CONTRACT AWARD FOR YORK PLACE

Noted Executive 1 paper

Cabinet noted this item on Tuesday 5 November 2024. Below is the council's own wording, with the papers it was decided on.

Item4

Resolved

(i) That the progress made to date by Capital & Centric on the York Place project in Newcastle Town Centre, be noted; (ii) That expenditure of up to £836,843, be approved, to develop the scheme to the end of RIBA Stage 4, for construction drawings, tender of a contractor, programme and agreement of a final project costs for the build out of the scheme to completion (subject to a separate Council approval at a future date); (iii) That the Deputy Chief Executive, in consultation with the Portfolio Holder for Finance, Town Centres and Growth, and Portfolio Holder for One Council, People and Partnerships, be authorised to progress legal agreements to enable the appointment of Capital&Centric under a Pre-Development Services Agreement (PDSA) for the development of the scheme through a direct award under the Pagabo Development Management Framework; (iv) That that the future submission of a separate Council Report for the final authorisation to award a construction contract for the build out of the scheme, be noted.
Word for word from the decision Newcastle-under-Lyme published for this meeting. Source: moderngov.newcastle-staffs.gov.uk

Follow this further

Built from Newcastle-under-Lyme's papers

What the report saysPro

Report to Cabinet

Recommendation

That Cabinet:

1. Notes the progress made to date by Capital&Centric on the York Place project in Newcastle Town Centre;

2. Approve expenditure of up to £836,843 to develop the scheme to the end of RIBA Stage 4, for construction drawings, tender of a contractor, programme and agreement of a final project costs for the build out of the scheme to completion (subject to a separate Council approval at a future date);

3. Authorise the Deputy Chief Executive, in consultation with the Portfolio Holder for Finance, Town Centres and Growth, and Portfolio Holder for One Council, People and Partnerships to progress legal agreements to enable the appointment of Capital&Centric under a Pre-Development Services Agreement (PDSA) for the development of the scheme through a direct award under the Pagabo Development Management Framework;

4. Note that the future submission of a separate Council Report for the final authorisation to award a construction contract for the build out of the scheme.

Reasons

The Council has been developing plans for several key sites across the Town Centre of Newcastle-under-Lyme as part of the Future High Street Fund and Town Deal Fund.

This report enables progress to be made on York Place.

Each of the individual town centre regeneration projects that have been subject to previous reports and approvals are now being taken through individual approval routes to allow the breakdown of projects into specific approvals / projects with stand-alone approvals as each project will eventually

1 be purchased by a Special Purpose Vehicle company as a stand-alone asset within Capital&Centric, as per their over-riding business model.

Background

1.1As reported to previous Cabinet meetings, the Council has secured Future High Street Fund and Town Deal Fund for the re-development of several key regeneration sites across the Town Centre. In September 2023 the Council appointed Capital&Centric to undertake feasibility studies for the re-development of the former York Place Shopping Centre and agreed in February 2024 that they would :-,

 Develop the scheme design and costs for York Place site to RIBA Stage 3, under an individual Pre-Development Services Agreement.  Manage the procurement and delivery of the re-development works at York Place including stripping out and retaining the concrete frame to suit the design for the overall scheme, again under an individual Pre-Development Services Agreement, which is now underway and will be complete shortly.  Submit a cost for the next stage of the design and cost development – that of RIBA Stage 4, for construction drawings, tender of a contractor, programme and agreement of a final project costs for the build out of the scheme to completion, for a subsequent Council approval to move to full build out.

1.2This incremental approach enables the Council to take a phased approach to the development, with cost certainty secured before progressing to the next stage.

1.3This report deals only with updating on progress to date across the site and securing commitment to progressing to RIBA Stage 4 designs and costs for York Place.

2. Update

Update on Current Position

2.1All of the tenants vacated the shopping centre by the end of February 2024 as planned. Some asbestos removal and survey work was undertaken in the months that followed whilst a demolition scope of works was drawn up and a price for the works sought through Capital&Centric.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CONTRACT AWARD FOR YORK PLACEReport 473 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 25 attended
ST
Councillor Simon TaggChair, present
SS
Councillor Stephen SweeneyVice-Chair, present
GH
Councillor Gill HeesomCommittee Member, present
AF
Councillor Andrew FearCommittee Member, present
CS
Councillor Craig SkeldingCommittee Member, present
DH
Councillor David HutchisonCommittee Member, present
GM
Gordon MoleOfficer, in attendance
SM
Simon McEnenyOfficer, in attendance
AH
Anthony HaroldOfficer, expected
SW
Sarah WilkesOfficer, in attendance
AB
Andrew BirdOfficer, expected
CJ
Craig JordanOfficer, expected

All 25 on the meeting page

On this subject at Newcastle-under-Lyme

Search all
  1. CONTRACT AWARD FOR YORK PLACEThis decision
  2. Approval for award of contract for h&s monitoringDecided
  3. Contract award for repairs to j2 main pool roofApproved
  4. Kidsgrove town deal update and contract awardsNoted
  5. Contract award for ryecroftNoted
  6. Contract award for astley placeApproved

More from Newcastle-under-Lyme Cabinet

All decisions
MeetingDecisionOutcome
15 Sep 2026 Minutes of previous meetingsThat the Minutes of the meeting held on the 4 August be agreed as a correct record. Agreed Open
15 Sep 2026 Walleys quarry odour updateThat the contents of the update report be noted. Noted Open
15 Sep 2026 Local government reorganisation update(i) That the content of the letter from the Minister for Devolution received on 7 th September 2026, reviewing decisi... Noted Open
15 Sep 2026 Recycling & waste re-routing(i) That the recycling and waste collection day changes for approximately 22,000 households in the south of the borou... Approved Open
15 Sep 2026 Improving safety and welfare infrastructure at knutton lane depot(i) That the works and budget necessary to refurbish and upgrade the Knutton Lane depot to improve health & safety we... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies