(i) Approves the principles of the scheme for play and recreational facilities at Bradwell Dingle (ii) Authorises officers to appoint a consultant to undertake further consultation, detailed design, and delivery of the project. (iii) Approves the use of the allocated £492,419.00 Section 106 funding for the delivery of the project. (iv) Delegates to the Service Director, Neighbourhood Delivery, to approve the detailed design in consultation with the Portfolio Holder for Sustainable Environment (v) Authorises officers to seek and accept the best value tender for the delivery of the project.
Word for word from the decision Newcastle-under-Lyme published for this meeting.Source: moderngov.newcastle-staffs.gov.uk
1) Approves the principles of the scheme for play and recreational facilities at Bradwell Dingle
2) Authorises officers to appoint a consultant to undertake further consultation, detailed design, and delivery of the project.
3) Approves the use of the allocated £492,419.00 Section 106 funding for the delivery of the project.
4) Delegates to the Service Director, Neighbourhood Delivery, to approve the detailed design in consultation with the Portfolio Holder for Sustainable Environment
5) Authorises officers to seek and accept the best value tender for the delivery of the project.
Reasons
To deliver play and recreational facility improvements to Bradwell Dingle in line with the needs of residents and users of the site.
Background
1.1Bradwell Dingle is a neighbourhood park within the Bradwell ward, which contains a range of play facilities, a multi-use games area and a kick-about area. Many of these facilities were last updated over 10 years ago.
1 1.2 Over several years, the skate equipment on Bradwell Dingle has deteriorated and this has led to the removal of these facilities A small amount of capital funding had previously been allocated to replace this equipment.
1.3Ward members and the Friends of Bradwell Dingle instigated a project to encompass the entire site, rather than just look to replace the skate park. A draft set of proposed facilities was agreed, and a consultation was undertaken with the wider community, the results of which were collated in the summer of 2023.
2. Issues
2.1From the consultation results, 97% of the consultees agreed that the facilities on the site should be improved and that 87% agreed with the draft set of proposed facilities for the site. In total 102 people responded to the consultation. The initial list of potential improvements for further consultation include:
Skate improvements/wheeled sports Improvements to existing Multi Use Games Area (MUGA) Community garden Play improvements CCTV Kickabout area improvements and possible creation of second kickabout area Outdoor gym kit
2.2Section 106 (S106) funds in the sum of £492,419 were secured in relation to the residential development of the Knype Way site, which is close to Bradwell Dingle. It is a requirement of the Section 106 agreement that the funds are to be specifically used to improve open space facilities at Bradwell Dingle. Since the consultation was undertaken, these funds have been received and will cover the costs of the proposed new facilities, including project management of the detailed design and implementation phase of the project.
2.3To enable the delivery of the project within available resources, it is proposed to engage consultants to refine the proposals, undertake a further consultation on the detailed plan, and for the consultant to tender and project manage the agreed scheme on site.
2.4The consultant will be required to undertake a further consultation with residents and users and a more targeted consultation with younger users of the site, to ensure that all users have a say in the proposed facilities for the site, and that the final scheme caters for as wide a range of needs as possible.
2.5Once the consultant is appointed and the consultation completed a final detailed design will be created, and it is proposed to approve this in consultation with the portfolio holder.
3.1Approval of the principles of the scheme for play and recreational facilities at Bradwell Dingle
2 3.2 Authority is given to officers to appoint a consultant to undertake further consultation, detailed design, and delivery of the project.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Local government reorganisation update(i) That the content of the letter from the Minister for Devolution received on 7 th September 2026, reviewing decisi...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.