That the application be permitted subject to the undermentioned conditions: (i) The removal of soil from the site shall cease within nine months from the date of the decision notice. (ii) All conditions of planning permission 14/00610/FUL and previously agreed details shall continue to apply other than condition 3 as varied by the grant of this permission.
Word for word from the decision Newcastle-under-Lyme published for this meeting.Source: moderngov.newcastle-staffs.gov.uk
A. Subject to Natural England removing their objection, approve the following variation of condition 3:-
1. The removal of soil from the site shall cease within 9 months from the date of the decision notice, 2. All conditions of planning permission 14/00610/FUL and previously agreed details shall continue to apply other than condition 3 as varied by the grant of this permission.
B. Should Natural England not remove their objection then refuse the application due to the application resulting in material being extracted that is not in accordance with paragraph 144 of the NPPF.
Reason for recommendation
The operations and activities at the site have resulted in significant and detrimental harm to the residential amenity levels of neighbouring occupiers. The applicant has shown very minimal endeavour to export the existing soil since planning permission was granted in 2014 and an extension st from the 1 June 2015 until December 2019 is not justified. Therefore to further minimise the impact on the residential amenity levels of neighbouring properties and to encourage the removal of the soil from the land it is considered on balance, from the submitted information, that only a 9 month extension is justified. Should any soil remain on the site at the end of the 9 month period then this would not result in a harmful impact on the character and appearance of the landscape or Green Belt due to its location and appearance. The extraction of peat would be contrary to the NPPF and until the objection from Natural England is removed the 9 month extension should not be agreed.
Statement as to how the Local Planning Authority has worked in a positive and proactive manner in dealing with the planning application
During the determination of the planning application the LPA has been in dialogue with the applicant’s representatives and additional information has been submitted. The applied for time extension is not in accordance with the requirements of the National Planning Policy Framework however a nine month extension is considered appropriate and in accordance with national policy.
Key Issues
The application is to vary condition no.3 of planning application 14/00610/FUL for the retention of water reservoir, formation of hardstandings and repairs to the existing track, which was permitted in December 2014. Condition 3 required that:
“All activity associated with the engineering works, including the vehicle movements, the removal of soil from the site, and the re-contouring of the site areas shall cease by the 1st June 2015. Reason: To safeguard the residential amenity levels of neighbouring residential properties and to meet the guidance and requirements of the National Planning Policy Framework 2012.” st The 1 June 2015 deadline has now passed and due to there being a large amount of material still remaining on the site the applicant seeks to vary the condition to extend the period to December 2019.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.