AI summaryCabinet agreed to start phase 1 of Lyme Park Countryside Park on the former Keele Golf Course, opening in late Spring 2026, with a free 2-hour car park subject to a Traffic Regulation Order consultation.
Written from the decision and the officer reportPDF Pro
OutcomeNotedTRO to be drafted for 2-hour free parking
MoneySection 106 funding identifiedCovers phase 1 works and master planning
What happens nextPhase 1a design work in September 2025TRO consultation to follow shortly
Who it affectsBorough residents and visitorsPlus Keele University staff and students parking nearby
What was decided
Cabinet agreed the three-phase timeline (short, medium and long term) for developing Lyme Park Countryside Park on the former Keele Golf Course. Report P2, 2.3
Cabinet supported starting phase 1 so the site can be operational from late Spring 2026, including refurbishing the existing car park, signage, gates, footpath clearance, seating, bins and water safety measures. Report P3, P17
Cabinet agreed to draft a Traffic Regulation Order 2025 Amendment to make the car park free with a 2-hour daily limit, and delegated adoption of the amendment to the Deputy Chief Executive in consultation with the Portfolio Holder for Finance, Town Centres and Growth, subject to consultation responses. Report P4, P19
Why
To create a new countryside park for the borough's residents and visitors on the former Keele Golf Course, following Cabinet approval in March 2025. Report 1.1, P8, 2.2
To protect the borough's green spaces and biodiversity infrastructure and to allow the site to develop alongside potential adjacent housing identified in the draft Local Plan. Report 2.3, 4.1
A 2-hour free parking limit is proposed to stop the car park being used all day by Keele University staff and students, and a TRO is needed for enforcement. Report P19
What happens next
Phase 1a: design and cost estimates for light-touch works in September and October 2025; tenders and quotations invited in November and December 2025; site work in January and February 2026; completion and soft launch in March and April 2026. Report P24
Phase 1b: prepare brief for master planning, ecological survey and tree survey from July to October 2025; commission awarded in January 2026; reports submitted in December 2026. Report P20, P24
Draft and consult on a Traffic Regulation Order 2025 Amendment so the car park restrictions are in place before the park opens. Report P19, 6.2
The money
£20k to £40k Estimated cost of master planning works, based on similar work at Bradwell Dingle and Clough Hall Park Report 8.2
£50k Estimate for phase 1a tree surveys and works, based on recent work at Clough Hall Report P50
£10k to £15k Likely cost of the phase 1 ecological survey Report P50
£80k Indicative cost of entrance works, gates, fences, seats, bins, signage and minor car park and footpath works, to be confirmed once quotes return Report 8.4
Section 106 funding Identified to cover the costs in paragraphs 8.1 to 8.4 for enhancement and maintenance of public open space Report 8.5
Options considered
Chosen: Develop Lyme Park Countryside Park on parts of the former Keele Golf Course. Cabinet agreed in March 2025 to create the park; this report agrees the three-phase timeline and starts phase 1 Report 5.1, P42, 2.2
Chosen: Two-hour free parking limit with no charges, enforced through a TRO. To prevent all-day parking by Keele University staff and students Report P19
Implications
Financial: Significant officer time needed, with phase 1 and master planning costs covered by Section 106 funding for public open space. No income is expected from car parking charges. Report 8.1, 8.2, 8.4, 8.5, 8.6
Legal: No legal or statutory implications at this stage, but planning and countryside park accreditation legislation will need to be considered later. A TRO Amendment must be drafted and consulted on to enable parking enforcement. Report 6.1, 6.2
Equalities: No equality issues identified at this stage; a full equality impact assessment will be required when detailed proposals are developed. Report 7.1, P45
Risk: No major risks identified at this stage. Phase 1 is dependent on capital funding being made available. Report 9.1
Staffing: Site management in phase 1 will be carried out by the Council's Streetscene service within existing resources, and TRO enforcement will use existing staffing. Report 8.6
Climate: The park contributes to the Council's open space, green infrastructure and Sustainable Environment Strategies, and supports the Sustainable One Council and net zero commitments. Report 11.1, P61
Keele University staff and students, whose parking behaviour the TRO is intended to manage Report P19
Timeline
September/October 2025: Phase 1a: prepare designs and cost estimates for light-touch works Report P24
July to October 2025: Phase 1b: prepare brief for master planning, ecological survey and tree survey Report P20, P24
November/December 2025: Invite tenders and quotations for phase 1a works; also quotations and tenders for the master planning commission Report P24
January 2026: Award the master planning, ecological survey and tree survey commission Report P24
January/February 2026: Phase 1a work on site Report P24
March/April 2026: Phase 1 completion and soft launch Report P24
Late Spring 2026: Lyme Park Countryside Park phase 1 operational Report P3, 2.5
December 2026: Master planning, ecological survey and tree survey reports submitted Report P24
January to March 2027: Phase 2: prepare brief, including community engagement, for management plan commission Report P29
December 2027: Phase 2 management plan commission report submitted Report P29
Long term (phase 3): Implementation of management plan and community engagement strategy, dependent on residential development timescales; costs and model unknown Report P33, P34
Plain English for the jargon
Traffic Regulation Order (TRO): A legal instrument used by the council to regulate traffic, including parking restrictions and enforcement.
