CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Newcastle-under-Lyme Borough Council
Finance, Assets & Performance Scrutiny Committee, Thursday 26 March 2026 at 7.00pm

TOWN DEAL AND FUTURE HIGH STREET FUNDS UPDATE

Noted Finance 1 paper

AI summaryNewcastle-under-Lyme scrutiny committee notes progress on Town Deal and Future High Street Fund projects, with £14.1m of the £23.6m Newcastle fund and £8.0m of the £16.9m Kidsgrove fund spent so far.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedNo new decisions required
MoneyTown Deal funds partly spent£14.1m of £23.6m Newcastle, £8.0m of £16.9m Kidsgrove
What happens nextFurther reports at future meetingsScrutiny to receive updates
Who it affectsBorough residents and businessesNewcastle and Kidsgrove town centres

What was decided

The committee noted the report on the delivery of the Town Deal and Future High Street Funds projects. Report P2

Why

To update the committee on progress with projects funded or part funded through the two Town Deals for Newcastle and Kidsgrove, and the Future High Street Fund for Newcastle Town Centre. Report P4, 1.1

To continue updating the committee on progress and issues surrounding the Future High Street Fund and Town Deal Fund projects. Report 4.1

What happens next

The committee will continue to receive further reports on the projects at subsequent meetings. Report 3.1

The Knutton village hall and community facility scheme will be priced up and considered by the Town Deal Board later in the year. Report P32

Planning permission will be sought for the adapted village hall development at Knutton now that a tenant is being secured. Report P34

The money

  • £11.0m Future High Streets Fund, all received and spent by 31 March 2025 Report 8.1
  • £23.6m Newcastle Town Deal award, all received Report 8.2
  • £14.1m Newcastle Town Deal spent to date Report 8.2
  • £16.9m Kidsgrove Town Deal award Report 8.3
  • £15.7m Kidsgrove Town Deal received to date Report 8.3
  • £8.0m Kidsgrove Town Deal spent to date Report 8.3

Options considered

  • Rejected: No options considered at this update. Not applicable: project options are detailed in separate Cabinet reports for each scheme Report 5.1

Implications

  • Legal: Activities must comply with the Local Government Act 2000, state aid rules, the Public Sector Duty of the Equality Act 2010, and the Prudential Code for Capital Finance in Local Authorities, with legal implications identified case by case. Report 6.1, 6.2, 6.3
  • Equalities: The development of these projects does not create any specific equality impacts. Report 7.1
  • Risk: Risk management is central to the Council's commercial approach, with all potential activities assessed under the corporate risk management framework. Report 9.1

Who and where

  • Newcastle town centre visitors, businesses and residents near the regeneration sites Report P11, P17, P21, P42
  • Knutton residents and future occupants of the new enterprise units and community facility Report P28, P30, P31, P32
  • Chesterton residents, including people aged over 55 on the Countryside development Report P36, P37
  • Kidsgrove residents, businesses and train station users Report P49, P50, P52, P57
  • Future users of the digital infrastructure, community learning hub and small scale enterprise units Report P46, P55, P57

Timeline

  • October 2025: Knutton High Street ground works commenced by Aspire Report P30
  • November 2025: Astley Place works commenced by Capital&Centric and AC1, due to complete January 2027 Report P11
  • Summer 2026: McCarthy and Stone residential works expected to commence, completing late 2027 Report P14
  • November 2025: Ryepark site clearance and ground works commenced, with early 2028 completion expected Report P17
  • Early November 2025: Karparc works started by Clegg Construction, due to complete by the summer of 2027 Report P21
  • End of March 2026: Sub-station connection expected, allowing the extended Enterprise Centre units to be occupied Report P31
  • Late 2025 to June 2026: Cross Street Chesterton Keon Homes phased handovers expected to complete Report P36
  • November 2026: Cross Street Countryside scheme of 39 social rented apartments and bungalows for over 55s expected to complete Report P37
  • Late 2026: Zanzibar Enterprise Units expected completion Report P39
  • Summer 2026: Digital infrastructure service expected to start operations after over 49,000m of cabling was laid Report P46

Plain English for the jargon

  • Future High Street Fund: Government funding awarded in June 2021 to support projects helping future economic growth in Newcastle town centre
  • Town Deal: Government funding programme covering Newcastle-under-Lyme and Kidsgrove regeneration projects
  • UNSDG: UN Sustainable Development Goals, which the projects help to realise
  • Public Sector Duty: Duty under the Equality Act 2010 that the Council must have regard to
  • Prudential Code: The Prudential Code for Capital Finance in Local Authorities, a framework the Council must follow
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5

Resolved

Resolved : That the report on the delivery of the Town Deal and Future High Street Funds projects be noted. Watch the debate here
Word for word from the decision Newcastle-under-Lyme published for this meeting. Source: moderngov.newcastle-staffs.gov.uk

Follow this further

Built from Newcastle-under-Lyme's papers

What the report saysPro

Report to Finance, Assets & Performance Scrutiny Committee

Recommendation

That:-

1. Scrutiny Committee notes this report on the delivery of the Town Deal and Future High Street Funds projects.

Reasons

To update the Scrutiny Committee on the progress with the various projects that are being funded or part funded through the two Town Deals – Newcastle and Kidsgrove, and the Future High Street Funds for Newcastle Town Centre.

