Item5
Resolved
That the application be permitted, subject to the undermentioned conditions: (i) Standard time limits for submission of reserved matters and commencement of development (ii) Approved plans (iii) Contaminated land (iv) Construction Environmental Management Plan (v) Habitat and maintenance plan (vi) Surface water drainage scheme (vii) Works to be completed in accordance with recommendations of Ecological Appraisal (viii) Works to be completed in accordance with recommendations of Hydrological Report (ix) Works to be completed in accordance with recommendations of Botanical Report (x) Programme of archaeological mitigation Watch the debate here
Word for word from the decision Newcastle-under-Lyme published for this meeting.
Source: moderngov.newcastle-staffs.gov.uk