(a) That the report received. (b) That the Head of Planning and Development with the Development Management Team Leader seeks to maintain performance of the Development Management team where satisfactory and improve the service provided where our level of performance falls significantly below the targets set out in the Planning and Development Service Plan for 2015/16. (c) That the next ‘Development Management Performance Report’ be submitted to Committee around May 2016 reporting on performance for the complete year 2015/16.
Word for word from the decision Newcastle-under-Lyme published for this meeting.Source: moderngov.newcastle-staffs.gov.uk
To provide members with a mid-year report on the performance recorded for Development Management between 1st April 2015 and 30th September 2015. Figures for 2013/14 and 2014/15 are also provided for comparison as are targets set within the Planning and Development Service Plans for 2013/14 and 2014/15.
Recommendations
(a) That the report be received.
(b) That the Head of Planning and Development with the Development Management Team Leader seeks to maintain performance of the Development Management team where satisfactory and improve the service provided where our level of performance falls significantly below the targets set out in the Planning and Development Service Plan for 2015/16.
(c) That the next ‘Development Management Performance Report’ be submitted to Committee around May 2016 reporting on performance for the complete year 2015/16.
Reasons for recommendations
To ensure that appropriate monitoring and performance management procedures are in place and that the Council continues with its focus on improving performance, facilitating development and providing good service to all who use the Planning Service.
Background
An extensive set of indicators is collected to monitor the performance of the Development Management. These include both “National Indicators” and those devised by this Council – “local indicators”. These indicators have changed over time and officers have sought to ensure that the right things are being measured to enable us to improve performance in every significant area. The range of indicators included reflects the objective of providing a balanced end to end development management service, including dealing with pre-application enquiries, breaches of planning control, considering applications, & approving subsequent details and delivering development
2. Matters for consideration:
There is an Appendix attached to this report:-
APPENDIX 1: ‘NATIONAL AND ‘LOCAL’ PERFORMANCE INDICATORS FOR DEVELOPMENT CONTROL, 2013/14, 2014/15 and 2015/16: Contains quarterly and annual figures for the national and ‘local’ Performance Indicators applicable during 2015/16 (comparative figures for 2013/14 and 2014/15 are also shown).
This report is a commentary on the national and local performance indicators as set out in detail in Appendix 1. It follows on from a report that was considered by the Planning Committee at its meeting on the 23rd June 2015 which reported on the performance achieved in 2014/15, and discussed appropriate targets. In addition it follows a report considered by the Planning Committee at its meeting on 18th August 2015 providing a Development Management Performance Action Plan.
3. The performance achieved:
6 indicators are included in the Planning and Development Service Plan for 2015/16. These are referred to in the commentaries below. It is currently predicted that the target set is likely to be met in three cases, whilst in the case of the other three it is predicted that the target is unlikely to be achieved. INDICATOR - Percentage of applications determined within timescales:-
(1) 70% of ‘Major’ applications determined ‘in time’ (2) 75% of ‘Minor’ applications determined within 8 weeks (3) 85% of ‘Other’ applications determined within 8 weeks
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.