AI summaryCabinet approved a revised £2.7m refurbishment of Kidsgrove train station, dropping plans for a larger car park that would have required £2m-£13m mining remediation.
Written from the decision and the officer reportPDF Pro
OutcomeNotedDeputy Chief Executive authorised to vary EMR grant
Money£2.7m estimated costWithin £3.45m Town Deal capital allocation
What happens nextDetailed design by May 2026Works from late 2026, completion late 2027
Who it affectsKidsgrove station usersPlus station adopter group of 12+ members
What was decided
Cabinet noted the current proposals for the Kidsgrove Station Project and the Government's funding simplification for Towns Deals. Report 5.1, 5.2
Cabinet recognised the strategic significance of investing in an improved train station facility for the Kidsgrove Town Deal and approved the revised scheme to progress. Report 5.3
The Deputy Chief Executive, in consultation with the Portfolio Holder for Finance, Town Centres and Growth, was authorised to vary the current Grant Funding Agreement with East Midlands Railway. Report P30
Why
The station refurbishment is a strategically important project in the Kidsgrove Town Deal Investment Plan, delivering objective 2 on a connected and accessible town centre. Report 6.1
Original proposals required costly ground investigation and mining remediation, with cost estimates of £2m to £13m, and no funding source is available for that work. Report 1.1, 7.1
Government funding simplification in September 2025 delegated Town Deal project approval to the local authority, removing the need for MHCLG sign off of the change. Report 1.4, P14, P15, 6.3
What happens next
The Council will agree a variation to the current funding agreement with East Midlands Railway, including amending the grant amount to £2.7m. Report 3.1, 10.2
East Midlands Railway and Network Rail will work together on detailed design, with progress reported to the Council, the Kidsgrove Town Deal Board and MHCLG. Report 3.1, 2.3
Detailed design is to be completed by May 2026, tendering by October 2026, refurbishment from late 2026 and completion by late 2027, within the March 2028 delivery deadline. Report P25, P14
The money
£2m to £13m Estimated cost of remediation of historic mining works Report 1.1
£3.45m Town Deal project capital allocation for the station Report 2.3
£2.7m Estimated cost of the revised scheme, including risk and optimism bias Report 2.3
£2,614 million Current grant funding agreement amount to be varied to £2.7m Report 10.2
Options considered
Chosen: Revised scheme avoiding ground investigation and mining remediation. Achieves many station improvement aspirations without costs beyond Town Deal funding Report 6.2, 2.1, P18, P19
Rejected: Original larger car park with full ground investigation and remediation. No funding available for the £2m-£13m remediation cost; MHCLG said doing GI without secured remediation funding would be fiscally irresponsible Report 7.1, 1.1, 1.2
Rejected: Not pursue improvements to the station and deliver alternative projects. Station upgrade is strategically important and no alternative funding is likely; users would be left with an out of date facility Report 7.2
Implications
Financial: Grant Funding Agreement with East Midlands Railway must be varied, with the amount changing from £2,614 million to £2.7m, still within the £3.45m Town Deal allocation. Report 10.1, 10.2
Legal: Council relies on the Local Government Act 2000 wellbeing powers and must ensure activities are legally and state aid compliant, with regard to the Public Sector Duty in the Equality Act 2010 and the Prudential Code. Report 8.1, 8.2, 8.3
Equalities: Refurbishment is intended to improve facilities for all users of the station, including new accessible toilets and added disabled parking bays. Report 9.1, P18, P19
Risk: Delivery depends on Network Rail confirming the works do not represent a significant change to ground loading levels, otherwise ground investigation could be triggered again. Report 11.1, 11.2
Climate: Works include air source heat pumps, solar panels, EV charging points and improved cycle storage, supporting sustainability objectives. Report P60, P58, P59
Who and where
Users of Kidsgrove train station Report 2.2, 7.2
Station adopter group with 12+ members using a new community space on Platform 2 Report P19
East Midlands Railway as delivery partner and grant recipient Report 1.2, 2.3, P30
Kidsgrove Town Deal Board overseeing Town Deal projects Report 1.2, 6.1
MHCLG as the former approver of Town Deal changes Report 1.2, 1.3, P15
Timeline
May 2025: Kidsgrove Town Deal Board agreed to reject options requiring ground investigation and asked EMR to find a solution Report 1.2
July 2025: Town Deal Board approved the Project Adjustment Request for the revised project Report 1.3
August 2025: Project Adjustment Request submitted to MHCLG Report 1.3
Sept 2025: Government funding simplification confirmed; Kidsgrove Town Deal Board updated on Network Rail design discussions Report 1.4, P25, 17.1
October 2025: Cabinet considered the revised project Report P25
May 2026: Joint development of detailed design to be completed Report P25
