That: (a) Cabinet notes the progress made on the project since the September 2020 Cabinet meeting in terms of scope, design and budget in consultation with the Kidsgrove Leisure Centre Community Group. (b) Notes that the Kidsgrove Town Deal funding allocation announced by MHCLG on the 3 rd March includes up to £2.3m towards the overall cost of the project. (c) Notes the further work to be undertaken to secure the release of the Town Deal funding and authorises the Executive Director – Commercial Development and Economic Growth, in consultation with the Portfolio Holder, Corporate and Service Improvement, People and Partnerships and the Kidsgrove Town Deal Board to progress the work with all haste to maintain momentum with the project.
Word for word from the decision Newcastle-under-Lyme published for this meeting.Source: moderngov.newcastle-staffs.gov.uk
To note the progress made to date on the refurbishment works to Kidsgrove Sports Centre.
Recommendation
That Cabinet
1. Notes the progress made on the project since the September 2020 Cabinet meeting in terms of scope, design and budget in consultation with the Kidsgrove Leisure Centre Community Group.
2. Notes that the Kidsgrove Town Deal funding allocation announced by MHCLG on the 3rd March includes up to £2.3m towards the overall cost of the project.
3. Notes the further work to be undertaken to secure the release of the Town Deal funding and authorises the Executive Director – Commercial Development and Economic Growth, in consultation with the Portfolio Holder, Corporate and Service Improvement, People and Partnerships and the Kidsgrove Town Deal Board to progress this work with all haste to maintain momentum with the project.
Reasons
This project will allow the Council to fulfil its commitment to provide sports facilities in Kidsgrove that are modern, attractive and high quality that meet public expectations.
Background
1.1The refurbishment and redevelopment of Kidsgrove Sports Centre and Swimming Pool is a corporate priority and will enable the centre to fully reopen to the public under community management, through the Kidsgrove Sports Centre Community Interest Company (KSC CIO).
1.2Previously Cabinet has approved that this scheme be developed in line with the expectations of the KSC CIO to refurbish Kidsgrove Sports Centre. At its meeting in September 2020, Cabinet considered a report which allowed the project to develop beyond initial cost estimates through Willmott Dixon Construction Ltd being contracted to undertake detailed design and contract award price build up exercises in order to provide certainty of the cost of the refurbishment, informed by strip out of part of the building. The report noted that this work would be Published 16th March 2021
completed in early 2021. This work has now been substantially completed and is the subject of this report.
2. Update
2.1Since Cabinet received its September 2020 update on the project, there have been four areas where significant progress has been made:
The process of transferring the site from Staffordshire County Council to the Borough Council was completed in November 2020; this is a significant milestone and has enabled the Council to progress discussions with the CIO regarding the onward lease from the Council to the CIO. In addition, the transfer released £352,273 in funding for the project from Staffordshire County Council.
A community use agreement and funding agreement has been signed with The Kings School in respect of the Advance Town Deal funded new 3G pitch at the school, and works have commenced to build this facility. These agreements protect access to the sport centre.
Willmott Dixon have continued their build-up of contract cost for the overall cost of the refurbishment.
The Government announced in March 2021 that the Kidsgrove Town Deal had been successful, with £16.9m being awarded for projects in Kidsgrove, including up to £2.3m for the Kidsgrove Sports Centre project.
The Town Deal Board at its meeting on March 15th confirmed it support for ‘fast tacking’ of the allocation of £2.3 million for Kidsgrove Sport Centre.
2.2In December 2020 a strip out and enablement contract was awarded to WDC, which commenced in January 2021. These works have helped investigate further the building condition and the extent of the refurbishment works required.
2.3The Project Steering Group which includes the CIO will meet shortly to receive the final costing from WD.
Town Deal Funds – Process
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Local government reorganisation update(i) That the content of the letter from the Minister for Devolution received on 7 th September 2026, reviewing decisi...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.