(i) That the progress made to date by Capital & Centric on the Midway Car Park project in Newcastle Town Centre, be noted; (ii) That expenditure of up to £854,117 be approved to develop the scheme to the end of RIBA Stage 4, for construction drawings, tender of a contractor, programme and agreement of a final project costs for the build out of the scheme to completion (subject to a separate Council approval at a future date); (iii) That the Deputy Chief Executive, in consultation with the Portfolio Holder for Finance, Town Centres and Growth, and Portfolio Holder for One Council, People and Partnerships be authorised to progress legal agreements to enable the appointment of Capital&Centric under a Pre-Development Services Agreement (PDSA) for the development of the scheme through a direct award under the Pagabo Development Management Framework; (iv) That the future submission of a separate Council Report for the final authorisation to award a construction contract for the build out of the scheme, be noted.
Word for word from the decision Newcastle-under-Lyme published for this meeting.Source: moderngov.newcastle-staffs.gov.uk
1. Notes the progress made to date by Capital&Centric on the Midway Car Park project in Newcastle Town Centre;
2. Approve expenditure of up to £854,117 to develop the scheme to the end of RIBA Stage 4, for construction drawings, tender of a contractor, programme and agreement of a final project costs for the build out of the scheme to completion (subject to a separate Council approval at a future date);
3. Authorise the Deputy Chief Executive, in consultation with the Portfolio Holder for Finance, Town Centres and Growth, and Portfolio Holder for One Council, People and Partnerships to progress legal agreements to enable the appointment of Capital&Centric under a Pre-Development Services Agreement (PDSA) for the development of the scheme through a direct award under the Pagabo Development Management Framework;
4. Note that the future submission of a separate Council Report for the final authorisation to award a construction contract for the build out of the scheme.
Reasons
The Council has been developing plans for several key sites across the Town Centre of Newcastle-under-Lyme as part of the Future High Street Fund and Town Deal Fund.
This report enables progress to be made across the Midway site.
Each of the individual town centre regeneration projects that have been subject to previous reports and approvals are now being taken through individual approval routes to allow the breakdown of projects into specific approvals / projects with stand-alone approvals as each project will eventually
1 be purchased by a Special Purpose Vehicle company as a stand-alone asset within Capital&Centric, as per their over-riding business model.
Background
1.1As reported to previous Cabinet meetings, the Council has secured Future High Street Fund and Town Deal Fund for the re-development of several key regeneration sites across the Town Centre. In September 2023 the Council appointed Capital&Centric to undertake feasibility studies for the re-development of the Midway Car Park and agreed in February 2024 that they would :-,
Develop the scheme design and costs for the Midway Car Park to RIBA Stage 3, under an individual Pre-Development Services Agreement. Submit a cost for the next stage of the design and cost development – that of RIBA Stage 4, for construction drawings, tender of a contractor, programme and agreement of a final project costs for the build out of the scheme to completion, for a subsequent Council approval to move to full build out.
1.2This incremental approach enables the Council to take a phased approach to the development, with cost certainty secured before progressing to the next stage.
1.3This report deals only with updating on progress to date across the site and securing commitment to progressing to RIBA Stage 4 designs and costs for Midway Car Park.
2. Update
Update on Current Position.
2.1The Midway Car park will close in late 2024 upon completion of the new Castle Car Park on The Ryecroft site. Morgan Sindall are due to complete the work by the end of 2024.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Local government reorganisation update(i) That the content of the letter from the Minister for Devolution received on 7 th September 2026, reviewing decisi...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.