Newcastle-under-Lyme Borough Council
Planning Committee, Tuesday 29 March 2016 at 7.00pm

Application for Major Development - Hamptons and Land adjacent to Hamptons, off Keele Road, Thistleberry, Newcastle. Mr JN and NW Hampton. 15/01085/OUT

Refused Planning 4 papers

Planning Committee refused this item on Tuesday 29 March 2016. Below is the council's own wording, with the papers it was decided on.

Item4

Resolved

(a) That the application be refused for the following reasons: (i) Odour arising from the adjoining landfill site is highly likely to adversely affect the living conditions of the occupiers of the proposed development and it is not considered that this can be addressed through appropriate mitigation. (ii) In the absence of a planning obligation, and having regard to the likely additional pupils arising from a development of this scale and the capacity of existing educational provision in the area, the development fails to make an appropriate contribution , which can be supported by the development without rendering it unviable, towards primary school provision, contrary to policy. (iii) In the absence of a planning obligation the development fails to provide 20% of the total number of proposed dwellings as affordable dwellings which can be supported by the development without rendering it unviable and which are required to provide a balanced and well-functioning housing market. (iv) In the absence of a planning obligation towards Travel Plan monitoring costs, the required contribution to sustainable transport measures, which can be supported by the development without rendering it unviable, would not be secured in accordance with policy. (v) In the absence of a planning obligation securing the long term maintenance and management of public open space on the site, the development would not be acceptable (vi) In the absence of a planning obligation which provides an appropriate future reappraisal mechanism to secure further affordable housing provision (to a maximum 25% provision in accordance with policy) to allow for changed financial circumstances in the event that the development does not immediately proceed, the development may not provide what it could and should (to comply with policy). (b) That the Council no longer intends to argue, at the appeal against the decision on application 14/00948/OUT, that the development would unduly restrict or constrain the activities permitted or allocated to be carried out at any waste management facility and the implementation of the Waste Strategy, contrary to local and national policy. (c) That the Council no longer intends to argue, at the appeal against the decision on application 14/00948/OUT, that a contribution toward off site public open space improvement and maintenance is required (d) That the Council should submit, at the appeal against the decision on application 14/00948/OUT, that an appropriate contribution towards Travel Plan Monitoring Costs is justified (e) To give authority for the Council to enter into a S106 obligation to secure the following: (i) An education contribution of £319,899 towards Primary School provision within Friarswood Primary School/ Hassell Community Primary School / St Giles’ and St George’s CofE Academy. (ii) 20% affordable housing provision (iii) Travel Plan monitoring fee of £6,300 (iv) Appropriate arrangements for the long term management and maintenance of the Public Open Space on the site (v) An appropriate reappraisal mechanism to secure further affordable housing provision (to a maximum 25% provision in accordance with policy) to allow for changed financial circumstances.
Word for word from the decision Newcastle-under-Lyme published for this meeting. Source: moderngov.newcastle-staffs.gov.uk

Follow this further

Built from Newcastle-under-Lyme's papers

What the report saysPro

Report to Planning Committee

ADVANCE SUPPLEMENTARY REPORT TO THE PLANNING COMMITTEE 29th March 2016

Agenda item 4 Application ref. 15/001085/OUT

Hamptons Metal Merchants and Land Adjoining Keele Road, Newcastle

Since the main agenda report was published, two further representations have been received.

A letter in support has been received indicating that there is little or no odour from the landfill site due to the processes which were implemented some time ago. The scrap yard has a noise problem, the vehicles entering the site cause traffic problems, and it is unsightly.

A further letter of objection has been received from the Thistleberry Residents Association reiterating concerns previously expressed regarding odour and indicating that there have recently been very strong odours coming from the site.

The applicant has submitted a letter from Permission Homes North West indicating that they would be interested in pursuing the purchase of the site. The letter further indicates that as lead developer on the adjoining site there were no issues with the attractiveness of the site. They received a steady sales pace, even through recession years. Notwithstanding the proximity of the landfill they consider the site would be very attractive and they would not anticipate having any selling issues. The development is accordingly deliverable.

