Resolved
Resolved : That the report on the delivery of the Town Deal and Future High Street Funds projects be noted. Watch the debate here
AI summaryNewcastle-under-Lyme scrutiny committee notes progress on Town Deal and Future High Street Fund projects, with £14.1m of the £23.6m Newcastle fund and £8.0m of the £16.9m Kidsgrove fund spent so far.
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
Resolved : That the report on the delivery of the Town Deal and Future High Street Funds projects be noted. Watch the debate here
That:-
1. Scrutiny Committee notes this report on the delivery of the Town Deal and Future High Street Funds projects.
Reasons
To update the Scrutiny Committee on the progress with the various projects that are being funded or part funded through the two Town Deals – Newcastle and Kidsgrove, and the Future High Street Funds for Newcastle Town Centre.
1.1As reported to previous Scrutiny meetings, the Council has secured Future High Street Funding and Town Deal Funds for the redevelopment of several key regeneration sites across the Town Centre and the wider Borough.
2. Updates
2.1Future High Street Fund
Work across this programme has now completed and the fund is spent. The current position regarding the projects that are following on from the funding as stand aloong projects is as follows:
2.1.1 Astley Place
Classification: NULBC UNCLASSIFIED Classification: NULBC UNCLASSIFIED
Capital&Centric and their contractor AC1 commenced works (November 2025) with the development due to be completed in January 2027 (13 month build period). Works are ongoing with drainage and concrete frame preparation works currently underway.
RyePark
2.1.2 McCarthy and Stone Residential Development
It is now anticipated that the works will commence in the summer of 2026 with completion in late 2027 to coincide with the adjacent Capital&Centric works.
2.1.3 Cap[ital &Centric Ryepark Development
Classification: NULBC UNCLASSIFIED Classification: NULBC UNCLASSIFIED
Capital&Centric have now appointed Henry Boot to undertake the Ryepark constructions works. Site clearance and ground works commenced in November 2025 and completion is expected in early 2028 (27 month build period). Drainage and foundation preparation works are currently underway.
Classification: NULBC UNCLASSIFIED Classification: NULBC UNCLASSIFIED
Classification: NULBC UNCLASSIFIED Classification: NULBC UNCLASSIFIED
2.2Newcastle Town Deal
2.2.1 Karparc As with the previous schemes noted above Capital&Centric have appointed Clegg Construction to undertake the works to this development. Works started in early November and will be completed by the summer of 2027 (18 month build period). Works underway include concrete ‘cut-out’ works and preparation for new lift and stairwells.
Classification: NULBC UNCLASSIFIED Classification: NULBC UNCLASSIFIED
‘Punching’ holes through structure for atrium along centre of the building
New void for new stairwell and lift shaft
Classification: NULBC UNCLASSIFIED Classification: NULBC UNCLASSIFIED
2.2.2 Knutton and Chesterton
Knutton
Aspire have commenced works on the residential development at High Street.
Classification: NULBC UNCLASSIFIED Classification: NULBC UNCLASSIFIED
Works on the former community centre site development by Aspire commenced with ground works in October 2025. Foundations have now been dug on most plots (see below).
The extension to the Enterprise Centre Is now complete and has been awaiting the connection to a sub-station before the units can be occupied. This connection is due to take place at the end of March 2026 so the units should be handed over for occupation after this.
The plans for a village hall have been adapted to incorporate new enterprise units with a community facility available for hire within the structure / development. The scope of the works has altered as no community group was identified to operate the new facility. The scheme is being priced up in order to give an indication to the Town Deal Board for its consideration later in the year.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
TOWN DEAL AND FUTURE HIGH STREET FUNDS UPDATEReport | 2.3 MB | DownloadRead as text |
Follow Finance, Assets & Performance Scrutiny Committee at Newcastle-under-Lyme and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Jul 2026 | Minutes of a previous meetingResolved : That the minutes of the meeting held on 26 th March 2026 be agreed as a true and accurate record. Watch th... | Agreed | Open |
| 2 Jul 2026 | Work programmeThat the work Programme be noted and the additions be received. Watch the debate here | Noted | Open |
| 26 Mar 2026 | Minutes of a previous meetingResolved : That the minutes of the meeting held on 15 th January 2026 be agreed as a true and accurate record. | Agreed | Open |
| 26 Mar 2026 | Financial and performance review report - third quarter 2025/26Resolved : That the contents of the report and appendices be noted and that the Council’s service and financial perfo... | Noted | Open |
| 26 Mar 2026 | Work programmeResolved : That the work programme be noted. Watch the debate here | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.