Planning and Transport Strategy Committee, Thursday 25 September 2008 at 3.00pm

Minutes

Agreed Planning 2 papers

Planning and Transport Strategy Committee agreed this item on Thursday 25 September 2008. Below is the council's own wording, with the papers it was decided on.

Item3

Resolved

a) The minutes of the meeting held on 24 July 2008 were agreed as a correct record. b) The minutes of the meeting held on 10 September 2008 were agreed as a correct record.
Word for word from the decision Newcastle published for this meeting. Source: democracy.newcastle.gov.uk

Follow this further

Built from Newcastle's papers

What the report saysPro

Report to Planning and Transport Strategy Committee

Planning and Transport Strategy Committee 10 September 2008

(3.00 pm – 3.20 pm)

Present:

Councillor: Shipley (In the Chair)

Councillors: Faulkner, Shepherd, and Stokel-Walker

In Attendance: D Slater - Executive Director of Environment and Regeneration H Emms - Director of Strategic Housing, Planning and Transportation G Mansbridge - Housing Development Manager R Hibbert - Strategic Planning and Transportation E Burns - B.A.R.A. J Curran - Democratic Services

12 APOLOGIES FOR ABSENCE

Apologies for absence were received from Councillors Taylor and A Lower.

13 NEWCASTLEGATESHEAD GROWTH POINT: PROGRAMME OF DEVELOPMENT

Submitted: Report of the Director of Strategic Housing Planning and Transport (Copies attached to Official Minutes)

D Slater introduced the report explaining that NewcastleGateshead was declared one of 20 new Growth Point areas by the Housing Minister on the 16th July 2008 following an application for Growth Point status. This followed the announcement in the Housing Green Paper, “Homes of the Future; More Affordable More Sustainable”, extending the opportunity for Growth Points to the North of England for the first time. NewcastleGateshead was therefore eligible to bid for new capital investment via the Growth Fund and the Community Infrastructure Funds (CIF) for transport, transport services and other works. However the deadline for the CIF was extremely tight, with expressions of interest required by the 15 September 2008. This was the reason for the urgent meeting being convened today.

G Mansbridge outlined the context of this new initiative. There was recognition by Government that NewcastleGateshead had ambitious plans for growth and renewal which were already set out in the sustainable, Community Strategy and

D:\moderngov\data\published\Intranet\C00000139\M00000436\AI00003000\h1090820.doc 2

Regeneration Strategy. The next step would be to produce a Programme of Development (POD) He stressed that the Growth Fund was purely capital, to be used for transport and was time limited i.e. it had to be spent by the 31st March 2011.

R Hibbert then outlined the Six Proposed Priorities for the Expression of Interest to the Community Infrastructure Fund in detail, which were set out in detail, which were set out in the report.

Questions and Comments

Members raised the following questions/comments:-

• In response to a query, R Hibbert explained that each of the six priorities identified would cost in the region of £1/2 to £11/2 M. The total settlement was £3 M on average. The bid from NewcastleGateshead is expected to be around £5 -£6m.

• H Emms stressed that in putting together the six priorities, a lot of information and guidance had been studied in detail so that a bid could be put together within the time scale which officers felt was deliverable and had some future leverage, in that it could be delivered on time and work completely on programme.

• R Hibbert stressed that the priorities were listed in the report, but this was not in any preferential order. The prioritisation would be left to the DFT and DCLG to take a view.

• A Member felt that a lot of Government initiatives had been announced recently, but, they did not seem to be linked in any strategic way. H Emms stressed that the fact that the bid was aligned with other core strategies within the two authorities, meant that it had a better chance of success.

• D Slater assured Members that resources were adequate to carry out the proposed work and to put the bid together by 27th October. There could be resource issues to address if the bid proved unsuccessful.

• H Emms stressed that dialogue would be ongoing and this was essentially the start of a new process. There would be an evaluation process put in place.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
(h) 10.9.08 2Report 66 KB DownloadRead as text
PDF
MinutesMinutes 78 KB Download

At this meeting

Whole meeting

On this subject at Newcastle

Search all
  1. MinutesThis decision
  2. Public Minutes of previous meeting held on 20 July 2026Approved
  3. Minutes of Meeting held on 9 March 2026Agreed
  4. Public Minutes of previous meeting held on 16 March 2026Approved
  5. Public Minutes of previous meeting held on 12 January 2026Approved
  6. Public Minutes of previous meeting held on 14 October 2024Approved

More from Newcastle Planning and Transport Strategy Committee

All decisions
MeetingDecisionOutcome
26 Feb 2009 The East Pilgrim Street Regeneration Opportunity Area: Interim Planning GuidanceThe Committee agreed to endorse the draft IPG for publication and further consultation, subject to:- ( i ) clarificat... Agreed Open
26 Feb 2009 Heart of Walker: Supplementary Planning Document ( SDP)RESOLVED – That:- (i) the issues raised as part of the consultation process and the ongoing work to address the issue... Noted Open
22 Jan 2009 Draft Gosforth Conservation Area Management Plan-Supplementary Planning DocumentResolved that a) the draft Conservation Area Management Plan Supplementary Planning Document in relation to the Gosfo... Approved Open
22 Jan 2009 Draft Brandling Village and South Jesmond Conservation Area Management Plans, Development Guidance Notes (DNGs)Resolved that:- a) the draft Conservation Area Management Plan Development Guidance Note (CAMP DGN) in relation to th... Approved Open
25 Sep 2008 The Former Scottish and Newcastle Brewery (Science Central) MasterplanThe Committee agreed: a) to note the preliminary findings of the latest consultation exercise undertaken on 8 July 20... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies