QUARTER 4 2020/21 AND QUARTER 1 2021/22 CORPORATE RISK MANAGEMENT REPORT

Decided Finance 2 papers

Audit and Standards Committee decided this item on Monday 26 July 2021. Below is the council's own wording, with the papers it was decided on.

Item66

Resolved

Resolved : that the Committee notes: (a) There are no overdue risk reviews during Quarter 4; (b) There are 10 overdue risk reviews during Quarter 1; (c) There were no risk level increases during Quarter 4; (d) There were no risk level increases during Quarter 1; (e) There were 2 new identified risks during Quarter 4; (f) There was one new risk identified during Quarter 1; (g) The updated corporate risks were set out in Appendix A; and (h) Identifies Walleys Quarry as the risk profile to be subject to detailed scrutiny at the next meeting.
Word for word from the decision Newcastle-under-Lyme published for this meeting. Source: moderngov.newcastle-staffs.gov.uk

Follow this further

Built from Newcastle-under-Lyme's papers

What the report saysPro

Report to Audit and Standards Committee

Purpose of the report

To inform Members of the progress made by the Council in enhancing and embedding risk management for the period January to March 2021 (Q4 (2020/21)) and April to June 2021 (Q1 (2021/22)) including progress made in managing identified corporate risks.

To ask members to recognise that risk likelihood can be mitigated but the risk impact may not change.

Recommendation

The Committee is asked to:- (a) Note that there are no overdue risk reviews during Q4 (point 2.1.1).

(b) Note that there are 10 overdue risk reviews during Q1 (point 2.1.2).

(c) Note that there were no risk level increases during Q4 (point 2.2.1).

(d) Note that there were no risk level increases during Q1 (point 2.2.2).

(e) Note that there were 2 new identified risks during Q4 (point 2.2.3).

(f) Note that there was 1 new risk identified during Q1 (point 2.2.4).

(g) Note Appendix A – update on the corporate risks (point 2.2.5).

(h) Identify, as appropriate, individual risk profiles to be scrutinised in more detail at the next meeting of the Committee.

Reasons

The risk management process adopted by the Council has been reviewed to incorporate changes in the way the Council works and to provide continuity and streamlined reporting of

Classification: NULBC UNCLASSIFIED Classification: NULBC UNCLASSIFIED

risks to allow the process to become further embedded at each level of the authority. This will also aid the identification of key risks that potentially threaten the delivery of the Council’s corporate priorities. The Risk Management Strategy provides a formal and proportionate framework to manage these identified risks and thus reduce the Council’s exposure.

Background

1.1The Council monitors and manages all its risks through the various risk profiles contained within GRACE (Governance Risk and Control Environment) – the Council’s software used to record and manage risks.

1.2The Council currently reviews its high (red 9) risks at least monthly and its medium (amber) risks at least quarterly.

1.3The last review of these risks (Q3 2020/21) was reported to the Council’s Audit & Standards Committee on 08 February 2021.

1.4Risk owners are challenged by the Council’s Risk Champions in respect of the controls, further actions, ratings and emerging risks related to their risk profiles, and are also challenged on the reasons for inclusion or non-inclusion and amendments of these.

1.5Projects are managed to a high level in relation to risk and are reviewed in accordance with the Risk Management Strategy (i.e. at least monthly). Any specific projects, where required can also have their risks monitored, maintained and managed in the Project Board meetings, in line with whichever risk management process they wish to use – this will stop ‘double reporting’ and enable officers to manage the project risks accordingly, but escalating any requirements via the process in the Risk Management Strategy.

2. Issues

2.1Further to an Audit Assurance recommendation your officers have been asked to report on overdue risk reviews that are 6 months out of date.

2.1.1 At the time of running the report, there are no overdue risk reviews in Q4 (2020/21).

2.1.2 At the time of running the report, there are 10 overdue risk reviews in Q1 (2021/22). Five of these sit in Legal and Governance; 4 in Environmental Protection (however it has been noted that the responsible Officer is dealing with other urgent matters at this time – Walleys Quarry); and the last one is in the Asset Management Strategy risk profile.

2.1.3 In line with the risk management strategy the escalation process will be followed, until such time that involvement of this Committee is required.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Corporate Risks with heat map 26.07.21Appendix A 157 KB Download
PDF
QUARTER 4 2020/21 AND QUARTER 1 2021/22 CORPORATE RISK MANAGEMENT REPORTReport 509 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 18 attended
PW
Councillor Paul WaringChair, present
BP
Councillor Barry PanterVice-Chair, present
MH
Councillor Mark HollandCommittee Member, present
SD
Councillor Sylvia DymondCommittee Member, apologies, sent representative
SP
Councillor Sarah PickupCommittee Member, present
MS
Councillor Mike StubbsCommittee Member, absent
BP
Councillor Bert ProctorCommittee Member, apologies, sent representative
PB
Phil ButtersCo-Optee, apologies
AB
Annette BaileyOfficer, expected
GD
Geoff DurhamOfficer, expected
SS
Simon SowerbyOfficer, expected
GW
Councillor Gillian WilliamsSubstitute, present as substitute

All 18 on the meeting page

On this subject at Newcastle-under-Lyme

Search all
  1. QUARTER 4 2020/21 AND QUARTER 1 2021/22 CORPORATE RISK MANAGEMENT REPORTThis decision
  2. Financial and performance review report - fourth quarter 2025/26Noted
  3. Financial and performance review report - third quarter 2025/26Noted
  4. Financial and performance review report - third quarter 2025/26Noted
  5. Financial and performance review report - second quarter 2025-26Noted
  6. Corporate risk management report quarter 2 2025/26Noted

More from Newcastle-under-Lyme Audit and Standards Committee

All decisions
MeetingDecisionOutcome
29 Jun 2026 Minutes of previous meetingThat the minutes of the meeting held on 27 April, 2026 be agreed as a correct record. Agreed Open
29 Jun 2026 Proposed accounting policies & sources of estimation uncertainty 2025/26( i ) That the proposed Accounting Policies that will form part of the 2025/26 Statement of Accounts, be approved. (i... Approved Open
29 Jun 2026 Draft statement of accounts 2025/26( i ) That the General Fund outturn and key issues in respect of the Council’s financial position at 31 March 2026, b... Noted Open
29 Jun 2026 Annual governance statement 2025/26That the Annual Governance Statement for 2025/26, be approved. Watch the debate here Approved Open
29 Jun 2026 Treasury management annual report 2025/26That the Treasury Management Annual Report for 2025/26 be received, ahead of it being reported to Full Council on 30 ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies