AI summaryCabinet endorses detailed scheme for play and recreational improvements at Bradwell Dingle, with construction set to start in early 2026 within a £412,419 budget.
What happens nextTenders invited December 2025Construction to start January/February 2026
Who it affectsBradwell Dingle park usersResidents of Bradwell and wider community
What was decided
Cabinet endorsed the detailed scheme for improvements to play and recreational facilities at Bradwell Dingle. Report P2, 3.1
The Deputy Chief Executive, in consultation with the Portfolio Holder for Sustainable Environment, was authorised to award a consultancy contract for further consultation, detailed design and delivery of the project. Report P3, 3.2
Why
To deliver play and recreational facility improvements at Bradwell Dingle in line with the needs of residents and users of the site. Report P5, 4.1
Consultation over summer 2025 with 126 respondents showed strong support for a pump track, outdoor gym, community garden, new benches and improved accessibility. Report P14, P15, 2.1
What happens next
Tenders for the construction work will be invited and returned in December 2025, with work on site programmed to begin in January or February 2026. Report 1.2, 2.5
An estimated 18-week construction period is expected, with facilities opening for community use in May or June 2026. Report 1.2, 2.5
Further community engagement will take place in the form of a 'you said, we did' promotion of the final detailed scheme online. Report 2.3
The money
£412,419 Section 106 capital funding secured from the Knype Way development for open space improvements at Bradwell Dingle Report P7, 8.1
£365,980 Current estimated cost of the proposed scheme Report 2.4, 8.2
£404,830 Total of estimated scheme cost and consultancy, within the approved budget Report 8.2
Options considered
Chosen: Endorse the detailed scheme and authorise the consultancy contract award. Delivers improvements in line with resident and user needs identified through consultation Report P2, P3, P5, 4.1
Rejected: Various options for the range of play and recreational facilities. Considered and consulted on as part of the development of the project; the proposed scheme reflects the preferred outcomes Report 5.1
Implications
Equalities: No negative equality implications; improved facilities should improve access and usability of the site for users. Report 7.1
Legal: No legal or statutory implications arising from the report. Report 6.1, P32
Financial: Total estimated cost of £404,830 sits within the approved Section 106 budget of £412,419, with capacity for minor increases. Report 2.4, 8.2
Risk: Remaining risk is failure to complete construction on time and within budget, to be mitigated through robust tender evaluation, value engineering and contract management. Report 9.2
Who and where
Residents of Bradwell and the wider community who use the park Report P15, 2.1
Future community garden committee members (to be formed) Report P20
Timeline
10th September 2024: Cabinet approved the principle of the scheme and allocated Section 106 funding Report 1.1, P7, 13.1
16th July to 14th September 2025: Latest stage of consultation carried out with residents and the community Report P12, 2.1
December 2025: Tenders for construction due to be returned and evaluated Report 1.2
January/February 2026: Work on site programmed to commence Report 1.2, 2.5
May/June 2026: Improved facilities expected to be open for community use Report 1.2, 2.5
Plain English for the jargon
Section 106 Agreement: A planning obligation under which a developer provides funding or contributions towards infrastructure or services linked to a development.
Fields in Trust: A programme that protects green spaces for community use in perpetuity.
Pumptrack: A tarmac-surfaced circuit of bumps and turns that can be ridden by bikes, scooters or skateboards using a pumping motion.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5
Resolved
(i) That the report be received and the detailed scheme for improvements to play and recreational facilities at Bradwell Dingle be endorsed. (ii) That the Deputy Chief Executive in consultation with the Portfolio Holder for Sustainable Environment be authorised to award a consultancy contract to undertake further consultation, detailed design and delivery of the project.
Word for word from the decision Newcastle-under-Lyme published for this meeting.Source: moderngov.newcastle-staffs.gov.uk
1. Receives the report and endorses the detailed scheme for improvements to play and recreational facilities at Bradwell Dingle.
2. Authorises the Deputy Chief Executive in consultation with the Portfolio Holder for Sustainable Environment to award a consultancy contract to undertake further consultation, detailed design and delivery of the project.
Reasons
To deliver play and recreational facility improvements to Bradwell Dingle in line with the needs of residents and users of the site
Background
1.1At the meeting of 10th September 2024, Cabinet resolved to:
• Approve the principle of the scheme for play and recreational facilities at Bradwell Dingle • Authorise officers to appoint a consultant to undertake further consultation, detailed design, and delivery of the project • Approve the use of the allocated £412,419 Section 106 funding for the delivery of the project • Delegate to the Service Director – Neighbourhood Delivery to approve the detailed design in consultation with the Portfolio Holder for Sustainable Environment • Authorise officers to seek and accept the best value tender for the delivery of the project
1 Classification: OFFICIAL
1.2Since this time, a consultant has been appointed to progress the project and has completed the consultation and detailed design work. A tender package has also been prepared and tenders will be invited for the construction of the play and recreational facilities, which are due to be returned and evaluated in December 2025, with a view to commencing work on site in February 2026. The estimated contract period is 18 weeks with a view to the facilities being open for use in May/June 2026.
2. Issues
2.1The latest stage of consultation was carried out by the consultants over the summer of 2025 and reached out to local residents, ward members, the Friends of Bradwell Dingle and the wider community via an online survey and onsite engagement. The results were collated into a report which is attached to this report at Appendix 1, and informed the detailed design of the proposed scheme. The main themes are summarised as follows:
2.1.1 Between 16th July and 14th September 2025, Newcastle-under-Lyme Borough Council asked people for their views on proposed improvements to Bradwell Dingle. This involved an on-site consultation carried out by Awscape Ltd followed by an online consultation.
2.1.2 General Feedback
In total 126 people gave feedback on the proposals.
• 89% of those who responded live in Bradwell. Others live local to the area. • 43% of those who responded use the park on a daily basis with 27% on a weekly basis. • 67% of those who responded used the park for walking the dog, with 50% saying they use it for walking and exercise and 49% saying they use the play area. • On accessibility 81% of respondents said they found it easy to access. One in six (16 %) did not, stating gates are hard to open and access with pushchairs, gates not wheelchair friendly, paths and surfacing uneven. • 72% would like to see a new wheeled area with 77% opting for a pump track. • 84% of those who responded would like to see outdoor gym equipment. • 81% of those who responded would like to see a community garden. • 98% of those who responded would like to see new benches. • 84% of those who responded said they would like to see the community more involved in the park through organized projects.
People felt most positive about: • Changes to the park and facilities. • People being involved in the park and respecting the park. • A community space.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Local government reorganisation update(i) That the content of the letter from the Minister for Devolution received on 7 th September 2026, reviewing decisi...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.