(1) That, subject to the applicant first entering into a section 106 obligation securing a commuted off-site affordable housing contribution of £45,000 by 14 th March 2016, the application be permitted subject to the undermentioned conditions: (i) Standard Time limit for commencement of development (ii) Approved plans (iii) Materials (iv) Protection and retention of existing trees and hedgerows (v) Compliance with Arboricultural Method Statement (vi) Specific and detailed landscaping scheme (vii) Provision of access, parking and turning areas prior to occupation (viii) Off-site highway works to include 1.8m wide footway and Checkley Lane junction improvements (ix) Submission and approval of Surfacing, drainage and visibility details (x) Garages to be retained for parking (xi) Gates to be in the position shown on the approved plans and to open away from Birks Drive. (xii) The existing Checkley Lane access permanently closed (xiii) Submission and approval of a Construction Method Statement (xiv) The erection of a ‘Private Road’ sign at the site entrance (xv) Unexpected land contamination (xvi) Noise mitigation measures (xvii) Construction hours (2) That, should the matters referred to in (A) above not be secured within the above period, that the Head of Regeneration and Planning Services be given delegated authority to refuse the application on the grounds that without such matters being secured the development would fail to ensure a commuted sum towards affordable housing or, if he considers it appropriate, to extend the period of time within which the obligation can be secured.
Word for word from the decision Newcastle-under-Lyme published for this meeting.Source: moderngov.newcastle-staffs.gov.uk
A. Subject to the applicant first entering into a section 106 obligation securing a commuted off-site affordable housing contribution of £45,000 by 14th Match 2016, permit the application subject to conditions relating to the following matters:
1. Standard Time limit for commencement of development 2. Approved plans 3. Materials 4. Protection and retention of existing trees and hedgerows 5. Compliance with Arboricultural Method Statement 6. Specific and detailed landscaping scheme 7. Provision of access, parking and turning areas prior to occupation 8. Off-site highway works to include 1.8m wide footway and Checkley Lane junction improvements 9. Submission and approval of Surfacing, drainage and visibility details 10. Garages to be retained for parking 11. Gates to be in the position shown on the approved plans and to open away from Birks Drive. 12. The existing Checkley Lane access permanently closed 13. Submission and approval of a Construction Method Statement 14. The erection of a ‘Private Road’ sign at the site entrance 15. Unexpected land contamination 16. Noise mitigation measures 17. Construction hours
B. Should the matters referred to in (A) above not be secured within the above period, that the Head of Regeneration and Planning Services be given delegated authority to refuse the application on the grounds that without such matters being secured the development would fail to ensure a commuted sum towards affordable housing or, if he considers it appropriate, to extend the period of time within which the obligation can be secured.
Reason for recommendation
An extant planning permission remains on the site for a residential development and whilst the proposal is inappropriate development within the Green Belt it is considered in this particular instance that there continues to be the required very special circumstances which outweighs the harm to the inappropriateness of the development, namely:- The site is strategically important inasmuch as it provides an appropriate and attractive gateway development providing an introduction to the village of Wrinehill. It is important, therefore, that this redundant site is redeveloped in the interests of the appearance of Wrinehill. In addition the proposal would secure a contribution to affordable housing provision off site.
The site has ready access to public transport connections. The proposal provides an acceptable layout and design for its location which is in accordance with planning policy and design guidance. Planning conditions would make the proposed development acceptable, the development accords with the provisions of the development plan and there are no other material planning consideration that would justify refusing the proposed development.
Statement as to how the Local Planning Authority has worked with the applicant in a positive and proactive manner in dealing with this application
Discussions with the applicant have been ongoing during the application and further supporting information has been provided which has lead to independent advice being received from the District Valuer in a prompt manner. This is now considered to be a sustainable form of development and so complies with the provisions of the National Planning Policy Framework.
KEY ISSUES
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.