug 2026 | Application for major development - land off bar hill road onneley. owl homes limited. 25/00897/remThat the application be permitted, subject to the undermentioned conditions: (i) Link to outline planning permission ... | Approved | Open |
| 18 Aug 2026 | Application for other development - 25-27 well st & 82 garden st, newcastle. marshallsay. 26/00051/couThat the application be refused for the following reasons: (i) Contrary to Policy HOU7 (Homes in Multiple Occupation)... | Refused | Open |
| 18 Aug 2026 | Five-year housing land supply update report 2026-31(i) That Members note the content of the five-year housing Land supply position statement (appendix 1) and agree that... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.