Background

1.1As reported to previous Scrutiny meetings, the Council has secured Future High Street Funding and Town Deal Funds for the redevelopment of several key regeneration sites across the Town Centre and the wider Borough.

2. Updates

2.1Future High Street Fund

Work across this programme has now completed and the fund is spent. The current position regarding the projects that are following on from the funding as stand aloong projects is as follows:

2.1.1 Astley Place

Classification: NULBC UNCLASSIFIED Classification: NULBC UNCLASSIFIED

Capital&Centric and their contractor AC1 commenced works (November 2025) with the development due to be completed in January 2027 (13 month build period). Works are ongoing with drainage and concrete frame preparation works currently underway.

RyePark

2.1.2 McCarthy and Stone Residential Development

It is now anticipated that the works will commence in the summer of 2026 with completion in late 2027 to coincide with the adjacent Capital&Centric works.

2.1.3 Cap[ital &Centric Ryepark Development

Classification: NULBC UNCLASSIFIED Classification: NULBC UNCLASSIFIED

Capital&Centric have now appointed Henry Boot to undertake the Ryepark constructions works. Site clearance and ground works commenced in November 2025 and completion is expected in early 2028 (27 month build period). Drainage and foundation preparation works are currently underway.

Classification: NULBC UNCLASSIFIED Classification: NULBC UNCLASSIFIED

Classification: NULBC UNCLASSIFIED Classification: NULBC UNCLASSIFIED

2.2Newcastle Town Deal

2.2.1 Karparc As with the previous schemes noted above Capital&Centric have appointed Clegg Construction to undertake the works to this development. Works started in early November and will be completed by the summer of 2027 (18 month build period). Works underway include concrete ‘cut-out’ works and preparation for new lift and stairwells.

Classification: NULBC UNCLASSIFIED Classification: NULBC UNCLASSIFIED

‘Punching’ holes through structure for atrium along centre of the building

New void for new stairwell and lift shaft

Classification: NULBC UNCLASSIFIED Classification: NULBC UNCLASSIFIED

2.2.2 Knutton and Chesterton

Knutton

Aspire have commenced works on the residential development at High Street.

Classification: NULBC UNCLASSIFIED Classification: NULBC UNCLASSIFIED

Works on the former community centre site development by Aspire commenced with ground works in October 2025. Foundations have now been dug on most plots (see below).

The extension to the Enterprise Centre Is now complete and has been awaiting the connection to a sub-station before the units can be occupied. This connection is due to take place at the end of March 2026 so the units should be handed over for occupation after this.

The plans for a village hall have been adapted to incorporate new enterprise units with a community facility available for hire within the structure / development. The scope of the works has altered as no community group was identified to operate the new facility. The scheme is being priced up in order to give an indication to the Town Deal Board for its consideration later in the year.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
TOWN DEAL AND FUTURE HIGH STREET FUNDS UPDATEReport 2.3 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 22 attended
MH
Councillor Mark HollandChair, present
AB
Councillor Amy BryanVice-Chair, expected
AP
Councillor Andrew ParkerCommittee Member, apologies, sent representative
AT
Councillor Andrew TurnockCommittee Member, present
PW
Councillor Paul WaringCommittee Member, present
M-
Mayor - Councillor Robert Bettley-SmithCommittee Member, apologies, sent representative
MS
Councillor Mike StubbsCommittee Member, present
DA
Councillor David AllportCommittee Member, apologies
AL
Councillor Annabel LawleyCommittee Member, apologies
DG
Councillor David GrocottCommittee Member, present
LD
Councillor Lynn DeanCommittee Member, apologies
DM
Deputy Mayoress. Councillor Susan BeestonSubstitute, present as substitute

All 22 on the meeting page

On this subject at Newcastle-under-Lyme

Search all
  1. TOWN DEAL AND FUTURE HIGH STREET FUNDS UPDATEThis decision
  2. Newcastle town dealNoted
  3. Kidsgrove towndealNoted
  4. Town deal and future high street funds updateNoted
  5. Town deal and future high street funds updateNoted
  6. Town deal and future high street funds updateNoted

More from Newcastle-under-Lyme Finance, Assets & Performance Scrutiny Committee

All decisions
MeetingDecisionOutcome
2 Jul 2026 Minutes of a previous meetingResolved : That the minutes of the meeting held on 26 th March 2026 be agreed as a true and accurate record. Watch th... Agreed Open
2 Jul 2026 Work programmeThat the work Programme be noted and the additions be received. Watch the debate here Noted Open
26 Mar 2026 Minutes of a previous meetingResolved : That the minutes of the meeting held on 15 th January 2026 be agreed as a true and accurate record. Agreed Open
26 Mar 2026 Financial and performance review report - third quarter 2025/26Resolved : That the contents of the report and appendices be noted and that the Council’s service and financial perfo... Noted Open
26 Mar 2026 Work programmeResolved : That the work programme be noted. Watch the debate here Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies