KIDSGROVE SPORTS CENTRE REFURBISHMENT

Noted Executive 1 paper

Cabinet noted this item on Wednesday 9 September 2020. Below is the council's own wording, with the papers it was decided on.

Item21

Resolved

(i) The progress made on the project since April 2020 Cabinet in terms of scope, design and budget in consultation with the Kidsgrove Leisure Centre Community Group be noted. (ii) It be noted that following detailed survey work, the target cost of the project is now £5.998m (iii) The submission of a bid under the Town Fund Advance Funding for a contribution towards the refurbishment of the Centre be noted. (iv) A supplementary capital estimate be approved of up to £400,000 to be drawn down from the Council’s 2020/21 capital programme contingency in the event that external funding contributions cannot be secured (v) That the Executive Director Commercial Development and Economic Growth, in conjunction with the Portfolio Holder for Corporate and Service Improvement, People and Partnerships, continue to work with the Community Group to progress the refurbishment.
Word for word from the decision Newcastle-under-Lyme published for this meeting. Source: moderngov.newcastle-staffs.gov.uk

Follow this further

Built from Newcastle-under-Lyme's papers

What the report saysPro

Report to Cabinet

Purpose of the report

To approve the development of the work package for full design and cost information prior to an award of contract and the financing arrangements for the refurbishment of Kidsgrove Sports Centre.

Recommendation

That Cabinet

1. Notes the progress made on the project since April 2020 cabinet in terms of scope, design and budget in consultation with the Kidsgrove Leisure Centre Community Group.

2. Notes that following detailed survey work, the target cost of the project is now £5.998m

3. Note that a bid been submitted under the Town Fund Advance Funding for a contribution towards the refurbishment of the Centre

4. Approves a supplementary capital estimate of up to £400,000 to be drawn down from the Council’s 2020/21 capital programme contingency in the event that external funding contributions cannot be secured.

5. That the Executive Director Commercial Development and Economic Growth, in conjunction with the Portfolio Holder for Corporate and Service Improvement, People and Partnerships, continue to work with the Community Group to progress the refurbishment.

Reasons

The procurement of this contract will allow the council to fulfil its commitment to provide sports facilities in Kidsgrove that are modern, attractive and high quality that meet public expectations.

Background

1.1On 22 April 2020 cabinet agreed a target cost of £5.6m for the refurbishment of Kidsgrove Sports Centre and to further survey and design work with Willmott Dixon to further define the scope and extent of necessary upgrades to the plant and building to establish a firmer target cost. Published 2 September 2020

1.2The refurbishment and redevelopment of Kidsgrove Sports Centre and Swimming Pool will enable the centre to fully reopen to the public under community management.

2. Update

2.1Since May 2020, a series of intrusive surveys have been undertaken to review the pool structure, together with the walls and roofs of the pool hall and sports hall, the equipment to the pool filtration systems and the main mechanical and electrical systems. These surveys have provided much more detail on the building condition, and as such have enabled the cost estimates to be firmed up.

2.2A number of design meetings have taken place with the Community Group, Willmott Dixon and their special leisure architects to review the design and scope of the scheme to achieve the most efficient use of the available space whilst reducing the extent of building works.

2.3Willmott Dixon have now prepared a revised design which the Community Group are satisfied with and have used this design and the output of the intrusive surveys to work up the refurbishment costs accordingly.

2.4The results of the above have resulted in a new design which makes the most of the existing building layout, satisfies the anticipated user requirements and provides the 25 year life span for the building. After providing for realistic budget allowances, overall costs have increased from £5.6m to £5.998m. Attached as Confidential Appendix 1 to this report is Willmott Dixon’s RIBA Stage 2 Report which summarises the survey findings and sets out the cost plan.

2.5The Council has been working with partners to secure the funding package to deliver the scheme. As previously reported, this includes contributions from Staffordshire County Council and Sport England. A contribution is also being sought as part of a package of proposals being put forward to Government for Town Deal funding in Kidsgrove. Discussions are ongoing with Sport England with a view to increasing their funding contribution.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
KIDSGROVE SPORTS CENTRE REFURBISHMENTReport 441 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 18 attended
ST
Councillor Simon TaggChair, present
SS
Councillor Stephen SweeneyVice-Chair, present
TJ
Councillor Trevor JohnsonCommittee Member, present
MH
Councillor Mrs Helena MaxfieldCommittee Member, present
PN
Councillor Paul NorthcottCommittee Member, present
MJ
Councillor Mrs Jill WaringCommittee Member, apologies
DA
David AdamsOfficer, in attendance
AB
Annette BaileyOfficer, expected
MH
Martin HamiltonOfficer, in attendance
CT
Craig TurnerOfficer, expected
JW
Jan WillisOfficer, in attendance
SM
Sian Morris-TaitOfficer, expected

All 18 on the meeting page

On this subject at Newcastle-under-Lyme

Search all
  1. KIDSGROVE SPORTS CENTRE REFURBISHMENTThis decision
  2. Kidsgrove sports centre final accountApproved
  3. Kidsgrove sports centre refurbishmentApproved
  4. Kidsgrove sports centre refurbishmentDecided
  5. Kidsgrove sports centre refurbishment updateNoted
  6. Kidsgrove sports centre refurbishmentAgreed

More from Newcastle-under-Lyme Cabinet

All decisions
MeetingDecisionOutcome
15 Sep 2026 Minutes of previous meetingsThat the Minutes of the meeting held on the 4 August be agreed as a correct record. Agreed Open
15 Sep 2026 Walleys quarry odour updateThat the contents of the update report be noted. Noted Open
15 Sep 2026 Local government reorganisation update(i) That the content of the letter from the Minister for Devolution received on 7 th September 2026, reviewing decisi... Noted Open
15 Sep 2026 Recycling & waste re-routing(i) That the recycling and waste collection day changes for approximately 22,000 households in the south of the borou... Approved Open
15 Sep 2026 Improving safety and welfare infrastructure at knutton lane depot(i) That the works and budget necessary to refurbish and upgrade the Knutton Lane depot to improve health & safety we... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies