Resolved
That, as resolved at the meeting held on 24 May, 2018, the Head of Planning will be exercising the delegated authority to permit the application subject to conditions relating to matters referred to in the report.
Planning Committee decided this item on Tuesday 19 June 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
That, as resolved at the meeting held on 24 May, 2018, the Head of Planning will be exercising the delegated authority to permit the application subject to conditions relating to matters referred to in the report.
LODGE FARM, NEWCASTLE ROAD, TALKE MS R LARGE 18/00062/FUL
The application is for full planning permission for the construction of a 30m by 55m manege and new stable block building for commercial use and the change of use of other land from agriculture to the keeping of horses. The stable block building is ‘L’ shaped measuring 37.9m in length along the longest wing, 25.5m in length along the shortest wind and 7.3m deep along both wings.
The applicant proposes that the manege is to be open for use 7am until 7pm. The application site area involved measures 1.28 hectares.
The application site is located within the Green Belt and an Area of Landscape Restoration as indicated on the Local Development Framework Proposals Map.
This is a holding report following the resolution of Planning Committee, on 24th May, to give the Head of Service delegated authority to permit the application subject to conditions subject to no objections being received from Kidsgrove Town Council by 12th June, which cannot be addressed by appropriate conditions. The resolution also included that in the event of objections being received from Kidsgrove Town Council by the 12th June, which cannot be addressed by appropriate conditions, the application is referred back to the Planning Committee for reconsideration. No comments from the Town Council have yet been received.
A further report will follow should Kidsgrove Town Council submit objections by 12th June which can’t be addressed by appropriate conditions.
The 13 week period for the determination of this application, 27th April, and the agreed extension of time to the statutory determination period, 28th May 2018, have both expired.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
000062FUL Lodge Farm Newcastle Road MS2Report | 55 KB | DownloadRead as text |
PDF |
18.062.FULReport | 333 KB | Download |
PDF |
APPLICATION FOR MINOR DEVELOPMENT: LODGE FARM, NEWCASTLE ROAD, TALKE. MS R LARGE. 18/00062/FULSupplementary | 50 KB | Download |
Follow Planning Committee at Newcastle-under-Lyme and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 18 Aug 2026 | Minutes of previous meeting(s)That the minutes of the meeting held on 21 July, 2026 be agreed as a correct record. | Agreed | Open |
| 18 Aug 2026 | Application for major development - tadgedale quarry. wain homes north west. 24/00589/fulThat the application be permitted subject to the undermentioned conditions: (i) Variation of condition 2 to refer to ... | Agreed | Open |
| 18 Aug 2026 | Application for major development - land off bar hill road onneley. owl homes limited. 25/00897/remThat the application be permitted, subject to the undermentioned conditions: (i) Link to outline planning permission ... | Approved | Open |
| 18 Aug 2026 | Application for other development - 25-27 well st & 82 garden st, newcastle. marshallsay. 26/00051/couThat the application be refused for the following reasons: (i) Contrary to Policy HOU7 (Homes in Multiple Occupation)... | Refused | Open |
| 18 Aug 2026 | Five-year housing land supply update report 2026-31(i) That Members note the content of the five-year housing Land supply position statement (appendix 1) and agree that... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.