(i) That the demolition of the former Knutton Recreation Centre building, at a cost of up to £50,000, be approved. (ii) That the Executive Director for Regeneration and Development in consultation with the Portfolio Holder for Finance, IT and Customer be authorised to commission suitably qualified and experienced contractors to undertake the necessary demolition works. (iii) That the cost be met from either borrowing, in accordance with the approved Treasury Management Strategy or from capital receipts. (iv) That consultation on the future disposal of the site in line with the Council’s Asset Management Strategy 2015/16 – 2017/18 be approved, with the results of this being reported to a later meeting of Cabinet alongside an update on other issues relating to the former Knutton Recreation Centre site.
Word for word from the decision Newcastle-under-Lyme published for this meeting.Source: moderngov.newcastle-staffs.gov.uk
To outline the proposal to demolish the disused former Knutton Recreation Centre building and the reasons for this.
Recommendations (a) To approve demolition of the former Knutton Recreation Centre building at a cost of up to £50,000.
(b) To authorise the Executive Director for Regeneration and Development in consultation with the Portfolio Holder for Finance, IT and Customer to commission suitably qualified and experienced contractors to undertake the necessary demolition works.
(c) That the cost be met from borrowing, in accordance with the approved Treasury Management Strategy.
(d) To approve consultation on the future disposal of the site in line with the Council’s Asset Management Strategy 2015/16 – 2017/18 with the results of this to be reported to a later meeting of Cabinet alongside an update on other issues relating to the former Knutton Recreation Centre site.
Reasons The Council remains responsible for this disused property and continues to incur costs of keeping it safe. Boarded-up properties are often an eye sore in the community and can attract anti-social behaviour (as has happened here); it is appropriate that the Council takes this into account when considering the building’s future use.
Background
1.1The former Knutton Recreation Centre became surplus to operational service requirements in 2012 as part of the then planned consolidation of indoor leisure activities to the new Jubilee2 centre in the nearby Newcastle town centre. It was always planned that the building would be demolished as part of the business case for the development of J2 and that the site would be disposed of for redevelopment at the most appropriate time.
1.2In September 2012 Cabinet authorised the disposal of the site on which the former Recreation Centre stands; however no resolution has been made regarding the building itself which is currently standing empty with all services cut off. The building is potentially subject to ongoing vandalism (as has occurred recently) and is incurring costs to the Borough Council through the payment of non-domestic rates, ongoing security inspections
and necessary repairs. As such it does nothing to contribute to the community or economic vitality of Knutton village and it creates an unnecessary drain on Council resources.
1.3On a broader level there are a number of issues which would affect the developability of the overall site were it to be disposed of in its current condition. Officers are working to address these and it is anticipated that an update will be given to a future meeting of Cabinet. Working sequentially however, this report seeks Cabinet approval to demolish the former recreation centre building in the interests of the visual amenities in the area; reducing the risk of anti-social behaviour; curtailing the Council’s costs of maintaining an empty structure on this site and; reducing owner’s liability in respect of third party safety.
1.4Cabinet have previously considered reports to outline that it would be beneficial to redevelop the site and the potential delivery of new housing (including affordable housing) has been highlighted alongside the option to redevelop a slightly wider area on a more comprehensive basis. Nevertheless it is recommended that whilst the Council continues to seek a comprehensive redevelopment to deliver the best outcomes for the local community it is considered that the demolition of the building would support the longer term redevelopment objectives.
2. Issues
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Local government reorganisation update(i) That the content of the letter from the Minister for Devolution received on 7 th September 2026, reviewing decisi...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.