In addition to the final report of the District Valuer (DV) has been received following consideration of additional information provided on behalf of the applicant. There remains disagreement between the DV and the applicant on matters summarised below:

 The DV does not agree with the applicant that incentives to the eventual developer should be included within the assessment of the Gross Development Value of the proposal A lower GDV would be achieved were such incentives to be included, thus reducing the viability of the scheme  The DV does not agree that a developer profit of 20% is in line with market allowances at this date. The DV considers that the allowance made for developers profit should be 17.5% for the open market housing and 6% for the affordable housing. The applicant submits that the site will only appeal to volume housebuilders who are currently assuming as standard rates of 20% profit on GDV and there are furthermore site specific reasons for considering this is very conservative return including o High abnormal costs (and thus a significant risk that the developer will need to allow for o The location, in comparison with other larger urban areas, is in a slower selling area and will therefore suffer from slower sale rates o The distance of the site from the offices of the volume housebuilders o other environmental issues “given the adjoining land uses”  The applicant fundamentally disagrees with the DVs approach to site value indicating that allowance needs to be made for the residential potential that the site offers. Their view is that the value adopted by the DV (£890,000 rather than the much greater figure which the applicant maintains) is substantially below what represents the market value of the site and falls far short of what would be considered to be a competitive market return for the landowner. The applicant consider their approach to site value assessment to be more appropriate than what they describe as the singular approach adopted by the DV. In support of this position they refer to the national Planning Practice Guidance and the RICS Guidance Financial Viability in Planning. The DV remains of the opinion that the development is marginally unviable, which is the conclusion of the applicant. The applicant’s position is, however, that the development could not support the level of contributions and affordable housing that the DV considers could be supported without resulting in the development becoming unviable.

As indicated within the main agenda report (paragraph 5.6) the DV was asked to undertake some sensitivity testing.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
01185OUT Hamptons ESMsuppReport 105 KB DownloadRead as text
PDF
1085OUT Land at Hamptons Metals and adj ESM (1) (2)Report 175 KB Download
PDF
15 1085Report 318 KB Download
PDF
Application for Major Development: Hamptons and Land adjacent to Hamptons, off Keele Road, Thistleberry, Newcastle. Mr JN and NW Hampton. 15/01085/OUTReport 49 KB Download

At this meeting

Whole meeting

Who was there

15 of 18 attended
ME
Councillor Mrs Eileen BraithwaiteCommittee Member, present
JC
Councillor John CooperCommittee Member, present
AF
Councillor Andrew FearCommittee Member, apologies, sent representative
TM
The Mayor. Councillor Sandra HambletonCommittee Member, present
CG
CouncillorMrs Gillian HeesomCommittee Member, apologies
MH
Councillor Mark HollandSubstitute, present as substitute
MC
Councillor Miss Chloe ManceyCommittee Member, present
PN
Councillor Paul NorthcottCommittee Member, present
KO
Councillor Kenneth OwenCommittee Member, present
MS
Councillor Ms Sarah PickupCommittee Member, apologies, sent representative
MR
Councillor Marion ReddishChair, present
CS
CouncillorMrs Sandra SimpsonCommittee Member, present

All 18 on the meeting page

On this subject at Newcastle-under-Lyme

Search all
  1. Application for Major Development - Hamptons and Land adjacent to Hamptons, off Keele Road, Thistleberry, Newcastle. Mr JN and NW Hampton. 15/01085/OUTThis decision
  2. Application for major development - tadgedale quarry. wain homes north west. 24/00589/fulAgreed
  3. Application for major development - land off bar hill road onneley. owl homes limited. 25/00897/remApproved
  4. Application for major development - baldwin's gate farm, newcastle road, baldwin's gate. mr chris o'hanlon, bellway homes limited. 26/00447/fulRefused
  5. Application for major development - baldwin's gate farm, newcastle road, baldwin's gate. mr chris o'hanlon, bellway homes limited. 25/00931/fulRefused
  6. Application for major development - baldwins gate farm, newcastle road, baldwins gate, newcastle. st5 5es. mr chris o'hanlon. bellway homes ltd. 26/00052/fulRefused

More from Newcastle-under-Lyme Planning Committee

All decisions
MeetingDecisionOutcome
18 Aug 2026 Minutes of previous meeting(s)That the minutes of the meeting held on 21 July, 2026 be agreed as a correct record. Agreed Open
18 Aug 2026 Application for major development - tadgedale quarry. wain homes north west. 24/00589/fulThat the application be permitted subject to the undermentioned conditions: (i) Variation of condition 2 to refer to ... Agreed Open
18 Aug 2026 Application for major development - land off bar hill road onneley. owl homes limited. 25/00897/remThat the application be permitted, subject to the undermentioned conditions: (i) Link to outline planning permission ... Approved Open
18 Aug 2026 Application for other development - 25-27 well st & 82 garden st, newcastle. marshallsay. 26/00051/couThat the application be refused for the following reasons: (i) Contrary to Policy HOU7 (Homes in Multiple Occupation)... Refused Open
18 Aug 2026 Five-year housing land supply update report 2026-31(i) That Members note the content of the five-year housing Land supply position statement (appendix 1) and agree that... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies