Resolved
( i ) That the content of the five year supply statement be noted. (ii) That the significance of the five year supply position in Development Management decision be noted.
Planning Committee noted this item on Tuesday 15 August 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
( i ) That the content of the five year supply statement be noted. (ii) That the significance of the five year supply position in Development Management decision be noted.
1) That members note the content of the 5 year supply statement.
2) That members note the significance of the 5 year supply position in Development Management decision making.
Reasons To ensure the Council makes decisions in line with up-to-date planning policy and its latest 5 year housing land Supply Statement.
1.0Member’s attention is drawn to the accompanying 5 year Housing Land Supply Statement and its Appendix. The purpose of this report is not to repeat the content of the Supply Statement but rather to draw attention to the key elements of it
1.1Whilst the Statement is a Supply Statement it is a measurement of the area’s supply of deliverable housing sites against the housing requirements or needs of the area. To this end the Statement explains that evidence relating to the housing need for both Newcastle and Stoke has been published in the Strategic Housing Market Assessment and the Strategic Housing Market Assessment Review 2017. At this stage the evidence is only a recommendation to the two authorities. Both documents have been published, as part of the Joint Local Plan Strategic Options public consultation exercise.
1.2These studies indicate that Newcastle-under-Lyme Borough Council and Stoke-on-Trent City Council share a single housing market area (HMA). The SHMA Review, 2017, recommends a full Objectively Assessed Need (OAN) of 1,390 dwellings per annum across the HMA for the period 2013 to 2033. This need draws on the implications of employment growth on housing need and supporting a return to a higher level of household formation for younger people.
1.3The SHMA Review, in order to identify a recommended OAN for the housing market area, is comprised of an up-to-date assessment of Newcastle’s housing need. The assessed housing need for Newcastle-under-Lyme is 586 dwellings per annum from 2013 through to 2039. This assessment does not represent a full OAN as the recommended requirement does not apply across the HMA. In simple terms the recommended figure of 586 dwellings per annum is the Borough’s component of the recommended OAN.
1.4As a result, this Statement provides only an interim and indicative picture of potential housing land supply in Newcastle-under-Lyme Borough alone, and not across the housing market area. That would require a Joint five year housing land supply calculation across both local authority areas in order to encompass the HMA, see Figure 1. It is intended to prepare such a statement at the Preferred Option stage of the Joint Local Plan process. Nevertheless it is considered appropriate to prepare a 5 year housing land supply statement for the Borough alone in order to support development management, and comply with paragraph 47 of the NPPF. There is a requirement to produce such a Supply Statement on an annual basis and the Council last produced such a Statement (in the form of a Mid-year update) in January 2016.
1.5The new Statement reports that the level of completions in 2015/16 was relatively low (154) whilst the figure was considerably higher (412) in 2016/17. When compared with the latest indication of housing need there has been a consistent and persistent underdelivery of housing against that need with the result that in calculating the amount of housing land required it is appropriate to use a 20% buffer. Taking this into account and the underdelivery that there has been since 2013, the starting year of the SHMA, the requirement or need figure for the area for the next 5 years comes to just over 5,000 dwellings – an annual requirement of 1,007 per year.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
08-17Appendix 07 | 108 KB | Download |
PDF |
FIVE YEAR HOUSING LAND SUPPLY STATEMENT FOR THE BOROUGH OF NEWCASTLE-UNDER-LYME FROM 1 APRIL 2017 TO 31 MARCH, 2022Report | 70 KB | DownloadRead as text |
PDF |
Five Year Housing Land Supply Statement (2017)FINALv6Report | 76 KB | Download |
Follow Planning Committee at Newcastle-under-Lyme and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 18 Aug 2026 | Minutes of previous meeting(s)That the minutes of the meeting held on 21 July, 2026 be agreed as a correct record. | Agreed | Open |
| 18 Aug 2026 | Application for major development - tadgedale quarry. wain homes north west. 24/00589/fulThat the application be permitted subject to the undermentioned conditions: (i) Variation of condition 2 to refer to ... | Agreed | Open |
| 18 Aug 2026 | Application for major development - land off bar hill road onneley. owl homes limited. 25/00897/remThat the application be permitted, subject to the undermentioned conditions: (i) Link to outline planning permission ... | Approved | Open |
| 18 Aug 2026 | Application for other development - 25-27 well st & 82 garden st, newcastle. marshallsay. 26/00051/couThat the application be refused for the following reasons: (i) Contrary to Policy HOU7 (Homes in Multiple Occupation)... | Refused | Open |
| 18 Aug 2026 | Five-year housing land supply update report 2026-31(i) That Members note the content of the five-year housing Land supply position statement (appendix 1) and agree that... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.