That the application be permitted subject to the undermentioned conditions: (i) Time limit. (ii) Submission of materials. (iii) In accordance with the approved plans. (iv) Contaminated land investigation and risk assessment to be submitted. (v) Tree protection in accordance with BS5837:2012 and submitted drawing. (vi) Development in accordance with P.359.13.05 and information provided in the Arboricultural Impact Assessment. (vii) Prior approval of landscaping proposals. (viii) Prior approval of tree and landscape management plan to address issues concerning the long term future of the woodland & replacement planting. (ix) Arboricultural site monitoring schedule. (x) Implement recommendations within the Phase 1 Extended Habitat Survey received with the application. (xi) Prior approval and implementation of sewage plant equipment on site. (xii) No levels alterations to be undertaken outside the development zone. (xiii) Schedule of works to retained trees.
Word for word from the decision Newcastle-under-Lyme published for this meeting.Source: moderngov.newcastle-staffs.gov.uk
1. Time limit 2. Submission of materials 3. In accordance with the approved plans 4. Contaminated land investigation and risk assessment to be submitted 6. Tree protection in accordance with BS5837:2012 and submitted drawing 7. Development in accordance with Arboricultural Method Statement for tree protection 8. Prior approval of landscaping proposals 9. Prior approval of tree and landscape management plan to address issues concerning the long term future of the woodland & replacement planting 10. Arboricultural site monitoring schedule 11. Implement recommendations within the Phase 1 Extended Habitat Survey received with the application 12. Prior approval and implementation of sewage plant equipment on site
Reason for recommendation
The development is inappropriate development within the Green Belt. There is, however, an extant outline planning permission for the residential development of this plot and a reserved matters application could lawfully submitted at any time. In addition planning permission was granted for a dwelling on this site under application reference 15/00281/FUL. Such a ‘fall back’ position amounts to very special circumstances required. Further, the development by virtue of its design, scale and materials, would not harm the character of the rural area, and there would be no adverse impact to highway safety or trees. The development is considered to accord with Policies N12 and T16 of the Local Plan, Policy CSP 1 of the Core Spatial Strategy and the aims and objectives of the National Planning Policy Framework.
Statement as to how the Local Planning Authority has worked in a positive and proactive manner in dealing with this application
This is considered to be a sustainable form of development and so complies with the provisions of the National Planning Policy Framework.
KEY ISSUES
The application seeks planning permission for the erection of a detached dwelling on a site off Birch Tree Road. The application site is located within an area of Green Belt, therefore the key consideration with regard to the principle of development is whether the proposal represents inappropriate development within the Green Belt. In addition it is within a landscape maintenance area as indicated on the Local Development Framework Proposals Map. The site is located just beyond the HS2 route, and as such any impact caused by the new railway should be acceptable. An extended Phase 1 Habitat Survey was submitted with the application, and states that the development would have very little harm to protected species on site providing the recommendations from the survey are implemented. The key issues to consider as part of the development are therefore as follows;
Is the development inappropriate development within the Green Belt and if so, are any very special circumstances in place to outweigh harm to the Green Belt Impact of design upon the character of the area Impact upon the amenities of neighbouring residents Highway implications Impact of the proposal on trees Impact upon protected species
Is the development considered appropriate development in the Green Belt, and if so are any very special circumstances in place to outweigh harm to the Green Belt?
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.