Resolved
That the appeal and costs decisions be noted.
Planning Committee noted this item on Tuesday 7 October 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
That the appeal and costs decisions be noted.
APPEAL BY MR D MORRIS AGAINST AN ENFORCEMENT NOTICE ISSUED RELATING TO AN UNAUTHORISED TWO STOREY EXTENSION AT XJK JAGUAR LIMITED, CROSS HEATH
Enforcement Ref. No 09/00230/207C3 & 14/00002/ENFNOT
Appeal Decision Allowed th Date of Appeal Decision 19 August 2014 st The full text of the appeal decision which followed and Informal Hearing held on 31 July 2014 is available to view on the Council’s website (as an associated document to appeal reference 14/00002/ENFNOT) and the following is only a brief summary.
The Inspector sought clarification as to what was unlawful – the extension as a whole or the ground floor works. It was confirmed by representatives of the Council that no material harm arose from the first floor extension sufficient to require enforcement action. The Inspector considered that the enforcement notice could be amended without injustice to relate expressly to the building works at ground floor.
The Inspector went on to consider the two grounds of appeal; that it was too late to take enforcement action (ground (d)) and that planning permission should be granted (ground (a)):
Ground (d)
• The appellants’ provided a statement that the work was completed in April 2009 (which was more than 4 years before the notice was issued) was not in the form of a sworn statutory declaration and there was no supporting documentary evidence which confirmed and corroborated the dates on which it was said that the ground floor works were carried out. • The Council provided contradictory evidence which was a log of a telephone call in December 2009 (less than 4 years before the notice was issued) which stated that the windows were being put into the ground floor area and it looked like they were making it into a room. In addition a written log was provided of a site inspection that took place in January 2010 which indicated that the site manager had confirmed that substantive work was completed during Christmas and New Year. • The Inspector was faced with two irreconcilable accounts of the date of the ground floor works. The burden of proof is with the appellant and the Inspector considered that the appellants’ evidence failed the required tests as the Council’s evidence contradicted their account of the date of completion of the works and it was not sufficiently precise and unambiguous to demonstrate the case on the balance of probabilities. • The Inspector concluded that the ground (d) appeal must fail.
Ground (a)
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Appeal Decision: XJK Enforcement Notice; 09/00230/207C3Decisions | 35 KB | DownloadRead as text |
Follow Planning Committee at Newcastle-under-Lyme and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 18 Aug 2026 | Minutes of previous meeting(s)That the minutes of the meeting held on 21 July, 2026 be agreed as a correct record. | Agreed | Open |
| 18 Aug 2026 | Application for major development - tadgedale quarry. wain homes north west. 24/00589/fulThat the application be permitted subject to the undermentioned conditions: (i) Variation of condition 2 to refer to ... | Agreed | Open |
| 18 Aug 2026 | Application for major development - land off bar hill road onneley. owl homes limited. 25/00897/remThat the application be permitted, subject to the undermentioned conditions: (i) Link to outline planning permission ... | Approved | Open |
| 18 Aug 2026 | Application for other development - 25-27 well st & 82 garden st, newcastle. marshallsay. 26/00051/couThat the application be refused for the following reasons: (i) Contrary to Policy HOU7 (Homes in Multiple Occupation)... | Refused | Open |
| 18 Aug 2026 | Five-year housing land supply update report 2026-31(i) That Members note the content of the five-year housing Land supply position statement (appendix 1) and agree that... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.