Resolved
Resolved : That the report on the delivery of the Kidsgrove Town Deal Funds projects be noted. Watch the debate here
AI summaryScrutiny committee notes progress on Kidsgrove Town Deal projects, with £8.9m of £16.9m spent on station, enterprise units, highways and public realm works.
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
Resolved : That the report on the delivery of the Kidsgrove Town Deal Funds projects be noted. Watch the debate here
That:-
1. Scrutiny Committee notes this report on the delivery of the Kidsgrove Town Deal Funds projects
Reasons
To update the Scrutiny Committee on the progress with the various projects that are being funded or part funded through the Kidsgrove Town Deal.
1.1As reported to previous Scrutiny meetings, the Council has secured Future High Street Funding and Town Deal Funds for the redevelopment of several key regeneration sites across the Town Centre and the wider Borough including Kidsgrove.
2. Updates
2.1Kidsgrove Town Deal
Classification: NULBC UNCLASSIFIED Classification: NULBC UNCLASSIFIED
2.1.1 Chatterley Valley This was a contribution to essential infrastructure works to release development land at Chatterley Valley, working with Staffordshire County Council and developer, Harworth to bring this long-term vacant site into use for employment.
Town Deal element complete and Harworth, are due to commence the construction of the first ‘shed’ shortly.
2.1.2 Kidsgrove Train Station works
The previously reported issue with the costs of car park underpinning due to mine works underground have now been resolved and the Town Deal Board have agreed a revised scope of works to develop the station with a refurbishment to the existing buildings and car park works outside the area that has been indicated for underground mine remediation or the ‘underpinning zone’. Design and costing works for the development are now underway. East Midlands Railway are leading the project, which requires approval by Network Rail. Works are expected to take place in 2027.
Classification: NULBC UNCLASSIFIED Classification: NULBC UNCLASSIFIED
Proposed refurbishment at Kidsgrove Station
The works have been reduced in size to not include the vacant space to the right of the entrance bridge to the station car park due to the extent and unknown costs of ground remediation in this area.
2.1.3 Canal Pathways
Led by the Canal & River Trust, the aim was to improve the walking and cycle route through Kiddsgrove by improving the tow path from the lock adjacent to the Bluebell Pub through to the Harecastle Tunnel north tunnel entrance. Through resurfacing and stabilising the tow path, installation of solar lighting, vegetation management and new wayfinding signage. It has also renewed access points to the railway station and resurfaced the driveway to the tunnel entrance (from Fourth Avenue) to enable safe access by pedestrians and emergency vehicles.
Ongoing works include restoration work at the old Harecastle Tunnel entrance. Installation of interpretation boards, and safety improvement to the canal crossing at the tunnel entrance.
An extension to the scope, that was agreed by the Kidsgrove Town Deal Board, to enable improvements to a Public Right of Way on a path connecting the canal towpath with a nearby residential area is now complete.
Classification: NULBC UNCLASSIFIED Classification: NULBC UNCLASSIFIED
Works at Harecastle Tunnel
2.1.4 Shared Service Hub
The original project allocation was £6,183,000, covering delivery of the shared service hub alongside highways any public realm improvements. Following issues around deliverability of the original Shared Service Hub scheme following the covid pandemic, the Town Deal Board resolved to split the project out into separate elements, which are reported on below.
• Community Hub
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
KIDSGROVE TOWNDEALReport | 2.7 MB | DownloadRead as text |
Follow Economy and Place Scrutiny Committee at Newcastle-under-Lyme and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 18 Jun 2026 | Minutes of previous meetingResolved : That the minutes of the meeting held on 19 th March 2026 be agreed as true and accurate record. Watch the ... | Agreed | Open |
| 18 Jun 2026 | Newcastle town dealResolved : That the report on the delivery of the Newcastle Town Deal Funds projects and the three major town centre ... | Noted | Open |
| 18 Jun 2026 | Pride in placeResolved : That the verbal update be noted. Watch the debate here | Noted | Open |
| 18 Jun 2026 | Work programmeResolved : That the Work Programme be discussed. Watch the debate here | Decided | Open |
| 19 Mar 2026 | Minutes of previous meetingResolved : That the minutes of the meeting held on 15 th December 2025 be agreed as a true and accurate record. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.