October 2026: Tendering of works to be completed Report P25
Late 2026: Station refurbishment works to commence Report P25
Late 2027: Project completion expected Report P25
March 2028: Extended Town Deal delivery deadline Report P14
Plain English for the jargon
GI: Ground investigation, surveys of soil and rock conditions
EMR: East Midlands Railway, the train operator and delivery partner
MHCLG: Ministry of Housing, Communities and Local Government
PAR: Project Adjustment Request, a formal change request to a Town Deal project
BCR: Benefit Cost Ratio, a measure of project value for money
S151 officer: The Council's statutory chief financial officer
Town Deal: Government regeneration funding programme for town centres
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8
Resolved
(i) That the current proposals for the Kidsgrove Station Project be noted. (ii) That the Government funding simplification for Towns Deals and the implications for projects currently in delivery be noted. (iii) That the strategic significance of investing in an improved train station facility at Kidsgrove for the delivery of Kidsgrove Town Deal and approves the revised scheme to progress be recognised. (iv) That the Deputy Chief Executive, in consultation with the Portfolio Holder, for Finance, Town Centres and Growth be authorised to vary the current Grant Funding Agreement with East Midlands Railway to enable the project to be delivered.
Word for word from the decision Newcastle-under-Lyme published for this meeting.Source: moderngov.newcastle-staffs.gov.uk
1. Notes the current proposals for the Kidsgrove Station Project.
2. Notes the Government funding simplification for Towns Deals and the implications for projects currently in delivery.
3. Recognises the strategic significance of investing in an improved train station facility at Kidsgrove for the delivery of Kidsgrove Town Deal and approves the revised scheme to progress.
4. Authorises the Deputy Chief Executive, in consultation with the Portfolio Holder, for Finance, Town Centres and Growth to vary the current Grant Funding Agreement with East Midlands Railway to enable the project to be delivered.
Reasons
To seek approval from Cabinet to progress the revised train station project in Kidsgrove, following a resolution by Kidsgrove Town Deal Board in July 2025 to proceed with the revised proposals for the project.
To outline the Government’s recent funding simplification for Town Deals, which delegates the decision-making process for Town Deal projects to a local level.
1 1. Background
1.1As reported to previous Cabinet meetings, the Council has secured Town Deal Funds for the redevelopment of Kidsgrove train station. Since submitting the business case, the Station project has been the subject of several revisions, primarily associated with need for costly ground investigation (GI) and subsequent mitigation. Most recent cost estimates produced in 2025 range from £2m to £13m for remediation. This was based on a number of modelled scenarios for the impact of historic mining works.
1.2Despite initial information that the GI could be carried out in good faith, even if funding for the mitigation was not available, following this updated cost estimate MHCLG confirmed that carrying out GI without secured remediation funding would be regarded as fiscally irresponsible. At its meeting of May 2025, Kidsgrove Town Deal Board therefore agreed to reject all options that required GI and East Midlands Railway (EMR) was tasked with finding a solution that would still deliver a refurbished station building but would not include any elements which triggered GI.
1.3This project change required the submission of a Project Adjustment Request (PAR) to MHCLG. However, because of a reduced scope which removed revenue generating areas, such as the expanded car park, the Benefit Cost Ratio (BCR) dropped from 1.5 to 0.9. At the stage of submission, a BCR below 1.2 would have required ministerial intervention to proceed and the project would need to be assessed as having strategic significance for delivery of Kidsgrove Town Deal. The PAR was approved by the Board in July 2025 and signed off by the Council’s S151 officer. It was submitted to MHCLG in August 2025.
1.4In Sept 2025, the Council received formal confirmation of the government’s funding simplification for Town Deals and Levelling Up funds, which are being combined into a Local Regeneration Fund. The main differences are:
• Significantly reduced reporting requirements. • Reducing the Project Adjustment Request process, giving greater powers and flexibility to local authorities to move funding between schemes (with sign off by S151 officer). • Simplified and combined payments at set intervals providing greater certainty for local authorities to plan. • An extension to the delivery deadline of March 2028.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Local government reorganisation update(i) That the content of the letter from the Minister for Devolution received on 7 th September 2026, reviewing decisi...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.