( i ) That a grant of £5000 for the repair of the south aisle roof of St James’ Church, Audley be approved subject to the appropriate standard conditions. (ii) That a grant of £180 for the repair of Madeley War Memorial and reinstatement of the bayonet on that memorial be approved subject to the appropriate standard conditions.
Word for word from the decision Newcastle-under-Lyme published for this meeting.Source: moderngov.newcastle-staffs.gov.uk
That Planning Committee approves the following grants:-
1. £5,000 for the repair of the South Aisle roof of St James’ Church, Audley, subject to the appropriate standard conditions
2. £180 for the repair of the Madeley War Memorial and reinstatement of the bayonet on that memorial, subject to the appropriate standard conditions
Purpose of report
To consider two applications for financial assistance which are recommended by the Council’s Conservation Advisory Working Party.
1. St James’ Church, Audley
This building is a Grade II* Listed Building. The project is to fix leaks in the south aisle roof. The slates will be removed, new sarking membrane installed and tiles refitted. The guttering has been found not to be sufficient during periods of heavy rain so the size of the guttering will be increased and an additional downpipe installed.
The total cost of the work is £44,450 including VAT, contingencies and mitigation for bats (the latter of which is not grant eligible work). Eligible costs total £41,210 including VAT. The works are eligible for grant up to 20% of the total costs which comes to £8,242 however the maximum grant that can be awarded under the rules of the Fund is £5,000. This is the recommended grant.
2. Madeley War Memorial
This project by Madeley Parish Council is to reinstate the soldier’s bayonet on the memorial which was stolen some years ago and to repair damage to the soldier’s hand. The memorial is a Grade II Listed building. The Borough Council supported a previous scheme in 2014 to stabilise the memorial awarding £2,160 to the Parish towards the costs. This work has been undertaken.
The lowest quotation for the work is £900 including VAT. The work is eligible for grant up to 20% of the total cost which comes to £180. This is the recommended grant.
Financial implications
There is sufficient funding to meet both grant applications with £27,583 in the Fund allowing for commitments.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.