- ( i ) That, subject to the applicant entering into a Section 106 Agreement by 7 October, to secure a routeing agreement, permit 13/00245/FUL subject to the two conditions set out in the report. If a Section 106 Agreement is not secured by the due date, refuse for the reason set out in the report unless the Head of Planning has extended the period. (ii) That, unless the applicant enters into a Section 106 Agreement by 7 October to secure a routing agreement for vehicles transporting miscanthus to and from the unauthorised building, enforcement action should be taken to seek removal of the building referred to. If the building is immune from action, the matter should be reported back to the Planning Committee.
Word for word from the decision Newcastle-under-Lyme published for this meeting.Source: moderngov.newcastle-staffs.gov.uk
OLD SPRINGS FARM, STONEYFORD 13/00245/FUL & 12/00068/207C2
The purpose of this report is twofold;
1. To enable the Planning Committee to consider whether the terms of a Section 106 (S106) obligation which the applicant is prepared to enter into and which involves the routeing of vehicles are acceptable and grant planning permission for the retention of an agricultural building for the chopping and storage of miscanthus (application reference 13/00245/FUL) subject to the obligation being completed within an agreed period of time, or alternatively refuse that application. 2. To decide whether enforcement action should be taken with respect to a breach of planning control consisting of the unauthorised construction of a different crop storage barn, not in accordance with the details approved under planning permission reference 09/00085/FUL, and an alleged breach of the routeing agreement secured through a S106 obligation in association with that permission.
The site lies within the open countryside and within an Area of Active Landscape Conservation all as indicated on the Local Development Framework Proposals Map.
RECOMMENDATION th A) (A) (1) Subject to the applicant entering into a S106 obligation by 7 October 2014 that secures a routeing agreement for vehicles transporting miscanthus to and from the building referred to in application 13/00245/FUL, B) C) Permit that application subject to the following conditions:-
a) Within two months of the date of the planning permission details of the re-grading and landscaping of the excavated material or its distribution elsewhere in the site is to be submitted and approved, and implemented within four months of the date of that approval; and
(b) Existing site access to be resurfaced in a bound material for a minimum distance of 10 m rear of the highway boundary and maintained as such; and
(2) That, should the matter referred to in (1) above not be secured in the specified period, the Head of Planning be authorised to refuse the application on the grounds that, in the absence of such an obligation, the development would have a detrimental impact upon highway safety and the amenity of the locality including the enjoyment of the national cycle route, and the character of the Conservation Area through which Tyrley Road passes; or, if he considers it appropriate, agree to extend the period of time within which the obligations can be secured. th B) Unless the applicant entering into a S106 obligation by 7 October 2014 that secures such a routeing agreement for vehicles the Head of Business Improvement, Central Services and Partnerships be authorised to issue enforcement and all other notices and to take and institute on behalf of the Council all such action and prosecution proceedings as are authorised by and under the Town and Country Planning Act 1990 for the following;
a. Removal of the building within 6 months.
Reason for recommendation and the taking of enforcement action
The applicant has indicated a willingness to enter into an obligation which restricts the routeing of the vehicles associated with the use of the building that is the subject of application reference 13/00245/FUL. Provided that a suitably worded obligation is secured within a limited, specified period of time it is considered that planning permission can be issued and that any highway safety concerns arising from that development would be suitably addressed. In the absence of an obligation that similarly restricts the vehicular movements associated with the building that was constructed not in accordance with the approved plans to planning permission 09/0137/FUL it is considered that the development has the potential to have an adverse impact upon highway safety and the amenity of the locality including the enjoyment of the national cycle route, and the character of the Conservation Area through which Tyrley Road passes. Enforcement action is therefore justified unless such an obligation is secured.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.