MTFS: Medium Term Financial Strategy, the council's revenue budget planning framework.
Section 106: Planning obligation under section 106 of the Town and Country Planning Act used to secure developer contributions, here for public open space.
UNSDG: UN Sustainable Development Goals.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item4
Resolved
(i) That the contents of the report be noted and that the timeline for the three phases of development for the Lyme Park Countryside Park, be agreed. (ii) That the commencement of phase 1 in the creation of a Lyme Park Countryside Park to allow for the site to be operational from late Spring 2026, be supported. (iii) That it be agreed that a Traffic Regulation Order 2025 Amendment is drafted for consultation on the basis that the car park to serve the Lyme Park Countryside Park is free for a 2-hour limit per day, then subject to consultation comments that delegation is given to the Deputy Chief Executive in consultation with the Portfolio Holder for Finance, Town Centres and Growth to adopt the amendment.
Word for word from the decision Newcastle-under-Lyme published for this meeting.Source: moderngov.newcastle-staffs.gov.uk
1. Notes the contents of the report and agree the timeline for the three phases of development for the Lyme Park Countryside Park.
2. Supports the commencement of phase 1 in the creation of a Lyme Park Countryside Park to allow for the site to be operational from late Spring 2026.
3. Agrees that a Traffic Regulation Order 2025 Amendment is drafted for consultation on the basis that the car park to serve the Lyme Park Countryside Park is free for a 2-hour limit per day, then subject to consultation comments that delegation is given to the Deputy Chief Executive in consultation with the Portfolio Holder for Finance, Town Centres and Growth to adopt the amendment.
Reasons
In March 2025, Cabinet agreed to the creation of a Countryside Park as part of the larger development of the former Keele golf course being considered as part of the Councils emerging new Local Plan.
Background
1.1In March 2025 Cabinet approved the creation of a Countryside Park, to be known as Lyme Park Countryside Park on the former Keele Golf Course, with the following recommendations –
(i) That the development of a Lyme Park Countryside Park on land at Keele, be approved.
1 (ii) That the action detailed in the report to progress the project be implemented.
(iii) That the Portfolio holder for Sustainable Environment work with Officers on those actions and report back to Cabinet.
2. Progress to date
2.1This report provides progress on several of the actions agreed by Cabinet in March 2025.
2.2An officer working group has been set up and has been working up options for the creation of Lyme Park as a new Countryside Park for the enjoyment of residents and visitors to the borough.
2.3Practical achievement in the creation of the Lyme Park Countryside Park is best served in three phases, short, medium and long term. This allows the Lyme Park Countryside Park to develop taking account of potential adjacent housing developments identified in the Councils draft Local Plan.
2.4Details of each of the phases are given below –
Short Term – Phase 1
2.4.1 This initial phase of the Lyme Park Countryside Park will be delivered in spring 2026, on land under the ownership of the Council, and will involve refurbishment / improvements to the existing carpark (originally provided for the golf course) signage and gates to all access points onto the site, minor footpath clearance work, seating and bins and safety provisions to 3 areas of open water, i.e. lifebuoys and warning signage.
2.4.2 Management of the site at this stage will be undertaken by the Councils Streetscene service who will inspect and maintain infrastructure to ensure safety and enjoyment of the public. The site will be brought into the Councils existing Grassland Management Strategy which is now in its third phase, and the tree stock will be managed through the Council’s existing Tree Management Strategy. Costs for this stage will be met from the Council’s Capital programme and MTFS revenue budget.
2.4.3 Restrictions on the car park will need to be considered to avoid it being used as all day parking by Keele University staff and students. A limit of 2 hours is proposed with no charges. In order to make the car park operational with the options for enforcement, the car park will need to be incorporated into a Traffic Regulation Order. To do this there is a requirement for consultation. It is therefore recommended that this commences shortly in order that the processes can be completed prior to the park opening.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Local government reorganisation update(i) That the content of the letter from the Minister for Devolution received on 7 th September 2026, reviewing decisi...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.