Item5
Resolved
That the Service Director – Planning, be given the delegated authority - in consultation with the Chair to permit the application subject to the conditions listed below, once additional drainage information has been submitted and agreed with the Lead Local Flood Authority. ( i ) Time limit (ii) Approved plans (iii) Facing/roofing materials as set out in the application documents (iv) Construction of vehicular access (v) Surfacing/drainage of parking, turning and circulation areas (vi) Secure cycle shelter details (vii) Dust mitigation measures during demolition/construction works (viii) Construction hours (ix) Boundary treatments constructed in accordance with approved details (x) Construction environmental management plan (xi) Noise mitigation measures outlined in the Noise Impact Assessment (xii) Implementation of landscaping scheme (xiii) Habitat management plan Watch the debate here
Word for word from the decision Newcastle-under-Lyme published for this meeting.