(i) That the report be received. (ii) That the Head of Planning and Development Manager seeks to Maintain and improve performance of the Development Management team (including the technical support team) to meet the targets. (iii) That the ‘Mid-Year Development Management Performance Report 2022/23 be submitted to Committee reporting on performance achieved for the first half the complete year 2022/23. Watch the debate here
Word for word from the decision Newcastle-under-Lyme published for this meeting.Source: moderngov.newcastle-staffs.gov.uk
To provide members with an end of year report on the performance recorded for Development Management between 1st April 2021 and 31st March 2022. Figures for 2019/20 and 2020/21 are also provided for comparison as are targets set within the relevant Planning Service Plan.
Recommendations
(a) That the report be received.
(b) That the Head of Planning and Development Manager seeks to maintain and improve performance of the Development Management team (including the technical support team) to meet the targets.
(c) That the ‘Mid-Year Development Management Performance Report 2022/23 be submitted to Committee reporting on performance achieved for the first half the complete year 2022/23.
Reasons for recommendations
To ensure that appropriate monitoring and performance management procedures are in place and that the Council continues with its focus on improving performance, facilitating development and providing good customer service to all who use the Planning Service.
Background
This report is produced by the Head of Planning and Development Management Business Manager in consultation with the Portfolio Holder for Strategic Planning. An extensive set of indicators is collected to monitor the performance of the Development Management service. These indicators have changed over time and officers have sought to ensure that the right things are being measured to enable us to improve performance in every significant area.
The range of indicators included reflects the objective of providing a fast and efficient development management service including dealing with pre-application enquiries, breaches of planning control, considering applications, and approving subsequent details and delivering development.
2. Matters for consideration:
There is an Appendix attached to this report:-
APPENDIX 1: PERFORMANCE INDICATORS FOR DEVELOPMENT MANAGEMENT 2019/20, 2020/21 and 2021/22: Contains quarterly and annual figures for the Performance Indicators applicable during 2020/21 (comparative figures for 2019/20 and 2021/22 are also shown).
This report is a commentary on the local performance indicators that the Council has as set out in detail in Appendix 1. It follows on from a report that was considered by the Planning Committee at its meeting on the 1st March 2022 which reported on the mid-year performance figures and gave predictions on whether the targets for 2021/22 would be likely to be achieved.
The Council’s Cabinet receives a Quarterly Financial and Performance Management report on a series of performance indicators including those which relate to whether Major and Non-Major planning applications are being determined “in time”, and any indicators failing to meet the set targets are reported by exception. 3. The performance achieved:
National Performance Indicators
The Government has a system of designation of poorly performing planning authorities – two of the four current criteria for designation under ‘Special Measures’ are thresholds relating to the speed of determination of Major and Non-major applications, performance below which designation is likely. Designation as a poorly performing Local Planning Authority would have significant and adverse consequences for the Council.
The assessment period for this measure is the two years up to and including the most recent quarter for which data on planning application decisions are available at the time of designation.
The threshold for designation as an underperforming authority at the end of that reporting period for ‘Major’ applications is where the Council has failed to determine a minimum of 60% of its applications within a 13 week period or such longer period of time as might have been agreed with the applicant.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.