REPORT TO THE PLANNING COMMITTEE 21st JUNE 2016
ANNUAL REPORT ON PLANNING AND RELATED APPEALS 1st APRIL 2015 – 31st MARCH 2016
Introduction
1. Appeal decisions are reported upon receipt to the Planning Committee, as are decisions on the award of costs in appeal proceedings. In addition, an annual report on planning and related appeals is produced for consideration by Members, intended to identify general issues relating to the Local Planning Authority’s (LPA’s) appeal performance, and to encourage an approach that reflects upon and learns from such appeals.
Appeal Performance
2. Well-considered decisions on planning applications are a key part of delivering an effective planning service. People should have confidence in the quality of the development decisions being made by the Authority – that all relevant considerations are being taken into account, and that the weight being given to different considerations is reasonable in the context of national and local policies. Appeals can be made both against the refusal of permission, but also against conditions attached to permissions. There are many cases where following a refusal of an application, discussions are held with an applicant and as a result the applicant decides either to no longer pursue the proposal or to submit revised proposals. In this way difficulties can be more effectively, quickly and cheaply resolved. Your officers would always seek to encourage such discussions. As advised in the National Planning Practice Guidance (2014), appeals should only be made when all else has failed.
3. An applicant has currently in most cases up to 6 months to lodge an appeal (from receipt of the decision notice), and given the time some appeals take to be determined (particularly as there is currently a significant backlog at the Planning Inspectorate), there is often a significant period of time between the LPA’s original decision and the appeal decision. For householder applications, the time limit to appeal is 12 weeks and the time period for submitting an appeal where the same or substantially the same development is subject to an Enforcement Notice is just 28 days.
4. Appeals can also be made within a specified time against Enforcement Notices on various specific grounds. If an appeal is lodged the Notice does not come into effect until the appeal has been determined. If no appeal is lodged the Notice comes into effect.
5. During the 12-month period from April 2015 to March 2016, 20 appeals against decisions by the Borough Council as the LPA were determined. During this period 2 appeals were withdrawn. A list of the appeal decisions is attached as Appendix 1. 19 were decided in the previous year 2014/15.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Annual Appeals Report 2015-16 RKAppendix to | 56 KB | Download |
PDF |
Planning Appeal Performance Report 2015-2016Report | 111 KB | DownloadRead as text |
Follow Planning Committee at Newcastle-under-Lyme and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 18 Aug 2026 | Minutes of previous meeting(s)That the minutes of the meeting held on 21 July, 2026 be agreed as a correct record. | Agreed | Open |
| 18 Aug 2026 | Application for major development - tadgedale quarry. wain homes north west. 24/00589/fulThat the application be permitted subject to the undermentioned conditions: (i) Variation of condition 2 to refer to ... | Agreed | Open |
| 18 Aug 2026 | Application for major development - land off bar hill road onneley. owl homes limited. 25/00897/remThat the application be permitted, subject to the undermentioned conditions: (i) Link to outline planning permission ... | Approved | Open |
| 18 Aug 2026 | Application for other development - 25-27 well st & 82 garden st, newcastle. marshallsay. 26/00051/couThat the application be refused for the following reasons: (i) Contrary to Policy HOU7 (Homes in Multiple Occupation)... | Refused | Open |
| 18 Aug 2026 | Five-year housing land supply update report 2026-31(i) That Members note the content of the five-year housing Land supply position statement (appendix 1) and agree that... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.